EOP Flashcards
Which one of the following describes the signal that would have been generated when the reactor coolant system pressure lowers to 1800 psia?
A. Safety injection actuation signal
B. Main steam isolation signal
C. Recirculation actuation signal
D. Containment spray actuation signal
Answer: A
While you are performing Standard Appendix 64, the Control Room tells you that the Spray Pond water temperature is 63F. What additional actions are required, if any?
A. Place the appropriate train chiller in service.
B. No additional actions are required.
C. Place the opposite train chiller in service.
D. Throttle open the SDC HX bypass valve.
Answer: B
What potential impact could reverse fluid flow from a steam generator tube rupture to the RCS have on the RCS?
A. Potential dilution of the RCS boron concentration.
B. Corrosive damage to the fuel assembly cladding.
C. Taking the RCS solid and lifting the pressurizer safeties.
D. Excessive cooldown of the RCS.
Answer: A
Which one of the following is the basis for waiting until Hot leg temperature is less than 540°F when isolating a S/G with a SGTR?
A. Affected Steam Generator pressure is low enough to prevent lifting of the Steam Generator safety valves.
B. Differential pressure between the RCS and the affected Steam Generator can be minimized while still maintaining subcooling.
C. Affected Steam Generator pressure is less than the shutoff head of the High Pressure Safety Injection pumps in case the tube leak propagates.
D. Steam Generator pressure is sufficiently high to minimize the possible RCS boron dilution to an acceptable level during the RCS cooldown.
Answer: A
Given the following conditions: Tcold 210F. Pressurizer pressure 250 psi. Pressurizer level 50%. All rods inserted. No radiation monitors in alarm. Train “A” Shutdown Cooling is in service, “A” LPSI is the running pump. Essential bus PBB S04 is down powered for an electrical outage. Train “A” LTOP relief valve lifts to 100% open and will not reseat. A loss of offsite power occurs, diesel generator “A” trips on differential and is damaged. What safety functions are jeopardized?
A. HR, CI, CTPC.
B. IC, PC, CI.
C. IC, HR, CTPC.
D. MVAC, IC, HR.
Answer: D
A steam generator should be “bottled up” if it is expected to take longer than _________ minutes to recover feedwater.
A. 30
B. 15
C. 45
D. 60
Answer: B
During performance of Standard Appendix 64 for alignment of EW “A” to the SFP, the procedure requires throttling EW to obtain a flowrate of 16,600 - 16,800 gpm total flow. How do you know the flowrate while you are adjusting the valve?
A. The local SDC HX A low flow alarm will clear.
B. EWA-HCV-53 has local position indication corresponding to a flowrate of 16,700 gpm.
C. SDC HX A flowrate is provided locally next to EWA-HCV-53.
D. The control room will inform you based upon control room indication.
Answer: D
Unit 1 has experienced a reactor trip and a failure of NAN-S01 and NAN-S02 to fast bus transfer. The control room staff has implemented Standard Appendix 64, Align EW to SFP, and has directed performance of Attachment 64-B. Prior to adjustment of NCB-HCV-265 to achieve the required flowrate, you must first:
A. Unlock and adjust EWB-V044, “EC CHILLER B DISCHARGE ISOLATION” to obtain 740-780 gpm.
B. Ensure that Spray Pond A temperature is 65° or less.
C. Place NCN-FI-257, “FPHX B Outlet Flowmeter” in service.
D. Ensure that EW pump B is being powered by Diesel Generator B for fault protection.
Answer: C
What is the purpose of cooling down the RCS to a Thot of less than 540°F prior to isolating the affected SG in the SGTR ORP? This action ensures….
A. that the core heat removal safety function is met.
B. steam generator safety valves do not lift following SG isolation.
C. SBCVs 1007 and 1008 will not open when using the SBCS.
D. pressurizer safety valves do not lift following SG isolation.
Answer: B
While recovering from a loss of all feed event the following conditions exist: PZR level 71% and trending up. Letdown is isolated due to valve failure. No RCPs are running. NCW is not in service. S/G levels have been restored to 50% NR by manually operating AFA-P01. Choose which one of the following actions is correct for PZR level control in accordance with the EOPs.
A. Maintain Seal Injection and allow PZR to go solid.
B. Secure the charging pumps.
C. Commence a plant cooldown.
D. Isolate RCP seal bleedoff and secure the charging pumps.
Answer: C
During a Steam Generator Tube Rupture (SGTR) event, an RCS cooldown to Th (RCS hot leg temperature) less than 540°F before isolating the affected steam generator will prevent…
A. lifting the pressurizer safeties.
B. overfilling the affected steam generator.
C. further steam generator tube degradation.
D. lifting the main steam safeties.
Answer: D
The LOAF procedure can be exited once it has accomplished its purpose by satisfying ALL of the following:
A. All Safety Function Status Check acceptance criteria are being satisfied. An appropriate procedure to implement has been provided and administratively approved. A cooldown is required to meet Shutdown Cooling Entry conditions.
B. Pressurizer Pressure is 150 psia. RCS Temperature is 340 degrees F. All Safety Function Status Check acceptance criteria are being satisfied. An appropriate procedure to implement has been provided, although not administratively approved.
C. All Safety Function Status Check acceptance criteria are being satisfied. A determination has been made that cooldown will not be required and maintaining Mode 3 conditions is desired. An appropriate procedure to implement has been provided and administratively approved.
D. Pressurizer Pressure is 2000 psia. RCS Temperature is 350 degrees F. All Safety Function Status Check acceptance criteria are being satisfied. An appropriate procedure to implement has been provided and administratively approved.
Answer: C
Following a SGTR 6 hours ago on SG #2, conditions are as follows: RCS Thot is 325 degrees RCS Pressure is 700 psia SG #1 Pressure is 95 psia SG #2 Pressure is 700 psia RCPs 1A and 2A are running What should be performed at this time?
A. Commence a cooldown of SG #2
B. Place SDC into service
C. Secure RCPs 1A and 2A
D. Lower Pressurizer pressure to less than 400 psia
Answer: A
Given a steam generator tube rupture event, once a steam generator is isolated, what is the preferred method of reducing the RCS to Steam Generator leak rate?
A. Increase Steam Generator pressure by raising the Steam Bypass Control System setpoint.
B. Blowdown the Steam Generator to the main condenser.
C. Raise the Steam Generator level above the top of the tubes.
D. Reduce RCS pressure to within +/-50 psid of the affected Steam Generator.
Answer: D
Given the following plant conditions: The reactor is tripped following a Steam Generator Tube Rupture. RCS pressure is 895 psia. RCS subcooling is 55°F. Steam Generator #1 pressure is 890 psia. RU-4 in high alarm. Steam generator #1 is isolated. Steam generator #1 level is 78% NR and rising slowly. Steam generator #2 level is 50% NR and steady. WHICH ONE of the following is the preferred method to control level in the isolated steam generator?
A. Line-up high rate blowdown to the condenser from #1 steam generator.
B. Steam the #1 steam generator to atmosphere via the ADVs.
C. Lower RCS pressure below #1 steam generator pressure and allow backflow to the RCS.
D. Bypass the MSIV and steam the #1 steam generator to the condenser.
Answer: C
Which one of the following components is tripped to minimize heat input into the RCS after a Loss of All Feedwater?
A. Reactor Coolant Pumps.
B. Pressurizer heaters.
C. Charging pumps.
D. Heated junction thermocouples.
Answer: A
A major grid perturbation has occurred such that the site has experienced a complete de-energization of the switchyard, and subsequent reactor trips and blackout conditions. Standard Appendix 54 has been implemented and you are directed to perform Attachment 54-A, which accomplishes what function?
A. Energizes EF battery charger NKN-H21 from DG-A.
B. Energizes F battery charger NKN-H19 from the GTG.
C. Energizes EF battery charger NKN-H21 from the GTG.
D. Energizes F battery charger NKN-H19 from DG-B.
Answer: C
Given the following plant conditions: The reactor has been manually tripped. Pressurizer pressure is 1810 psia and slowly lowering. SPTA’s have been completed. All ESFAS systems are performing as designed. RCS subcooling is 20°F and slowly lowering. Containment temperature is 145°F. 4 RCP’s are running. The crew is required to…..
A. trip one RCP in each loop.
B. trip RCP’s 1A and 1B.
C. trip all four RCP’s.
D. trip all four RCP’s when subcooling is less than 0°F
Answer: C
Given the following conditions: The reactor has been manually tripped A small LOCA has occurred. The LOCA procedure has been implemented. Under what conditions would an operator be required to trip 2 RCP’s and under what conditions would an operator be required to trip all RCP’s?
A. actuation of CSAS and trip all RCPs on subcooled margin of less than 24 degrees.
B. actuation of MSIS and trip all RCPs on a loss of subcooling.
C. pressurizer pressure remaining below 1837 psia and trip all RCPs on subcooled margin of less than 24 degrees.
D. pressurizer pressure remaining below 1837 psia and trip all RCPs on a loss of seal injection flow.
Answer: C
Given the following plant conditions: The unit is at 100% power. It has been determined that a 150 gpm high pressure seal cooler leak exists. Before the affected HPSC is isolated, which one of the following describes the limitations on plant operation?
A. Nuclear cooling water flow to the affected RCP must be increased.
B. The plant must commence a normal shutdown within 72 hours.
C. The affected RCP must be stopped, resulting in a automatic trip.
D. The plant must be manually tripped and all RCP’s must be stopped.
Answer: D
Reflux boiling will be enhanced by raising…
A. pressurizer pressure from 750 to 850 psia.
B. RCS T-cold to >550°F.
C. PZR lever from 15 to 55%.
D. SG level from 10% to 50% N/R.
Answer: D
Given the following conditions: A hot leg break has occurred. All reactor coolant pumps are stopped. Representative core exit thermocouple temperature is 450°F. Maximum quadrant core exit thermocouple is 456°F. T-hot is 483°F and dropping. Pressurizer pressure is 610 psia. Containment temperature and pressure are 125°F and 2.0 psig. WHICH ONE of the following identify the condition of heat transfer in the reactor coolant system?
A. Saturated natural circulation (reflux boiling)
B. Saturated steaming through the break
C. Subcooled natural circulation
D. Subcooled natural circulation with localized flow blockage.
Answer: C
Given the following plant conditions: A LOCA occurred with the plant at 100% MOC. RCS pressure is currently 1860 psia. PZR level is 30% and stable. The leak rate was 135 gpm into containment when RCS pressure was 2250 psia. Subcooled margin is 48°F and stable. The reactor was manually tripped and SIAS/CIAS were manually initiated. No equipment is out of service Which one of the following describes the primary heat removal method that will be used during the cooldown? (assume the physical size of the RCS breach remains constant and CSAS does not actuate)
A. Reflux boiling
B. Forced circulation
C. HPSI injection
D. Subcooled natural circulation
Answer: B
Given the following plant conditions: A subcooled natural circulation cooldown is in progress following a small break LOCA in containment. Aux Spray is in use, lowering RCS pressure. Sub-Cooled Margin is 50°F and degrading slowly. Containment temperature is 120°. Pressurizer level is 45% and rising rapidly. HPSI is throttled. Reactor vessel head is reading 41%. The Control Room Staff should immediately…
A. open the reactor vessel head vents.
B. re-initiate full Safety Injection flow.
C. stop depressurizing the RCS.
D. exit LOCA and enter the functional recovery procedure.
Answer: C
Which one of the following most correctly describes plant conditions if the switchyard grid has de-energized, and remains so, and both diesel generators have started and are running and powering their respective 4.16kV AC class busses?
A. Loss of All Feedwater (LOAF)
B. Blackout (BO)
C. Loss of Power (LOP)
D. Loss of Offsite Power (LOOP)
Answer: D
Given the following conditions: The plant is operating at 100% power The normal supply breaker to PBA-S03 trips open. The “A” Emergency Diesel starts but does not supply power to PBA-S03. All other electric plant buses are energized and normal. Which one of the following events has occurred?
A. Loss of Offsite Power (LOOP)
B. Blackout (BO)
C. Loss of Power (LOP)
D. Loss of Forced Circulation (LOFC)
Answer: C
Which one of the following conditions currently exists if NAN-S01 and NAN-S02 are deengergized and PBA-S03 and PBB-S04 are energized from their respective Emergency Diesel Generators?
A. Loss of all Feedwater (LOAF)
B. Blackout (BO)
C. Loss of Power (LOP)
D. Loss of Offsite Power (LOOP)
Answer: D
Given the following conditions: The Unit 2 power uprate and SG replacement are complete. The plant is at 100% power. A loss of vacuum occurs. The crew enters the 40AO-9ZZ07, Loss of Vacuum AOP. The secondary operator is told to reduce turbine load using the load limit pot. When compared to Unit 1 and 3, what plant response should the secondary operator expect from the load limit potentiometer?
A. More responsive.
B. Less responsive.
C. The same response.
D. Same response in the throttling range but more responsive outside the throttling range.
Answer: A
You have been directed to perform Standard Appendix 54, Attachment 54-A. Which one of the following indicates the appendix or action that the control room operator must assure has been completed, prior to assigning you this attachment?
A. Standard Appendix 53.
B. Normal AHU’s for the Turbine Building must be stopped.
C. Standard Appendix 52.
D. NKN-D41 must be energized.
Answer: A
The number of starts for an electric motor in a given period of time should be limited because…
A. overheating of the windings can occur due to a high starting current.
B. rotor damage can occur due to excessive cyclic stresses on the shaft.
C. overheating of the windings can occur due to shorting within the stator.
D. rotor damage can occur due to excessive axial displacement of the shaft.
Answer: A
During performance of Standard Appendix 62, what is the time restriction for depressurizing the main generator of H2 during a loss of offsite power with a battery charger not restored to NKN-M46?
A. Within 7 hours of the loss of offsite power.
B. Prior to the stopping of the Main Turbine shaft rotation.
C. Prior to the stopping of both MFPT’s shaft rotation.
D. Within 4 hours of discovery of the power loss.
Answer: A
After reduction of H2 pressure in the Main Generator per Standard Appendix 62, when is the generator purged of residual hydrogen?
A. After power is restored to the CO2 vaporizer from NHN-M27.
B. As soon as possible after a 4.16 kV class bus is restored.
C. When the Main Generator hydrogen concentration is less than 50%.
D. Hydrogen purging is not required by this appendix.
Answer: A
While performing Standard Appendix 63-A, valve EWA-HCV-53 is required to be throttled to obtain adequate flow through the RCP seal coolers. How do you [as the assigned NLO] accomplish this?
A. The Control Room notifies you of adequate flow through the RCP seal coolers and Normal Chiller WCN-E01A.
B. The Control Room notifies you of the flowrate through the SDC Heat Exchanger.
C. You obtain the information from the flow indicator on the wall next to the valve.
D. The preset throttle value is obtained from SWMS prior to performing the appendix.
Answer: A
With the reactor at 100% power, what is the normal condition of the SIT outlet valves and why are they in that condition?
A. The valves are open and downpowered to maintain it as a passive system.
B. The valves are open and powered up to provide for rapid closure after a SIAS.
C. The valves are closed and powered up to allow the SIAS to automatically open the valves.
D. The valves are closed and downpowered to prevent voiding the RCS with nitrogen after a SIAS.
Answer: A
Given the following plant conditions: The reactor has tripped An ESD has occurred on SG # 2 SG # 2 has reached dryout conditions, The following indications are available: Loop 1 Tcold - 460°F Loop 1 Thot - 480°F Loop 2 Tcold - 448°F Loop 2 Thot - 476°F
Which one of the following pressures indicates the pressure that SG # 1 should be reduced to?
A. 466 psia
B. 414 psia
C. 545 psia
D. 566 psia
Answer: B
When cross-connecting Train “B” EW to NC in accordance with Standard Appendix 63, which one of the following valves is operated from the Control Room?
A. EWB-HCV-66, EW CROSS-TIE VLV TO NC
B. EWB-HCV-54, “B” SDCHX OUTLET ISOLATION
C. EWA-HCV-53, “A” SDCHX OUTLET ISOLATION
D. NCN-UV-99, NC CTMT HEADER RETURN
Answer: D
Given the following plant conditions: FRP is in progress. Main steam safety valve has failed open on SG #1. Prior to the trip, the following RMS alarms were alarming: RU-142 Channel 1 at 7.6 x 10+5 RU-142 Channel 2 at 8.2 x 10+5 RU-142 Channel 3 at 2.1 x 10+5 RU-142 Channel 4 at 9.1 x 10+4 Loss of the Grid. DG ‘A’ tripped on low lube oil pressure. PZR level is off scale low. SI flow is adequate. All other ESFAS systems operate as designed. Assuming no other events, which success path should be performed first?
A. HR-2, SG with SI.
B. HR-1, SG with no SI.
C. CI-1, Auto/man CTMT ISOL.
D. IC-2, SI.
Answer: C
Given the following conditions: The Unit 2 power uprate and SG replacement are complete. The plant is operating at 100% power Which AOP would be most impacted by operating in full arc admission when compared to the unit(s) operating in partial arc admission?
A. Control Room Fire, 40AO-9ZZ19
B. Loss of Letdown, 40AO-9ZZ05
C. Loss of Vacuum, 40AO-9ZZ07
D. Inadvertent PPS-ESFAS actuations, 40AO-9ZZ17
Answer: C
Given the following conditions: The Unit 2 power uprate and SG replacement are complete. The plant is at 100% power. Condenser vacuum begins to degrade The crew enters the Loss of Vacuum, 40AO9ZZ07, AOP. What plant response would be most affected in Unit 2 when compared to the other units?
A. Charging flow would be more responsive to Pressurizer level changes.
B. SBCVs 1007 & 1008 would be more responsive to thumbwheel changes.
C. Letdown would be more responsive to Pressurizer level changes.
D. Turbine power would be more responsive to load limit pot changes.
Answer: D
Given the following conditions: Unit 1 is operating in Mode 1. A Pressurizer Safety valve becomes inoperable. All other safety valves are operable. What actions (if any) are required per Technical Specifications?
A. No actions since the LCO is met.
B. Restore the safety valve to OPERABLE status in 15 minutes.
C. Restore the safety valve to OPERABLE status in 30 minutes.
D. Restore the safety valve to OPERABLE status in 1 hour.
Answer: B
Which ONE of the following Unit combinations can be simultaneously energized by the GTGs?
A. 1 and 3 only
B. 1 and 2; or 1 and 3
C. 1 and 2; or 2 and 3
D. 1 and 3; or 2 and 3
Answer: B
Which of the following actions taken in the Blackout ORP is designed to assist in preventing core uncovery?
A. Start a Gas Turbine Generator and energize PBA-S03 within one hour.
B. Maximize RCS cooldown and depressurization to minimize RCP seal leakage.
C. Commence cooldown and stabilize RCS pressure to maximize subcooling and maintain natural circulation.
D. Ensuring Core and RCS heat removal is maintained by use of AFN and Train “A” ADVs.
Answer: A
During an ESD, why should safety injection be throttled as soon as the throttle criteria is met?
A. Minimizes the possibility of pressurized thermal shock.
B. Prevents excessive cooldown.
C. Minimizes erosion damage to the injection valves.
D. Minimizes the time SI pumps are running on mini-flow.
Answer: A
Given the following plant conditions: The plant has tripped from 100% due to a large break LOCA in Containment. The crew has entered the LOCA EOP Containment pressure is 15 psig and stable. A LOOP has occurred. PBA-S03 has faulted. While the crew is performing the actions of the EOP, “B” CS pump trips due to a motor fault. Which of the following is true? The crew …
A. must leave the LOCA ORP because Inventory Control is not met.
B. may remain in the LOCA ORP as all SFSCs are still met.
C. must leave the LOCA EOP because CTPC is NOT met.
D. may remain in the LOCA ORP because no other EOP directly addresses this condition.
Answer: C
The control room staff is implementing Standard Appendix 42 to align the Aux Feedwater Pumps suction to the Reactor Makeup Water Tank. A potential for contamination of the CST exists due to:
A. the fact that the suction piping is normally vented back to the CST.
B. the Aux Feed Pump(s) recirculation flow remains aligned to the CST.
C. a gravity flow path that would exist between the RMWT and the CST when the RMWT suction valve(s) are opened.
D. failure of the auto-closure interlock of the mini-flow valves when the Aux Feedwater pumps are aligned to both the RMWT and the CST.
Answer: B
The Lower Mode Functional Recovery Procedure addresses three specific conditions or “sets” of Success Paths. Which one of the following correctly identifies those three “sets” of Success Paths?
A. LTOPs not in service, LTOPs in service, and Reactor Vessel Head Removed.
B. Pzr Filled, Pzr Drained, and Reactor Vessel Head Removed.
C. Pzr Manway On, Pzr Manway Off, and Reactor Vessel Head Removed.
D. Reactor Vessel Head Tensioned, Reactor Vessel Head Detensioned, and Reactor Vessel Head Removed.
Answer: C
Given the following conditions: An overcooling transient occurred which dropped plant temperature uncontrollably to 470°F. RCS temperature and pressure have been stablized on the left side of the 200°F subcooled line of Standard Appendix 2. Which of the following actions is appropriate?
A. Cool down and maintain RCS pressure constant.
B. Heat up and repressurize the RCS.
C. Cool down and repressurize the RCS.
D. Depressurize and maintain RCS temperature constant.
Answer: D
Given the following conditions: Rx tripped due to low RCS pressure The CRS has entered the LOCA procedure RCS is 40 degrees subcooled and stable The Emergency Coordinator has identified the following Emergency Action Levels as being exceeded RCS leakrate > 44 gpm (1-6) Rapid unexplained CTMT pressure decrease (1-10) Which one of the following correctly describes the required event classification?
A. General Emergency
B. Unusual Event
C. Alert
D. Site Area Emergency
Answer: D
Given the following plant conditions: An ESD has occurred due to a steam line break inside containment. The Operating crew has just entered in the ESD procedure. Containment pressure peaked and is stable at 9 psig Containment temperature is 186°F. PZR level is 12% and rising. RVUH is 100%. RCS subcooling is 112°F SG 1 is at 24% WR (increasing) and being fed from AFW at 505 gpm. SG 2 is below the indicated level. Both HPSI pumps are injecting into the RCS. Based on these conditions, the operator should…
A. throttle HPSI when PZR level reaches 15%.
B. throttle HPSI immediately.
C. maximize feedflow to SG 1.
D. maximize feedflow to SG 1 and throttle HPSI when PZR level reaches 15%.
Answer: A
Given the following conditions: A steam leak occurs in the Turbine Building. A manual reactor trip is initiated. The turbine trip isolates the steam leak. T-cold for both loops indicate 555°F. The crew is performing the SPTAs. SBCS is functioning properly. No ESFAS actuations have occured Based on these conditions, the Control Operator should…
A. allow the RCS to heat up to its normal post trip band of 560° to 570°F Tcold.
B. continue the cooldown to a Tcold of 500°F.
C. initiate an MSIS and stabilize temperature using ADVs.
D. stabilize RCS temperature at its present value with SBCS in manual.
Answer: A
The following plant conditions exist: Unit 3 tripped from 75% power An ESD has occurred on # 1 SG The CRS has directed stabilizing RCS temperature The following indications are available:
Loop 1 T-cold 401 degrees
Loop 1 T-hot 485 degrees
Loop 2 T-cold 450 degrees
Loop 2 T-hot 490 degrees
Which one of the following pressures indicates the value that # 2 SG pressure should be reduced to? A. 590 psia B. 620 psia C. 250 psia D. 420 psia
Answer: C
Given the following plant conditions: An ESD has occurred due to a steam line break inside containment. The Operating crew has just entered in the ESD procedure. Containment pressure peaked and is stable at 9 psig. Containment temperature is 160°F and lowering. PZR level is 34% and rising. RVUH is 100%. RCS subcooling is 112°F and increasing. SG 1 is at 24% WR, rising slowly and being fed from AFW at 505 gpm. SG 2 is below the indicated level and not being fed. Both HPSI pumps are injecting into the RCS. SG 1 indicates 300 gpm Steam Flow Which of the following identifies what operator actions are required?
A. Decrease SG 1 FW flow to
Answer: B
“Reactive Power” in an AC electrical circuit is that power that:
A. is lost in the circuit due to the resistance of the electrical conductors.
B. never leaves the source.
C. is consumed by the load(s) to produce heat, light or motion.
D. oscillates in the circuit and produces no useful work.
Answer: D
A ESD has occurred due to a steam line break on SG 2 inside containment. The operating crew is in the process of performing the SPTAs. Containment pressure is at 10 psig and rising. Containment temperature is in excess of 200°F. PZR level is 12% and rising. RCS temperature is rising. RCS subcooling is 112°F. SG 1 is at 45% WR and being feed from AFW at 300 gpm. HPSI flow to the RCS is acceptible per appendix 2. Based on these conditions, the operator should:
A. throttle HPSI immediately.
B. increase heat removal on SG 1 to stabilize Tc
C. Start all available charging pumps.
D. immediately reduce RCS pressure to lower subcooling to less than 100°F.
Answer: B