Contract Practice Level 1 Flashcards
What is a contract?
A contract is a legally binding promise by one party to fulfil an obligation to another party in return for consideration
What are the components of a legally binding contract?
Offer
Acceptance
Consideration - the promise made by both sides to do something e.g. providing a building in return for money
Intent - the intent to create legal relation, could be in the form of a letter of intent
What are ‘express terms’?
Terms which are expressly stated and agreed within a contract
What are ‘implied terms’?
A contractual term which is not expressly stated or agreed within the contract but has been implied into the contract by common law or statute
What is the difference between statutory provisions and contract provisions?
Statutory provisions are set out by the law and must be complied with regardless
Contract provisions relate to the specific contract and only apply to the project at hand
What are the different types of subcontractors?
Domestic - selected by the main contractor to carry out a package of works designed by somebody else
Named - the employer provides a list of pre-approved and named subcontractors, the main contract then selects one from this list through the tendering process
Nominated - selected by the employer to carry out an element of works, employed by the main contractor. Usually imposed upon the main contractor
Why do main contractors sublet works?
Complexity and specialisation
avoids need to maintain directly employed operatives
reduces supervision and admin costs
flexibility as large volumes of work can be carried out
What is the overarching purpose of the Contracts (Rights of Third Parties) Act 1999?
Allows third parties to enforce terms of a contract that they are not party to, but which benefits them in some way, or which the contract allows them to enforce
Gives them access to various remedies if those contract terms are breach
Those who are not party to the principle contract has access to the same contractual remedies as those who do
What are the advantages of third party rights?
time and cost - the Contract (Rights of 3rd Parties) Act 1999 cuts down on the time and cost associated with warranties being signed up / drawn or circulated
Certainty - limited room to revisit wording once agreed
Subcontractors - 3rd party rights can be extended to subcontractors so eradicates the need to chase large numbers of individual warranties
Why are third party rights used instead of collateral warranties?
CW can involve a lot of admin and cost
Easier to get in place as no separate document is required
What are collateral warranties?
A formal contractual agreement which runs alongside another contractual agreement, creating a contractual relationship between two parties which otherwise would not exist
Typically used as protection for the client in the event a 3rd party fails to perform their obligations
Often used between clients and sub-contractors / sub-consultants through the main contractor
What are JCT contracts?
JCT is a standard form of contract; Joint Contracts Tribunal
There are 12 contracts within the JCT family, examples include: Standard Building Contract Intermediate Building Contract Minor Works Building Contract Design & Build Contract
What are the key project characteristics which influence which JCT contract is used?
size, value & type of project need for contractor design certainty on final cost attitude towards client risk ownership and risk transfer client experience programme requirements
When would you use a JCT Minor Works Contract?
smaller, basic construction projects where works are of a simple nature
where the procurement route is traditional
where the client is responsible for design, however if the contractor is responsible for designing elements of the works then MWBC with contractor’s design should be used
When would you use the JCT Standard Building Contract?
Designed for large or complex projects where detailed contractual provisions are required
where projects are procured via the traditional procurement route
where the employer is carrying out the design, however there are provisions for ‘Contractors Designed Portion’
Works being carried out in sections
When would you use the JCT Intermediate Contract?
Construction projects involving all recognised industry trades and skills
Detailed contractual provisions are required but without complex building services or specialist work
Suitable for projects following the traditional procurement route