AOP Flashcards
Given the following plant conditions:
Unit 3 is operating at 100% rated power.
A loss of NKN-M46 occurs.
Which one of the following procedures should be used to address this event?
A. 40EP-9EO01, SPTAs
B. 40AO-9ZZ13, Loss of Class Instrument or Control Power
C. 40AO-9ZZ12, Degraded Electrical
D. 40AO-9ZZ14, Loss of Non-Class Instrument or Control Power
Answer: D
Given the following plant conditions: Unit is operating at 100% power. Regulating Group 5 is at 135" RRS selected to Control Channel #1. Control Channel #1 fails high. CEDMCS in Auto Sequential Which one of the following is correct? CEAs......
A. may withdraw a few steps.
B. may insert a few steps.
C. will not move due to an AMI.
D. will insert until CEDMCS is taken out of automatic.
Answer: B
Which one of the following describes the operation of AFN-P01 following a loss of PKA-D21 in which PKA-D21 can NOT be re-energized?
Control power must be shifted to the ‘A’ battery…
A. output to restore remote operation of both the breaker and suction valves.
B. output to restore remote operation of the breaker.
C. charger output to restore remote operation of the AFN-P01 breaker.
D. charger output to restore remote operation of both the breaker and suction valves.
Answer: C
Given the following Plant conditions:
The CRS has entered 40AO-9ZZ08 due to an unexpected load reduction.
Megawatts had been 1300 MW but is no longer stable.
Secondary Operator reports that Main Generator frequency is oscillating between 59.8 and 60.2 hertz.
All systems are in their normal configuration.
Which of the following actions should the CRS first direct:
A. Perform appendix I, placing Main Turbine in Standby
B. Shift Gennerex to DC control.
C. Verify RPCS in service then trip the Reactor.
D. Reduce the load limit potentiometer until the “LOAD Limiting” light is on.
Answer: D
Given the following conditions:
Unit 1 is operating at rated power when backpressure in the Main Condenser starts to rise.
Regulating Group 5 is at 135 inches.
Turbine load is being shifted to SBCS valve 1007 in an effort to stabilize backpressure causing first stage pressure to decrease with reactor power remaining constant.
If CEDMCS is left in AUTO SEQUENTIAL, the Operating Crew should expect CEAs to…
A. start stepping in.
B. start stepping out.
C. remain in their present position due to an AMI.
D. remain in their present position as long as load is being removed.
Answer: A
Which one of the following describes how RRS develops CEA motion demand?
A. Power error compensated by rate of change of temperature error signal.
B. Power error signal ONLY.
C. Temperature error ONLY.
D. Temperature error compensated by rate of change of power error signal.
Answer: D
Given the following conditions:
Group 5 CEAs are 140 inches withdrawn with CEDMCS in Auto sequential.
A Control Channel detector fails high. RRS is selected to the failed detector.
Which of the following describes the RRS response?
A. No CEA motion will occur due to an AMI being generated.
B. CEAs may insert a few steps due to the Rate of Change circuit sensing a power error.
C. No CEA motion will occur due to the Rate of Change circuit eliminating the effects of the instrument failure.
D. CEAs may attempt to withdraw a few steps due to the Rate of Change circuit sensing a power error.
Answer: B
Given the following conditions:
The plant is operating at 100% power.
A single NI control channel has failed to 0%.
With no operator actions, which of the following is true concerning the DFWCS?
A. There will be no effect on the plant.
B. S/G levels will rapidly increase.
C. The unit will go through feedwater swapover.
D. Both downcomers control valves will go closed.
Answer: A
40AO-9ZZ07, Loss of Condenser Vacuum, has been entered. The cause of the degradation of vacuum has been corrected. Condenser pressure is
Answer: B
Given the following plant conditions:
Unit 1 is operating at 100% power.
A Regulating Group 4 CEA drops to the bottom of the core. Based on these conditions, the operating crew must:
A. begin efforts to restore the CEA in 10 minutes.
B. have the CEA restored within 15 minutes.
C. be less than 80% power within 30 minutes.
D. begin a power reduction within 10 minutes.
Answer: D
Given the following plant conditions:
Loss of PKD-M44 How many ADV’s are available from the control room?
A. 2
B. 0
C. 1
D. 4
Answer: A
Given the following plant conditions:
Unit 1 is operating at rated power with all rods 150 inches withdrawn.
A Regulating Group 3 CEA slips to 135 inches withdrawn. Shortly after this, a Regulating Group 5 CEA drops to the bottom of the core.
Based on these conditions, the operating crew must:
A. monitor CPC DNBR and LPD margins to trip and trip the reactor if either one approaches its trip setpoint.
B. monitor CPC ASI and trip the reactor if it approaches +0.5.
C. reduce turbine load to maintain Tavg and Tref within 3°F of each other.
D. immediately trip the reactor.
Answer: D
Given the following conditions:
Unit 1 is operating at rated power.
A CREFAS is manually initiated with both trains of Control Room Essential AFUs running.
Window 7B01A “INST AIR SYSTEM TROUBLE” alarms. Instrument Air header pressure is noticed to be lowering.
If the air problem continues to degrade, the Control Room Essential AFUs….
A. will trip.
B. ventilation lineup will not change.
C. will lose cooling water.
D. outside air dampers will fail open.
Answer: B
Given the following conditions:
A large load rejection has resulted in a RPCB.
This load rejection was due to a spurious failure in the EHC system and did NOT result in a turbine trip.
The Operating Crew desires to pick up load on the Main Turbine.
RPCB has been taken to Test Reset and Auto Actuate Out of Service.
In order to accomplish this, the Secondary Operator must…
A. simply raise the setting of the LOAD LIMIT potentiometer, since the setting of this control follows the SETBACK and RUNBACK down.
B. reduce turbine load below 15% to clear the SETBACK, then raise load as desired using the LOAD LIMIT potentiometer.
C. first reduce the LOAD LIMIT potentiometer until the LOAD LIMITING light comes on, then pick up load as necessary.
D. perform this manipulation with the LOAD SET pushbutton since the LOAD LIMIT potentiometer is out of the circuit until the original (pre-rejection) load has been established.
Answer: C
A condenser tube rupture exists in Train “A” of the main condenser. The control room has directed an auxiliary operator to close the inlet isolation valve for Drawoff to the CST . This action by the auxiliary operator will…
A. isolate the make-up function from the condensate storage tank to the condenser hotwells.
B. slow the rate at which condenser hotwell levels are increasing.
C. prevent contamination of the condensate storage tank by isolating hotwell draw off.
D. prevent condensate pump LO-LO level trips after the circ water overboard valves are opened.
Answer: C
Given the following plant conditions:
The plant is operating at 100% power.
A large load reject occurs due to degraded vacuum in the condenser.
Hotwell level is 35 inches and holding steady.
Which one of the following actions will need to be performed?
A. Open at least one Main Feed Pump Mini-flow Valve.
B. Trip the Reactor.
C. Trip the Main Turbine.
D. Open the Hotwell Manual Makeup Isolation Valve(s).
Answer: D
Given the following plant conditions:
The plant is operating at 100% power.
Condenser pressure is increasing.
Hotwell level is 35 inches and decreasing slowly.
Which one of the following actions might the AO need to perform, if directed by the Control Room, and why?
A. Monitor the nitrogen storage tank level to ensure CST cover gas remains available.
B. Ensure the hotwell drawoff valve is open to maximize available water in the CST.
C. Open the manual makeup valves to the hotwell to prevent a condensate pump trip at 30 inches hotwell level.
D. Increase the amount of cooling tower makeup to ensure proper NPSH to the Circulating Water Pumps.
Answer: C
An Emergency Boration using a HPSI pump is in progress. What is the flowrate required for the HPSI pump if the emergency boration must continue for 2 hours?
A. 185 gpm
B. 75 gpm
C. 85 gpm
D. 225 gpm
Answer: D
Unit 1 is operating at rated power with ARO.
A Regulating Group 3 CEA (non twelve finger) slips to 138 inches withdrawn. A Regulating Group 5 CEA slips to 145 inches withdrawn. The operating crew is required by procedure to …
A. reduce turbine load to maintain Tave and Tref within 5 degrees of each other and reduce reactor power within 10 minutes.
B. trip the reactor and implement the SPTAs.
C. reduce turbine load to maintain Tave and Tref within 3 degrees of each other and reduce reactor power within 20 minutes.
D. reduce turbine load to maintain Tave and Tref within 3 degrees of each other and reduce reactor power within 10 minutes.
Answer: D
According to 40AO-9ZZ04, when Seal Injection is isolated to the RCPs while at power, you can expect…
A. HP Seal Cooler inlet and outlet temperatures will rise to between 200°F and 220°F while all other temperatures remain the same.
B. NO change in the RCP temperature indications.
C. HP Seal Cooler inlet temperature will rise to between 200°F and 220°F, all other temperatures should increase by about 70°F.
D. HP Seal Cooler inlet temperature will rise to between 200°F and 220°F while all other temperatures remain the same.
Answer: D
The reactor has tripped, Two CEA’s have stuck out and cannot be tripped, RCS pressure is 1600 psia and stable. Which of the following could be used to emergency borate the RCS?
1. HPSI 2. LPSI 3. CS 4. Charging
A. only 4
B. 1 and 4
C. only 1
D. 1 and 2
Answer: B
Unit 1 is at 80% power and dropped a 4 finger CEA.
Unit 2 is at 80% power and dropped a 12 finger CEA.
Assume that the CEAs remained misaligned. What would be the impact on the respective CEACs?
A. Both units will eventually trip due to a penalty factors ramping in over the next 6 hours.
B. Neither unit will trip based on these misaligned CEAs.
C. In Unit 1 the 4 finger CEA will effectively generate NO CEAC penalty factor, whereas in Unit 2, the 12 finger CEA will eventually trip the reactor due to a penalty factor ramping in.
D. In Unit 2, the 12 finger CEA will effectively generate NO CEAC penalty factor, whereas In Unit 1, the 4 finger CEA will eventually trip the reactor due to a penalty factor ramping in.
Answer: C
Unit 1 is operating at rated power at 200 EFPD. A condenser tube rupture occurs. The four available condensate demineralizers have been placed in service. CDN-PDV-195 is still open. SG Sodium, based on the inline monitor, indicates 800 ppb and rising rapidly. Based on these conditions, the operations crew should:
A. conduct a controlled downpower.
B. initiate a manual RPCB (LOFP).
C. trip the reactor and enter standard post trip actions.
D. take manual control of the controller in order to close CDN-PDV-195.
Answer: C
Unit 1 is operating at rated power. EW Train A is in the process of being aligned to NC due to a problem with both NCW pumps. Each RCP has about 375 gpm of cooling water flow indicated on B04. An Operator is standing by in the Train A SDC Heat Exchanger room to throttle the EW outlet of the SDC Heat Exchanger using EWA-HCV-53. Based on the above conditions, you should direct the Operator to throttle EWA-HCV-53:
A. open to increase the EW pump’s flowrate.
B. closed to divert more flow to the NCW system.
C. closed to reduce the heat load on the EW Heat Exchangers.
D. open to overcome the increased head loss that the NCW places on the EW system.
Answer: B