Black Books - All Flashcards
What are the pros & cons of subcontracting?
Pros: Using specialists Flexible resources Transfer of risks Reduce cost of training & development
Cons:
Smaller businesses lack resources for training & development
Less control
Risk dumping
Types of subcontracting?
Nominated
Named
Labour only
Design consultants
Features of a subcontract?
Agreement Conditions Particulars Scope & Attendances Technical documents Security (Bonds / PCG) Collateral Warranties
What is the difference between procurement & tendering?
Procurement is the overall process of obtaining goods and services including the strategy of how.
Tendering is the bidding process phase of procurement
Why are amendments included in a contract?
- To reflect a project specific obligation (i.e. an agreement for lease)
- To reflect the client’s business needs ( i.e. performance security)
Where does the Construction Act NOT apply?
Residential occupiers
Demolition of plant and machinery
What are the payment terms under a JCT subcontract & NEC subcontract?
JCT:
Application 7 d - Due Date - FDFP 14 d = 21 days
NEC4:
Application 14 d - Due Date - FDFP 14 d = 28 days
How do the notices in NEC4 differ between the standard contracts and subcontracts?
Standard - Main Contractor has 8 weeks
Subcontract - Subcontractor has 7 weeks
What are damages?
- Time related prelims (often fixed LDs)
- L&E from other s/c
- Inflation costs
- Costs due to retention held under MC
- Loss of contribution to OH&P
- Interest costs
What is included in a procurement strategy?
- Exec summary
- Contract details
- MC works
- s/c packages
- Financial planning
- Programme
- Pre-qual
- Tendering procedure
- ITT
- Assessment
- Appointment
What are the signs of subcontractor insolvency?
- Difficultly getting pricing from supply chain
- Resignations / high t/o of staff
- Requests for advance payments / reduced payment terms
- Refusal to provide bonds / high premiums
- Rumours of financial stability
- Lack skilled labour
- Inflated valuations / claims
- Chasing payments
- Payment for Materials off site
What are cashflows used for?
- Obtaining bank loans
- Progress monitoring
- Managing cash
- Forecasting business performance
Types of Valuations?
- Staged payments (payments at set times regardless of progress)
- Milestones
- Activity Schedule
- Valuation of works done.
What are the key impacts of the Construction Act?
- Right to interim payments
- Right to adjudicate
- No withholding payments unless payless notice issued
What are the considerations when collating a cashflow?
- Should retention be included
- Whole development or just contract
- Gross / net
- Monthly / cumulative / both
- Adjustments for easter / xmas breaks
Reasons for variances in cashflows?
- Progress
- adverse weather
- site conditions
- resequencing
- materials off site
- materials not delivered / labour shortages
Why might a contractor be ahead of forecast cashflow?
- Front loading
- Ahead on Programme
- Re-sequenced works
- Variations
- Acceleration to finish earlier
- Cashflow not accurate in first place
What are the different forms of procurement?
- Lump sum
- Remeasureable
- D&B
- Construction Management
- Management contracting
- Partnering
- PFI