Quantification & Costing Flashcards
What methods of measurement are you aware of?
IPMS - Offices, Resi & Retail - mandatory if asked to use otherwise - will undertake under code. (Incl balconies and limited use areas e.g height less than 1.5m i.e. window reveals)
RICS Code of Measurement Practice - 6th Ed 2015 - GEA/GIA/NIA - all other buildings.
ICMS - International framework for measurement - basis of NRM.
NRM 1, 2 & 3 (2021) - 2021 update to align with ICMS & RIBA PoW 2020 & CPPS (cost prediction proff standard)
CESMM - Civil Engineering Standard Method of Measurement.
What is NRM?
New Rules of Measurement
Books published by the RICS to provide a set of measurement rules for estimating / cost planning / procurement for construction projects.
What is NRM 1?
Provides guidance on quantification of building works for cost estimates and cost plans.
It is the ‘cornerstone’ of good cost management of construction projects – enabling more effective and accurate cost advice to be given to clients and other project team members, as well as facilitating better cost control
What is NRM 2?
Provides guidance on the detailed measurement and description of building works for preparation of bills of quantities.
What is NRM 3?
Provides guidance on the quantification of maintenance works.
What is the shorter schedule of cost components
The Shorter Schedule of Cost Components is designed for assessing compensation events.
What are the types of cost estimate?
Floor area
Functional unit
Elemental
What information is required for an Order of Cost Estimate?
Location of site Statement of floor area Floor plans Roof plan Elevations Sections Storey heights Initial risk register
What information is required for a Formal Cost Plan?
Procurement Strategy Contract Strategy Fees Budget Detailed design info
What are the sections of NRM?
0 - Facilitating Works 1 - Substructure 2 - Superstructure 3 - Internal Finishes 4 - Fittings Finishes and Equipment 5 - Services 6 - Prefabricated Buildings and Building Units 7 - Work to Existing Buildings 8 - External Works 9 - Main Contractor's Prelims 10 -Main Contractor's Overhead and Profit 11 - Project / Design Team Fees 12 - Other Development / Project Costs 13 - Risks 14 - Inflation
What is the structure of NRM 1?
Part 1 - Cost estimating + cost planning in the context of RIBA stages
Part 2 - Purpose + content of order of cost estimate
Part 3 - Purpose + content of formal cost plans
Part 4 - Tabulated measurement rules
Appendices
What is ICMS?
International Construction Measurement Standards
They are a new universal system that enable global comparison of construction project costs.
RICS prepared a global professional statement on cost prediction incorporating ICMS in 2020.
Basis of NRM
Why does location affect cost?
Availability of materials Transport cost & routes Availability of labour Ease of access to site Availability of services to site Vicinity of sites in relation to amenities Local labour costs Travel distances Existing land conditions
What are RPI and CPI?
Retail Price Index and Consumer Price Index.
Government’s preferred measures of inflation
May be used to update costs
Use with caution as they are not construction specific
Construction activity does not necessarily reflect the profile of UK economic activity
TPI - inflation measure for tendering for costplans
What is the RICS Code of Measurement Practice?
A UK measurement guidance note published by the RICS. It gives definitions for GEA, GIA and NIA and explains how to measure them correctly.
To be used on all other asset types that the IPMS does not cover (ie. anything other than offices, retail, resi)
What is IPMS?
International Property Measurement Standard
IPMS 1 -
The sum of the areas of each floor level of a Building measured to the outer
perimeter of external construction features, which may be reported on a
Component-by-Component basis for each floor of a Building.
IPMS 2 – Office
The sum of the areas of each floor level of an office Building measured to the
Internal Dominant Face and reported on a Component-by-Component basis for
each floor of a Building.
IPMS 2 – Residential
The sum of the areas of each floor level of a Building measured to the Internal
Dominant Face, which may be reported on a Component-by-Component basis for
each floor of a Building.
IPMS 3 – Office The Floor Area available on an exclusive basis to an occupier, but excluding Standard Facilities, and calculated on an occupier-by occupier or floor-by-floor
basis for each Building.
IPMS 3 – Residential The Floor Area available on an exclusive basis to an occupier
What does IPMS cover?
Offices & Residential
RICS members are expected to advise their client or employer on the benefits of using IPMS. However, it is understood that IPMS is not suitable in all circumstances
and in these circumstances RICS members must document the reason for departure.
When did IPMS come into use?
2nd Ed - Jan 2018
What is NRM?
New Rules of Measurement provides a standard set of rules and essential guidance for the cost management of construction projects and maintenance works
What did the NRM CPD event that you attended cover?
It was a general overview of NRM suite and how to use them
How do you quantify differently for a feasibility estimate or a cost plan?
A feasibility estimate will be based on areas or functional units. Usually just GAs and facades are measured.
Cost plans are measured on an component basis.
What did you advise the client were the key changes between IPMS and RICS Code of Measurement Practice?
On a previous the biggest difference was the inclusion of window reveals in IPMS 1. These are stated as limited use areas.
What did you advise the client were ways to meet the net to gross efficiency ratio target on the masterplanning project?
There was a large stepped theatre like ‘touch-down’ space within the atrium which, although was intended as flexible working space, could not be included within NIA. Reducing the area of this and increasing the area of the mazzanine floor would increase net to gross efficient.
What is Benchmarking?
The systematic method of comparing project performance against others, then using lessons from the best to make targeted improvements.
The ‘Benchmark’ is the best in class.
It is often misused to mean average or minimum performance.