Schedule Flashcards
A __________ is waiting time inserted between activities, such as needing to wait three days after pouring concrete before constructing the frame for a house.
Lag
An activity must finish before the successor can start. This is the most commonly used relationship.
Finish-to-start (FS)
This technique involves creating detailed estimates for each part of an activity or work package. Doing this type of estimating well requires an accurate WBS. The estimates are then rolled up into control accounts and finally into an overall project estimate.
Bottom-Up Estimating
This type of dependency is inherent in the nature of the work or is required by a contract.
Mandatory dependency
This technique involves determining the longest duration path through the network diagram, the earliest and latest an activity can start, and the earliest and latest it can be completed.
Critical Path Method
This type of estimating is an adaptive technique that involves grouping items into similar cateogies or collecitons. One of the most important purposes is to make sure a story point unit remains consistent for all estimates over the duration on the project.
Affinity Estimating
The use of this formula gives stronger consideration to the most likely estimate. Deriver from the program evaluation and review technique (PERT), this technique uses a formula to create a weighted average for the work to be done. This method of estimating leverages the benefits of risk management in reducing the uncertainty of estimates.
Terms like “weighted” on the exam refer to beta distribution.
This technique involves adding or adjusting resources in or to compress the schedule while maintaining the original project scope.
Crashing
* Crashing always results in increased costs, and may increase risk. It trades time for money.
This is a high-level estimating approach that is used to do the initial estimates of the product features and user stories during the early stages of an adaptive project.
T-shirt Sizing
This technique involves taking critical path activites that were originally planned to be done one after another and doing them instead in parallel for some or all of their duration.
Fast Tracking
* Fast tracking often results in rework, usually increases risk, and requires more attention to communication.
A __________ may be used to indicate that an activity can start before its predecessor activity is completed.
Lead
This technique is a common way that agile teams come up with estimates for their user stories. Each participant receives a set of cards with numbers on them that represent the relative units that will be used for the estimates, such as story points.
Planning Poker
What are significant events within a project schedule that are not work activites and have no duration?
Milestones
What are the (6) processes of Schedule Management?
- Plan Schedule Management - Planning
- Define Activities - Planning
- Sequence Activities - Planning
- Estimate Activity Durations - Planning
- Develop Schedule - Planning
- Control Schedule - M&C
This technique uses computer software to simulate the outcome of a project, based on three-point estimates (optimistic, pessimistic, and most likely) for each activity and the network diagram.
Monte Carlo Analysis