Risk Flashcards

1
Q

Monitor Risks Key Inputs

A

Work Performance data

Work Performance Reports

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is Risk Mgmt

A
Conducting risk mgmt
    Planning
    Identification
    Analysis
    Response Planning
    Response Implementation
    Monitoring risk
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the processes of Risk Mgmt

A
  1. Plan Risk Mgmt
  2. Identify Risks
  3. Perform QUALITATIVE risk Analysis
  4. Perform QUANTITATIVE Risk Analysis
  5. Plan Risk Responses
  6. Implement risk responses
  7. Monitor Risks
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is plan risk Mgmt

A

How to conduct risk mgmt activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is Identify Risks

A

Identifying Individual and overall project risks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is Perform QUALITATIVE Risk Analysis

A

Prioritizing INDIVIDUAL risks

probability of impact

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What QUANTITATIVE Risk Analysis

A

Numerically analysis

Combined effect of INDIVIDUAL risks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is “Plan Risk Responses”

A
Options
Strategies
Agreeing 
Overall risk exposure
Treat INDIVIDUAL Risks
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is “Monitor Risks”

A

Agreed upon risk response plans
tracking identifies risks
Analyzing new risks
Evaluating risk process efficacy

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Individual Project risk

A

Uncertain event or condition

+/- effect on project objectives

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Overall Project Risk

A

Uncertainty of whole project
From All sources of uncertainty and Individual Risks
Exposure of Stakeholders

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

When is risk first addressed

A

During project planning

Shapes project strategy

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Risk Thresholds

A

Measured

Reflect Stakeholder appetite

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are Non-event risks

A

Risks not considered

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Variability Risk

A

Uncertainty about some key characteristic

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Ambiguity Risk

A

Uncertainty about some future event

Monte Carlo

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Project Resilience

A

Unknowable-Unknowns
Can only be recognized after they occur
Need budget and schedule contingency
Need Flexible project processes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Integrated Risk Mgmt

A

Risks should be owned by program or portfolio as required

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Plan Risk Mgmt Tools and Techniques

A

MED
Meetings
Expert Judgement
Data Analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

When is Risk Mgmt Plan written

A

Plan Risk Mgmt

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Components of Risk Mgmt Plan

A
Risk Strategy
Methodology
Roles and Responsibilities
Funding (inc. Funding and Mgmt Reserve)
Timing
Risk Categories
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Risk Breakdown structure

A

Hierarchical representation of sources of risk
Major Categories; e.g. Technical, External
Considers full range of sources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

How should stakeholder appetites be reflected

A

Measurable risk thresholds

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Definitions of levels of risk probability and impacts

A

Number of levels reflect degree of detail

e.g. Scale (very high-Nil)
Probability (>70% - < 1%)
Time
Cost
Quality
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

Probability and Impact Matrix

A

Probability versus Impact chart

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

“Identify Risks” Tools and Techniques

A
P(R)IMED2
Prompt Lists
Interpersonal Skills
Meetings
Expert Judgement
Data Gathering
Data Analysis (e.g. SWOT)

Prompt Lists

27
Q

Does “Identify Risks” consider both individual and overall project risk

A

Yes

28
Q

Requirements Mgmt Plan

A

Component of PMP

Describes how rqmts will be treated

29
Q

Key Inputs to “Identify Risks”

A
ABCS-PLAID -R2
Assumption Log
Baselines
Cost estimates
Stakeholder register
Procurement Documentation
Lesson Learned Register
Agreements (External Procurement of resources)
Issue Log
Duration estimates
Rqmts Mgmt Plan
Resource Rqmts
30
Q

Risk Report

A

Sources of OVERALL project risk

Summary information on individual project risks

31
Q

“Perform Qualitative Risk Analysis”

A

Process of prioritizing INDIVIDUAL project risks

32
Q

Perform Qualitative Risk Analysis Tools and Techniques

A
DIMER-D2
Data Analysis
Interpersonal skills
Meetings
Expert Judgement
Risk Categorization
Data Gathering
Data Representation
33
Q

Risk Categorization

A

Priority of INDIVIDUAL project risks
Probability
Impact
Assessments are subjective

34
Q

What are the components of “QUALITATIVE” data analysis

A

Risk Data Quality Assessment
Risk Probability and Impact assessment
Assessment of other risk parameters

35
Q

Urgency

A

Period of time to implement risk response

36
Q

Proximity

A

When will the risk have an impact

37
Q

Dormancy

A

How long after risk occurred will we know about it

38
Q

Manageability

A

How well risk owner can manage the TIME of a risk occurring and/or its impact

39
Q

Controllability

A

How well risk owner can control risk OUTCOME

40
Q

Detectability

A

How easily can we detect risk beginning to occur

41
Q

Connectivity

A

How is risk related to other INDIVIDUAL risks

42
Q

Strategic Impact

A

Can risk affect organization’s strategic goals

43
Q

Propinquity

A

How much a risk matters to more than one stakeholder

Propinquity is high if risk is very significant

44
Q

Probability and impact matrix

A

Grid for mapping probability of each occurrence and its outcome on X-Y graph

45
Q

Hierarchical Charts

A

e.g. Bubble charts for showing 3 dimensions of data

46
Q

Documents: Assumption Log

A

For QUALITATIVE risk analysis

47
Q

Documents: Risk Register

A

Updated with information for QUALITATIVE risk analysis

48
Q

Documents: Risk Report

A

Most important individual risks

Prioritized list of all identified risks and summary conclusion

49
Q

QUANTITATIVE risk analysis

A

Numerically analyzing combined effect of identified INDIVIDUAL risks and other sources of uncertainty

50
Q

QUANTITATIVE Tools and Techniques

A
D-DIRE
Data Analysis
   Simulation
   Sensitivity Analysis
   Decision Tree Analysis
   Influence Diagrams
Data Gathering
Interpersonal Skills
Representations of Uncertainty
Expert Judgement
51
Q

How are outputs of QUANTITATIVE risk analysis used

A

As inputs to “Plan Risk Responses”

52
Q

Project Documents

A
Basis of Estimates
Cost Estimates
Cost Forecasts
Duration estimates
Milestone list
53
Q

Why is Basis of estimates used

A

For variability model during a QUANTITATIVE risk analysis

54
Q

Why are cost forecasts used

A

EAC, ETC, BAC and TCPI may be compared to results of QUANTITATIVE risk analysis

55
Q

Why are Duration Estimates used

A

They provide the starting point from which schedule variability is evaluated

56
Q

What are Representations of Uncertainty

A

If Duration, Cost, or Resource rqmt is uncertain, use range of possible values modeled ads probability distribution

57
Q

How is probability distributions of Representations of Uncertainty represented?

A
Triangular
Normal
Lognormal
Beta, Uniform
Discrete
58
Q

How is sensitivity analysis used

A

What individual project risks or other sources of uncertainty could have the most impact

59
Q

Tornado Diagram

A

Bar chart

Shows correlation for each element of quantitative risk analysis model

60
Q

Decision Tree

A

Uses nodes and branches (e.g. Decision Node, Chance Node)

Shows net path value for each path

61
Q

Influence Diagrams

A

Shows decision making under uncertainty
Represent project risks as ranges of uncertainty
Monte Carlo Analysis

62
Q

QUANTITATIVE Outputs

A
Assessment of OVERALL risk exposure
Probabilistic Analysis
Prioritized risks
Trends
Recommended risk responses
63
Q

What is Risk Data Quality Assessment

A

Is risk data accurate and reliable?
Risk Probability and Impact assessment
Assessment of other risk parameters

64
Q

What are the components of data analysis for QUALITATIVE risk analysis

A

Simulation
Sensitivity Analysis
Decision Tree Analysis
Influence Diagrams