Project Finance (Control & Reporting) Level 1 Flashcards

1
Q

What is the structure of NRM 1: Order of Cost Estimating & Cost Planning for Capital Building Works?

A
  • Part 1: General introduction
  • Part 2: Measurement rules for order of cost estimate
  • Part 3: Measurement rules for cost planning
  • Part 4: Tabulated rules of measurement for elemental cost planning
  • Appendices
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the structure of NRM 2: Detailed Measurement for Building Works?

A
  • Part 1: General introduction
  • Part 2: Rules for detailed measurement for building works
  • Part 3: Tabulated rules of measurement for building works
  • Appendices
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the structure of NRM 3: Order of Cost Estimating and Cost Planning for Building Maintenance Works?

A
  • Part 1: General introduction
  • Part 2: New rules of measurement for building maintenance works
  • Part 3: Measurement rules for order of cost estimating (renewal and maintain)
  • Part 4: Measurement rules for cost planning for renewal and maintain works
  • Part 5: Calculation of annualised costs for renewal and maintain works
  • Part 6: Tabulated rules of measurement for elemental cost planning
  • Appendices
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is a provisional sum?

A

Generally an allowance or estimate included within the contract price for works that are:

  • not sufficiently defined, designed or detailed to allow an accurate determination of its cost at the time the contract is entered and / or
  • work that the employer may or may not wish to be carried out
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How are provisional sums expended?

A
  • the contract administrator (JCT) should issue an instruction for its expenditure
  • where a contract includes a provisional sum, the final amount payable will be adjusted (the provisional sum is omitted and replaced with the actual cost of the work)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How are provisional sums dealt with within the final account?

A
  • by the FA stage, the contract administrator will have issued instructions to expend all provisional sums
  • the instruction will show an add and omit (add actual costs and omit the provisional sum)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What types of provisional sums are there?

A
  • defined
    -undefined
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is a defined provisional sum?

A

the contractor is deemed to have allowed for programming and preliminaries within the contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is an undefined provisional sum?

A

The contractor does not allow for planning, programming and preliminary implications. This means the contractor may be entitled to an extension of time and / or additional preliminaries when the actual works are undertaken

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are prime cost sums?

A
  • only include for supply
  • no installation or associated costs are accounted for
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is cash flow projection?

A
  • a financial planning tool that shows the predicted flow of cash in and out of a project
  • this is typically shown month by month, for the duration of the project
  • when the construction phase is underway, the cash flow projection for contractor payments will typically form an S curve
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are the main types of cash flow projection?

A
  • the cash flow projection of a company (i.e. a contractor or consultant), known as an organisational cash flow
  • the cash flow projection of a particular construction contract or projects, known as project cash flow
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the purpose of post-contract cost reporting?

A
  • to provide an overview of the clients current financial commitment
  • to inform the client of the likely out-turn cost of the project, including forecasting the out-turn cost as a variance against the budget
  • to give the client an understanding of potential savings or additional monies required
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Define the outturn cost.

A

The known cost at the end of a project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are the 3 stages of a cost prediction system?

A
  • Inputs - the values, attributes & quantities
  • Process - the analysis & quantification
  • Outputs - the cost prediction at each of the relevant stages
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What factors can impact the outturn cost?

A
  • provisional sums
  • provisional quantities
  • prime cost sums
  • day work allowances
  • variations such as contract instructions, risk allowances, fluctuations