Contract Administration Level 1 Flashcards
Define a contract.
A contract is a legally binding promise by one party to fulfil an obligation to another party in return for consideration
Who are typically the two parties to a main building contract?
- Client / employer - this party requires the work to be carried out
- Principal / Main contractor - the party carries out the work for an agreed fee
What is a contract administrator?
The CA is NOT party to the principle building contract
They simply administer it on the clients behalf
They must remain impartial at all times and apply the ‘rules’ of the contract rather than favouring either party
What are some of the common contractual agreements and what are your views of them?
verbal agreement - unprofessional, risky with no evidence of agreement, often used on smaller projects, should be avoided at all costs
exchanging of letters - commonly used but inadequate with regards to agreement and control mechanisms, to be avoided at all costs
letters of intent - used as an interim contract to proceed before full contract is signed, can be used to provide an early start but ensure they contain all relevant info linked to the form of contract used
written form of contract - as produced by JCT or NEC for example, preferred method to form any building contract regardless of size or value
What are the main duties of the contract administrator?
Chairing the pre-contract meeting
Issuing instructions
Dealing with payment provisions
Managing change procedures
Involvement with dispute avoidance
Dealing with completion and possession issues
Issuing certificates
What are the key aspects of contract documentation?
The contract (agreement, conditions, name of parties and contract sum)
Drawings
Specification
Schedule of work
BOQ (or employers requirements and contractors proposals under D&B)
What are the key aspects which determine selection of a contract and why?
Value of work - higher value projects present more financial risk and require greater cost control measures such as a BOQ
Timescale - a longer contract period may create unavoidable changes affecting both parties e.g. legislation for the client and inflation for the contractor
Complexity of work - simplistic work (like decoration) requires limited specification and monitoring whereas complex work (like construction of a high spec new build property) requires far more design, planning and control on site
Specialist subcontractor work - subcontractors are likely to be required on most projects and the more complex projects will require detailed provisions for appointing and managing them
What are JCT contracts?
JCT is a standard form of contract; Joint Contracts Tribunal
There are 12 contracts within the JCT family, examples include:
Minor Works Building Contract
Standard Building Contract
Intermediate Building Contract
Design & Build Contract
When would you use a JCT Minor Works Contract?
Smaller, basic construction projects where works are of a simple nature
Where the procurement route is traditional
Where the client is responsible for design, however if the contractor is responsible for designing elements of the works then MWBC with contractors design should be used
When would you use the JCT Standard Building Contract?
Designed for large or complex projects where detailed contractual provisions are required
Where projects are procured via the traditional procurement route
Where the employer is carrying out the design, however there are provisions for ‘Contractors Designed Portion’
Works being carried out in sections
When would you use the JCT Intermediate Contract?
Construction projects involving all recognised industry trades / skills
Detailed contractual provisions are required but without complex building services or specialist work
Suitable for projects following the traditional procurement route
What are the NEC ECC contracts?
New Engineering Contracts - Engineering and Construction Contract
Suitable for any construction based contract between employer and contractor
Intended to be suitable to any sector within industry
PM assumes full responsibility on behalf of the employer and controls time and cost as an administrative function
Programme is a key contract document
Based on mutual trust and co-operation
Focuses on pro-active risk management
What are the 6 main options o NEC ECC?
A - priced contract with activity schedule
B - priced contract with BOQ
C - target contract with activity schedule
D - target contract with BOQ
E - cost-reimbursable contract
F - Management contract
Provide an overview of NEC Option A
Lump sum contract
payments are made against completion of activities on the activity schedule
suitable for traditional and D&B procurement routes
risk of carrying out the work at the agreed price is with the contractor
Provide an overview of NEC Option B?
Priced contract with BOQ
contractor is entitled to payment via interim payments as a % of each BOQ line with the contract payment schedule
Risk of carrying out work at the agreed price is with the contractor
Provide an overview of NEC Option C?
target cost contract with activity schedule
financial risk is shared between employer and contractor at an agreed proportion
motivates contractor to deliver works in the most cost-efficient way
Provide an overview of NEC Option D
Target cost set by BOQ
Financial risks are shared at an agreed proportion between client and contractor
Provide an overview of NEC Option E
Reimbursable contract, often referred to as cost plus
Employer largely takes on the financial risk as the contractor is reimbursed their actual costs plus an agreed OH&P %
Might be used where the scope of works cannot be defined at the outset such as emergency work
Provide an overview of NEC Option F
Cost reimbursable / cost plus contract
Suited to the MC procurement route so the works are designed and construction by multiple subcontractors who are contracted to the management contractor
MC is responsible for the work and paid a fee
Risk is largely taken by the client
Under JCT, who takes on the role of contract administrator?
Historically and traditionally been the architect
The JCT form refers to ‘architect / contract administrator’
The scope of who can be the CA has widened to include building surveyors, quantity surveyors, management surveyors and engineers’
Under NEC, who takes on the role of the contract administrator?
NEC does not refer to a contract administrator as the project manager is the focal point of the project
Essentially, the PM controls the contract as an administrative function
Under FIDIC, who takes on the role of the contract administrator?
The Engineer
With reference to JCT MW Contract, provide an overview of the contract booklet.
Articles of agreement - identifies the key parties to the contract and other stakeholders
Contract particulars - contains all important contract clauses covering items such as carrying out the works, control of the works, payment, injury, damage and insurance, termination and disputes
Section 2: Carrying out the works - contractors obligations, possession of site, errors, discrepancies and divergencies, extensions of time, practical completion, liquidated damages, defects, certificate of making good and contractors programme
Section 3: control of the works - person in charge, assignment / sub-letting, CA instructions, provisional sum, CDM regs, contract instructions
Section 4: payment - Contract sum, payment certificates, retention, payment terms
Section 5: injury, damage and insurance - outlines contractors liabilities re insurance provisions during contract period
Section 6: termination - covers conditions under which each party can terminate the contract due to specific breaches including insolvency / default by the client
Section 7: settlement of disputes - outlines process available for dealing with disputes such as mediation, arbitration and adjudication
Under JCT MW, what does the contractors obligations clause cover?
contractor is required to carry out the specified works to the requisite quality within the agreed timescale
CA responsibility to check quality of work completed during regular site progress inspections
Under JCT MW, what does the possession of site clause cover?
the site must be made fully available to the contractor by the client by the agreed date for the contractor to mobilise operations and commence work to meet agreed programme of work
Failure could constitute a breach of contract and justify an EOT
Under JCT MW, what does the errors, discrepancies and divergencies clause cover?
Errors with the design documentation are often discovered once contractor has started on site
this section covers how they are dealt with
Under JCT MW, what does the extension of time clause cover?
allows for the CA to extend or fix a new completion date, therefore postponing the clients rights to recover liquidates damages
contractor will apply
CA decision to approve or decline
Only issued if a relevant event