Quantification & Costing Level 2 Flashcards

1
Q

What can you tell me about order of cost estimates?

A
  • it’s a term used by the RICS under NRM 1
  • key purpose is to establish if the proposed project is affordable and if so, to set a realistic cost limit
  • it’s based on the employer’s requirements and is the initial phase of the costing process
  • usually completed using m2 areas or functional units
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What can you tell me about cost plans?

A
  • prepared by the cost consultant, provides an estimate of what the actual project cost is likely to be
  • it identifies the client’s agreed cost limit and how the money is allocated to the different parts of the project
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How did you carry out your cost plan in accordance with NRM 1?

A
  • metric measurement
  • measured internal walls and partitions in m2 in accordance with Group Element 2.7
  • measured wall and floor finishes in m2 in accordance with Group Element 3.1 and 3.2
  • measured shopfittings as Nr in accordance with Group Element 4.1
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

How do you compile unit rates?

A
  • considers labour, materials and plant
  • for .labour I established an all-in hourly rate which covers wages, overtime, holiday, sick pay, travel, tool allowance
  • for materials I considered supplier rate, transportation costs, storage costs & waste allowance
  • for plant I considered operating costs (fuel, operator wages) and fixed costs (purchase cost, maintenance, tax / insurance)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

When would you use a defined provisional sum? What did you use it for in your cost plan?

A
  • where design and specification is unknown but extent of works is known enough for programming and management
  • bespoke medicines cabinet
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

When would you use a undefined provisional sum? What did you use it for in your cost plan?

A
  • when design, specification and extent is unknown at date of contract
  • investigating a leak, repairing mould to ceiling
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is a bill of quantities?

A
  • a document prepared by the cost consultant that provides specific measured quantities of items of work identified by drawings
  • issued to tenderers for them to price
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How did you produce the bill of quantities in accordance with NRM 2?

A

Consisted of the following in accordance with NRM2:
- prelims
- measured works
- provisional sums for non-measurable works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the constituents of a cost plan according to NRM 1?

A

Works cost estimate:
- facilitating works
- building works
- prelims
- OH&P

Project / Design Team estimate:
- consultants fees
- MC pre-construction fees

Risk allowances estimate:
- design development risk
- construction risk
- employer change risk
- employer other risk

Tender inflation estimate

VAT Assessment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the base cost?

A

The total of:
- works cost estimate
- project / design team fee estimate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the cost limit?

A

Base cost plus risk allowances

How well did you know this?
1
Not at all
2
3
4
5
Perfectly