Project start and end Flashcards
Please explain following graph? (2 points, p. 3) PROJECT START AND END
as time goes on we have development of costs increases and the ability to influence those costs decreases
What should be available at a project launch at a narrower and a broader sense? (8 points, p. 6)
in narrow we should have a rough idea of planning process where first ideas are exchanged and we have rough targets
in broader sense we need more detailed planning - justification of the project team, implementation of kick off and analysis of environment and stakeholders
What is a project ‘kick-off’, who should take part and about what should be spoken? (3 points, p. 7)
this is an information event where the project manager involve the project team/stakeholders to introduce everyone and tranfer information about goals/risks/dates
What a ‘final report’ should contain (5 points, p. 11)
Summary report at end of project which gives post calculation, evaluation of customer surveys, personnel transition plan. Product data