Why is the CEA band widened from 500 pcm to 750 pcm for initial startup following a refuel?
Fuel performance uncertainties
NOTE: Also denotes when Mode 2 is declared (-750-initial and -500-subsequent refuels)
What are the sequence of events that occur during a RX startup (ZZ02/03)?
- RTCB closed
- RCS Boron at ECBC
- Shutdown and PSCEA’s withdrawn
- Reg Group CEA’s withdrawn as planned
- Criticality, RX Power held constant, data point taken
- High Log bypassed >1E-4%
- RX Power up to POAH
When CEA’s are below the PDIL’s, how do we determine the max magnitude of the next CEA withdrawal?
Select smaller of:
- 1/2 distance to criticality in PCM, based on most recent ACP
- The next targeted hold point
Below PDIL’s, what allows the next CEA withdrawal to the next hold point?
- Most recent ACP says RX will go Critical at a CEA position > than next hold point
- RX is known to be far from Critical, as evidence of 3-4 CR doublings on both SU channels
2 or more consecutive ACP’s on same power channel predict Criticality to occur BELOW the PDIL’s and we are currently < PDIL’s and ECRP position, what is done?
Trip RX, Ensure SDM per 3.1.2, Monitor RX Power, RX Engineering investigate
How is “Criticality” indicated during a startup?
By a steadily or exponentially increasing count rate/RX Power with NO CEA Motion (Power Rise/Time)
Who’s responsible to initially determine when Reactor is “critical”?
RO conducting the Startup (RX MGR then confirms)
If the Reactor goes CRITICAL while pulling Shutdown or PS CEA’s, what should occur?
Simultaneously, Trip the Reactor, Initiate emergency boration until adequate SDM, Perform SPTA’s
What are required actions if Reactor goes CRITICAL below the PDIL’s or ECRP (-500/-750 pcm)?
Trip the Reactor
Perform SPTA’s
Initiate emergency oration
What are the required actions if CEA withdrawal is STOPPED due to CR doubling during withdrawal to 1st or 2nd hold points?
Trip Reactor, Ensure adequate SDM, Monitor RX Power (ensure no increase), Direct RX ENGR to investigate
If CEA RG GRP 5 reaches 135” withdrawn and Reactor is still subcritical, what can be done?
Dilution
What is “proper overlap” between Startup and Log Safety Channels?
ONE Decade
When and why are Startup Channels turned off during a Reactor Startup?
1 x 10-4 CPS (When High CPS alarm received)
De-energized to protect from high flux
What are the guidelines to raise power to the POAH?
Don’t exceed 1 DPM SUR
Use CEA withdrawal to get to .1% power
Insert CEA once at POAH to stabilize power
If SBCS is in MANUAL during rise to POAH, what happens to RCS temperature?
Goes Off-Program HIGH