Cost Mgmt Flashcards
Earned Value
How much work has been completed as of today
Budget at Completion
What is the total budget for the project
Variance at Completion
How much do we expect to vary from the BAC (VAC=BAC-EAC)
Estimate to Complete
How much more (or less) do we need to spend over what we already have
Actual Cost
How much have we spent for the work completed
How much work was scheduled to be completed as of today
What is Planned Value
What is cost variance
The difference between the value of the work completed (EV) and the Actual Cost
Planned Value
How much work was scheduled to be completed today
“the difference between the the work completed and the work planned”
What is schedule variance
SV=EV - PV
The difference between the work completed and the the actual costs
What is cost variance
CV=EV - AC
Ratio of Earned Value to Actual Costs
Cost Efficiency
What is Cost Performance Index
CPI=EV/AC
What is Schedule Performance Index
Schedule efficiency
Ratio of value of the work completed to the The work scheduled to have been completed
SV=EV/PV
Budget Planned - Estimated Cost to complete
What is Variance at completion
VAC = BAC - EAC
Estimate at Completion
Expected Cost if Staying the Course: EAC = BAC/CPI If righting the Ship: AC - (BAC - EV) If dependent on CPI and SPI: EAC = (BAC-EV)/SPI*CPI
Estimate to Complete
The expected cost to finish the remaining work
ETC = EAC - AC
The ratio of the cost to finish the work, to the remaining budget where remaining budget can be the planned cost (BAC) or the Estimated Cost to complete the project (EAC)
What is TCPI
a measure of the cost performance that must be achieved with remaining resources
What is TCPI
a measure of the efficiency that must be maintained in order to complete the project
What is TCPI
What does a CPI < 1.0 tell us
Project over cost
What does a SPI < 1.0 tell us
Project behind schedule
What does a negative value of CV tell us
Project over cost
What does a positive value of SV tell us
Project ahead of schedule
What does a TCPI less than 1 tell us
Project EASIER to complete
Note difference integer value
Units of Measure
Agreed to units defined for each resource