Please explain following graph? (2 points, p. 3) PROJECT START AND END

A

as time goes on we have development of costs increases and the ability to influence those costs decreases

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What should be available at a project launch at a narrower and a broader sense? (8 points, p. 6)

A

in narrow we should have a rough idea of planning process where first ideas are exchanged and we have rough targets
in broader sense we need more detailed planning - justification of the project team, implementation of kick off and analysis of environment and stakeholders

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is a project ‘kick-off’, who should take part and about what should be spoken? (3 points, p. 7)

A

this is an information event where the project manager involve the project team/stakeholders to introduce everyone and tranfer information about goals/risks/dates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What a ‘final report’ should contain (5 points, p. 11)

A

Summary report at end of project which gives post calculation, evaluation of customer surveys, personnel transition plan. Product data