Construction Tech Flashcards

1
Q

When would you use pile foundations?

A

In weak or water baring soil.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

When would you use strip foundations?

A

In houses or buildings where the perimeter walls transfer load to the ground.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

When would you use pad foundations?

A

For lighter structures such as warehouses. Wide span light weight buildings.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

When would you use raft foundations?

A

On soils with good bearing capacity.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Name four different types of foundations.

A

Pad
Raft
Pile
Strip

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What types of piles are you aware of?

A
Pre-Cast
Sheet
Bored
CFA
Contiguous
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the advantages of steel over concrete frame?

A

Quicker erection
Recyclable
Tensile strength
High strength to weight ratio
Foundations may cost less due to lower dead load
Larger spans
Less wet trades on site than for in-situ, potentially lower prelims

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How does rainwater harvesting filter the water?

A

Using ultra violet light

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the advantages of concrete over steel frame?

A
Thermal mass
Fire resistance
Acoustic and thermal performance
Cost fluctuates less
Can achieve complex shapes
Compressive strength
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What types of façade are you aware of?

A

Stick

Unitised

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are the advantages of a stick system?

A

Stick systems use mullions and transoms (sticks) to hold glazing against the structure. It is more economically friendly for small volume facades.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are the advantages of a unitised system?

A

High quality due to off-site manufacture

Quick installation due to no glazing being installed on site

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the build-up of a stick system?

A

Transoms and mullions fixed into floor slabs
Glazing fixed to transoms and mullions
Aluminium cap over glazing to hold it in place

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What types of basement construction are there?

A

Traditional (battering, ramped sides to stop it collapsing)
Retaining walls
Top-down

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What strategies of basement waterproofing are there?

A

Barrier (tanking)
Structurally integral (additive)
Drained (cavity drained)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How would you reduce the amount of excavated material taken on and off site?

A

By doing a cut and fill exercise

Reuse of materials on site

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What types of demolition are there?

A

Top down
Bottom up
Blast

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

How do you calculate rebar weights?

A

Using the bending schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What methods can be used for fixing unitised façade panels?

A

Crane them in
A monorail system
On floor manipulators
Which one is used will depend on site constraints and programme.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Why would you do a cut and fill exercise?

A

To minimise the amount of material needed to be brought to site to make up levels, as this is expensive.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

How would you carry out a cut and fill exercise?

A

Mark-up a grid on a drawing
Take the average of the highest and lowest points within that grid
The difference from this to the desired level is the cut/fill amount required

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What are the types of ground anchor?

A

Tensioned
Non-tensioned
Pre-fabricated

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

What are British Standards?

A

Publications issued by the British Standards Institution – prefixed BS
They give recommended min standards for materials, components, design and construction practices

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

What are international standards?

A

Prepared by the International Organisation for Standardisation – prefixed ISO
Compatible with and complement BS’s

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
What are the typical components of site investigations?
``` Anything on adjacent sites that may impact Boundary hedges / fencing Existing trees Size, depth and location of services Existing buildings Ground water conditions Soil investigations – trial pits etc ```
26
What is landfill tax?
The tax, administered by HM Customs & Excise, applies to all waste disposed of, at a licensed landfill site, unless specifically exempt. In force since 1996
27
At what rates is landfill tax charged?
Landfill Tax is charged at 2 rates: £2 per tonne for all inert waste £38 per tonne for all other taxable waste
28
What is a tower crane and how do you erect one? What would stop a tower crane from working?
A tall crane used for lifting objects into high places. The boom allows a longer reach with 360 access. A longer boom reduces the payload capability. Use a smaller crane to erect a tower crane Weather conditions could prevent it from working, in particular high, strong winds.
29
What is shoring?
Form of temporary support given to existing buildings | Purpose is to provide a precaution against damage or injury for collapse of structure
30
What are hoists?
Designed for the vertical transportation of materials or people
31
What is a borehole?
A borehole can be used for soil investigation | Boreholes are the most suitable method of soil investigation when foundations are over 3m deep
32
What are the problems to the PQS regarding cost control with piling? Whose risk is the piling?
The end depth of the piles are never a certainty and the procurement route used determines who takes the risk (traditional/ D&B = the main contractor; management contracts = employer)
33
What are the different parts of a steel beam?
A simple I Beam is made up: Flange (Top and Bottom of the vertical steel) Web, which is the vertical steel part of the I Root, which is where the Flange and the Web join.
34
What is powder coating?
A tough durable factory applied organic coating on metals, such as aluminium or galvanized steel, available in many colours. E.g. polyester, polyurethane, acrylic, and epoxy which are sprayed on, followed by heat curing to give a film thickness of 50 to 100micorns. Any holes should be made and any cutting done before the coating is applied.
35
What is an RHS / SHS?
``` RHS = Rectangular Hollow Section SHS = Square Hollow Section ```
36
What are the different types of brick bond?
Stretcher – most common, walls just a half brick wide | English – alternating courses of headers and stretchers
37
What is an air brick?
A perforated brick to allow for ventilation into a room or an underfloor space. NOT a weep hole.
38
What are bonded and unbonded types of screed?
Bonded Screeds – Laid on to a ready prepared rough, cleaned concrete base Unbonded Screeds – Laid on to a sound, clean Bitumen damp proof membrane to BS4483
39
What is a shear force?
A perpendicular force
40
What is torsion?
A twisting force
41
How do you counter torsion?
With outriggers
42
What is the typical build-up of a unitised façade
``` Back-up wall Structural build-up / steel frame Insulation Waterproofing Rainscreen ```
43
What types of excavation are there?
Open and trenched | with or with trench box supports
44
What are connections in steel?
Plates, bolts or welding. Around 12.5% by weight.
45
What is a composite floor?
Consist of profiles steel decking and in-situ reinforced concrete. Decking acts as permanent formwork for the concrete and provides sufficient shear bond to the concrete that the two materials act in composite together. Usually used in steel frames.
46
What are Building Regs?
Statutory instrument that sets minimum standard for performance for the design and construction of buildings.
47
What types of retaining wall are you aware of?
Contiguous pile | Concrete reinforceed retaingin wall
48
What types of building envelopes are there?
Cavity walls Cladding Glazing brickwork
49
What is the make-up of a stud partition?
Base plate and top plate/keels Vertical and horizontal timber or metal studs Plasterboard/gyproc board screwed and fixed into partitions Firestop and smoke seal at the top of the partition
50
What are the advantages of a fan-coil unit?
Good control of air movement Quick installation High cooling capacity
51
What are the disadvantages of a fan-coil unit?
The air filter requires maintenance | The fan can be noisy on a high speed setting
52
What is the difference between a two-pipe and a four-pipe fan-coil unit?
A two pipe FCU provides cooling | A four pipe FCU provides heating and cooling
53
What are the types of chilled beam?
Active chilled beam | Passive chilled beam
54
What are the advantages of a chilled beam?
They can be accommodated in a shallow ceiling void | Passive beams have no moving parts
55
What are the disadvantages of a chilled beam?
Their cooling output is limited | They require a separate ventilation system to supply fresh air
56
What types of basement construction are you aware of?
``` Traditional open (excavate) Traditional enclosed (retaining wall to perimeter then excavate) Top down (retaining wall to perimeter, plunge columns, ground floor slab leaving hole for excavation. Faster but more expensive) ```
57
What is a steel table?
They provide standard information on steel sections in tabulated form. For each serial size and universal beam number.
58
What are temporary works?
Works that do not usually appear on construction drawings but are necessary for safe construction i.e. propping
59
What is an AHU?
An air handling unit - responsible for drawing air into the building and disposing of exhaust air
60
What are fire dampeners?
Effectively blades within a vent | A fire sensor will go off and close the blades in the event of a fire
61
What is Part B of building regulations?
The section of building regulations relating to fire safety
62
When was Approved Document B Fire Safety last updated?
2010
63
What is an AHU?
Air handling unit Centralised plant in basement or on roof Controls air intake and distribution into ductwork
64
What is MVHR?
Mechanical Ventilation Heat Recovery
65
What are fire dampeners?
Vents within ducts that close in event of a fire.
66
What are the advantages and disadvantages of stick and unitised façade systems?
Stick is suited to façades with not much repetition Unitised is more suited to repetition Unitised is assembled off-site so less time to install on site and higher quality
67
What are the different types of foundations?
Pad Raft Strip Pile
68
How do ground conditions effect choice of types of foundations?
Soil type will effect foundation type as this dictates how the building's load is transferred into the ground London clay means friction piles are often used
69
What are the advantages of steel and concrete frames?
``` Steel quick to construct Steel priced more volatile Concrete has better fire resistance Concrete has better thermal mass In-situ concrete can be used to create complex shapes Concrete pour can be affected by weather ```
70
How do you price concrete or steel frames?
Concrete Rebar Formwork Finish Steel Fittings Fire protection sequence / revisits
71
What is post-tensioned concrete?
Steel tendons are laid through the slab Concrete poured Once the concrete has cured a stressing jack is used to tension the slab Stronger than RC slab as the concrete is under compression
72
What is pre-tensioned concrete?
Steel tendons are laid through the slab Concrete poured Before the concrete has cured a stressing jack is used to tension the slab Stronger than RC slab as the concrete is under compression
73
What are the implications of working on an Over Site Development?
High levels of vibration and movement monitoring are required Site B sits on bearings to reduce vibrations into the theatre
74
What is soft toe piling?
It is a way of creating a pile where the end is soft where no load is transferred. There are different methods of achieving this such as using a sack of water. It used for friction piles above existing LUL assets, to guarantee that no load will be transferred through the toe of the pile and into the structure below.
75
How to fan-coil units work?
Contains a heating and or cooling (2 or 4 pipe) heat exchanger 'coil' and a fan to draw air across They are controlled by manual on/off switches or by thermostats The thermostat controls the throughput of water to the heat exchanger using a control valve and /or the fan speed
76
How does a chilled beam work?
HVAC system designed to heat or cool large spaces It uses pipes of water passed through a beam which is either integrated into the suspended ceiling or is just above it Active chilled beams use fans to draw air across it Passive chilled beams rely on convection
77
What is a retaining wall?
A structure designed to resist the lateral pressure of soil | Sheet piled and bored piled retaining walls are used on central London sites
78
How was the construction methodology of one of you projects effected by the site constraints?
A 'semi top-down' approach was selected for basement construction in order to provide a logistics slab for site deliveries and carting away excavated material
79
What is SIPs
Structurally Insulated Panel systems - often manufactured off site (Meadowfilds)
80
What are the advantages & disadvantages of Modular construction
St Georges School Quicker on site period Can be cheaper in some cases Reduced nr. of trades on site Can create longer design stage - need to engage early in design & fabrication off site can take time (needs to be factoreed into program) May need funding upfront and /or advance payments
81
How does planning permission impact on design?
Requirements for new roads, renewable energies, community use facilities, sustainability outputs / KPIs, ecological issues, resticts changes, comply with condition.
82
What other legislation impacts on construction?
Brexit, covid, planning, fire regulations, building regulations, sustainable product use & renewable energy targets.
83
How does the age of the building affect construction methods?
Pre 1999 may contain asbestos. | Listed or timber buildings - may need to match existing & may be hard and expensive to match products
84
What are the RIBA stages?
``` 0 - Stategic definition 1- Prep & briefing 2 - Concept 3 - Spatial co-ord 4 - Technical 5 - Construction 6 - Handover 7 - In use ```
85
Where are these used
Design fee drawdowns, project milestones, valuing work, help identify roles & responsibilities in appointments & contracts
86
Can you give me examples of 2 alternative air condition systems?
Water heating / cooling system | Earth - air heat exchangers that use ground temperatures
87
What do you understand by the term bus bar?
Metal strip or bar for power distribution - often found in panels / switchgear fro local high power distrbution
88
What are the advantages of a steel framed building over a concrete frame?
Steel - lighter, quicker, greater spans, lower weight, mass production of repeat items. Concrete can offer better thermal & acoustic properties and can achieve less uniform shapes.
89
What current challenges is Covid and/or Brexit bringing to Construction Technology?
Planning works with unknown certainty of cost of materials, labour & availbility - longer lead in Flexible quickly Impacts on labour - slower installation Impacts on cost of materials & availbility and or able to source materials through delivery issues Enhaned H&S - social distancing, cleaning, working methods Enhancement of importance of AI, IT remote working, planning ahead with contingency plans, data use & control
90
Tell me more about the review of design details for the fire requirements at Giles Lane Student accommodation. What issues were you targeting in your review? Why?
Reconfigoration of student accomodation and fire compartments. Largely removed externally and internally to ensure compliance. Reviewed with design team to ensure met requirements. Internal fire compartments, fire breaks in external façade & at openigns where addedd.
91
Give me an example of a fire protection solution for structural steelwork.
Boarding, intumescent painting, concrete encasement
92
Give me an example of other foundation solutions that are commonly employed in the construction industry.
Piling Strip Pads Raft
93
Take me through the construction process of a strip foundation.
Check GI for obstructions, Setting out, excavation of tench (with formwork/tenchbox if required and working space), blinding, reinforcement (if requried), mass fill concrete & tamp, cure, remove forwork etc / concrete samples 7/14/21/28 days or as requried by spec
94
what are the key factors in selectiing cladding
``` 1 - Meets fire requirements 2 - Certified system (not just cladding product but build up also) 3 - Meets plannign requirements 4 - Program impacts - lead in / access 5 - Price ```
95
Tell me more about the façade design that you refer to in your summary of experience. Explain the factors considered before coming to the final solution and the rationale for the choice made.
Gebrick at Barton Court I looked at an alternative option to tradtional brickwork which involved liasing with design team, planning and building control. I explored the buildability with the construction team to understand program and how the alternative option could omit some of the scaffold, improve installation time and in turn offer further savings over and above the material cost. Arranged full mock up samples to demonstrate to planners and client the aesthetic similarities and sought all the technical data info along with report outlining benefits and savings available - in both money and time for client to make a decision.
96
From your experience, what are the key factors to be considered on the selection of suitable cladding? Explain the importance of each factor.
``` Fire compliance Acoustic & thermal compliane Certification of whole system buildup Planning requirements Lead in of materials Installation methodology / access and time Price - as every project has a budget ```
97
When would you recommend the use of prefabricated units such as the pods referred to under your level 2 experience?
High repetiton - student accomodation / hotel High use - durability Minimal access for maintenance required Watertight room Speed on site - 4 hours per pod to fit & connect pre-plumbed pod
98
What is Underpinning
suppport to existing struc wall
99
What is Shoring
Shoring - lateral support to structurual wall / structure - temporary support
100
What is Slip form / jump form
Form work - slip continuous moving. Slip = no joints
101
what is importance of construction tech
If don’t understand how something is constructed - cannot measure and value it
102
What is an element
functional unit
103
how to identify elements
NRM / BCIS
104
Plasterboard types
acousitic / moisture / general / fire
105
CAT A fitout
Uk only - building to tenant with only primary finish- i.e. they fitout (CAT B - fitout - tenants fittings & customised)
106
Ventilation
Natural / Mechanical / stack (warm air rising up)
107
Intumecent paint
Active - reactive fire protection - expands
108
What are the disadvantages of steel frame
STEEL - COSTLY / CORROSION / ENERGY IN MAN PROCCESS / NOT GOOD INS OF HEAT & SOUND / INSTALL - CRANE & LEAD TIME
109
What are the advantages of concrete frames
Adv - Conc frames - thermal & acoustic benefits / cast complex shapes, maintenance low, cashflow slower
110
What is formwork
formwork - holding conc in place / mould
111
What is falsework
falsework - temp work for supporting formwork / scaffold
112
What updates are you aware of to Fire post Grenfell?
21 DEC 2018 - COMBUSTABLE MAT OVER 18M - LOOKING TO RECUDE TO 11M (11M RESI SPRINKLERS) - Buildign regs part B RICS cladding guidance PII requirement to have fire cover
113
28. Warm & Cold roof
a. Cold roof – insulation in ceiling | b. Warm – in roof buildup
114
34. What are the 3 types of building notice (for building control)?
a. Full (based on plans – sign off of building in advance) b. Building notice -simple project c. Regularization – retrospective
115
35. What are the implications if GDPR is not complied with?
a. 4% t/o upto £17m