Schedule Flashcards

1
Q

What is the purpose of the project schedule?

A

Provide a detailed plan for how and when the project will deliver the results defined in the scope

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

After your schedule is approved it is the what?

A

Schedule baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Why should the project schedule be flexible?

A

To adjust for knowledge gained
To increase your understanding of risks
To add value to activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the project schedule processes that make up project schedule management?

A
Estimate activity durations
Sequence activities 
Develop schedule
Define activities process
Plan schedule management
Control schedule
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are some trends and emerging practices in the project schedule management process?

A

Adaptive planning
Iterative scheduling with a backlog
On-demand scheduling

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is Iterative scheduling with a backlog?

A

A form of adaptive planning. A form of rolling wave planning that charts requirements that may be vague during the initial planning phase. Welcomes changes throughout development life cycle.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is on-demand scheduling?

A

A form of adaptive planning. Limits your project team’s work to balance demand against delivery. Pulls work from a backlog as resources become available. Utilizes on demand scheduling for projects that evolve the product incrementally

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are some tailoring considerations for the project schedule management process?

A

Life cycle approach
Resource availability
Project dimensions
Technology support

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are some key questions to ask when tailoring for project schedule management?

A

“What is the most appropriate life cycle approach that provides an appropriately detailed schedule?”
“What are the factors influencing durations (such as the correlation between available resources and their productivity)?”
“How will the presence of complexity, technological uncertainty, product novelty, pace, or progress tracking impact the desired level of control?”
“Is technology used to develop, record, transmit, receive, and store project schedule model information and it it readily accessible?”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How does a predictive life cycle approach project schedule management?

A

Develops long term roadmaps for many similar projects under one broad schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

How does an adaptive/agile life cycle approach project schedule management?

A

Uses short cycles to undertake work, review the results and adapt the schedule as needed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What does the plan schedule management process do?

A

It establishes policies, procedures, and documentation for planning, developing, managing, and controlling your project schedule.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What does the schedule management plan outline?

A

How you allocate resources and prioritize activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What documents can be affected by the schedule management plan?

A

Project management plan
Assumption log
Risk register
Lessons learned register

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are the inputs to the schedule management plan process?

A

Organizational process assets
Enterprise environmental factors
Project management plan
Project charter

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is the configuration management plan?

A

Describes the configurable items of the project, identifies items that will be updated so that the product of the project remains consistent.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What are the outputs to the schedule management plan process?

A

Schedule management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What are some tools and techniques for the schedule management plan process?

A

Expert judgement
Meetings
Data analysis (alternative analysis)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What is the purpose of the estimate activity durations process?

A

Creating duration estimates clarifies the time to complete an activity, monitor performance, and report delays. Establish deadlines and timeline.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What factors are there to consider in the estimate activity durations process?

A

Law of diminishing returns, number of resources, advances in technology, motivation of staff.

21
Q

What is analogous estimating?

A

Uses past data from a similar activity

22
Q

What is parametric estimating?

A

Uses a statistical relationship between historical data and other variables to calculate an estimate for activity parameters.

23
Q

What is three point estimating?

A

A formula to better estimate durations. tE=(tO+tM+tP)/3. Where M= most likely, O=optimistic, P=pessimistic, and E=Expected

24
Q

What is bottom up estimating?

A

Done by aggregating the lower-level components of the work breakdown structure. The work within the activity is decomposed into more detail. The detailed durations are estimated and then these estimates are summed up.

25
Q

What are inputs to the estimate activity durations process?

A

Project documents
Organizational process assets
Project management plan
Enterprise environmental factors

26
Q

What are outputs to the estimate activity durations process?

A

Project documents updates
Basis of estimates
Duration estimates

27
Q

What are tools and techniques for the estimate activity durations process?

A
Three point estimating
Bottom up estimating
Meetings
Expert judgement
Analogous estimating
Parametric estimating 
Data analysis
Decision making
28
Q

What is alternatives analysis?

A

Used to compare various levels of resource capability or skills, scheduling compression techniques, different physical tolls.

29
Q

What is reserve analysis?

A

Used to determine the amount of contingency and management reserves needed for the project. Also called schedule reserves, are put aside for known risks and account for schedule uncertainty.

30
Q

What is the purpose of the develop schedule process?

A

Create a schedule model with planned dates for completing activities. Helps analyze activity sequences, durations, resource requirements, and schedule constraints.

31
Q

What is the critical path method?

A

Used to estimate the least possible amount of time to complete a project and to determine the amount of flexibility within the schedule.

32
Q

Define float.

A

Flexibility

33
Q

How is the critical path method done?

A

First create the network diagram, then add a legend to each activity, performing a forward pass, and finishing with a backward pass

34
Q

What is resource optimization?

A

Used to adjust activities according to resource availability

35
Q

What is resource levelling?

A

Used when limits on the available resources is paramount. Adjustments are made to the project schedule according to resource availability and may affect the critical path.

36
Q

What is resource smoothing?

A

Used when the time constraint takes priority. The project’s critical path is not changed. Activities may only be delayed within their free and total float.

37
Q

What is schedule compression?

A

Technique to shorten or accelerate the schedule without reducing the project scope in order to meet constraints, imposed dates or other objectives.

38
Q

What is crashing?

A

Technique to shorten the schedule duration by adding resources

39
Q

What is fast tracking?

A

Technique in which activities or phases normally done in sequence are performed in parallel. May result in rework and increased risk.

40
Q

What are inputs to the develop schedule process?

A
Agreements
Enterprise environmental factors
Organizational process assets
Project documents
Project management plan
41
Q

What are outputs to the develop schedule process?

A
Project management plan updates
Project documents updates
Project calendars
Schedule data
Project schedule 
Schedule baseline
Change requests
42
Q

What are tools and techniques used for the develop schedule process?

A
Resource optimization
Project management information systems
Schedule compression
Leads and lags
Schedule network analysis
Critical path method
Data analysis
Agile release planning
43
Q

What is the purpose of the control schedule process?

A

Allows you to create work performance information, schedule forecasts, and make changes and updates to existing documents

44
Q

What are the inputs to the control schedule process?

A

Work performance data
Project documents
Project management plan
Organizational process assets

45
Q

What are the outputs to the control schedule process?

A
Project documents updates
Work performance information
Schedule forecasts
Change requests
Project management plan updates
46
Q

What are tools and techniques used in the control schedule process?

A
Project management information system
Data analysis
Critical path method
Schedule compression
Resource optimization
Leads and lags
47
Q

What is earned value analysis?

A

When schedule performance measurements are used to compare the current project work to the original schedule baseline

48
Q

What is the iteration burndown chart?

A

Tracks the work that remains in the iteration backlog. It includes lines that represent the ideal remaining work, the actual remaining work, and the forecasted remaining work.

49
Q

What is variance analysis?

A

Looks at planned versus actual variances in the schedule