Project Schedule Management Flashcards
Activity list
Udemy- The primary output of breaking down the WBS work packages.
PMBOK- A documented tabulation of schedule activities that shows the activity description, activity identifier, and a sufficiently detailed scope of work description so project team members understand what work is to be performed.
Alternative analysis
udemy- The identification of more than one solution. Consider roles, materials, tools,
and approaches to the project work.
PMBOK- A technique used to evaluate identified options in order to select the options or approaches to use to execute and perform the work of the project.
Analogous estimating
udemy- A somewhat unreliable estimating approach that relies on historical information to predict what current activity durations should be. Analogous estimating is more reliable, however, than team member recollections. Analogous estimating is also known as top-down estimating and is a form of expert judgment.
pmbok- A technique for estimating the duration or cost of an activity or a project using historical data from a similar activity or project.
Bottom-up estimating
udemy- The most accurate time-and-cost estimating approach a project manager can use. This estimating approach starts at “the bottom” of the project and considers every activity, its predecessor and successor activities, and the exact amount of resources needed to complete each activity.
pmbok- A method of estimating project duration or cost by aggregating the estimates of the lower-level components of the work breakdown structure.
Control account
udemy- A WBS entry that considers the time, cost, and scope measurements for that
deliverable within the WBS. The estimated performance is compared against the actual performance to measure overall performance for the deliverables within that control account. The specifics of a control account are documented in a control account plan.
pmbok- A management control point where scope, budget, actual cost, and schedule are integrated and compared to earned value for performance.
Control threshold
A predetermined range of acceptable variances, such as +/–10 percent off schedule. Should the variance exceed the threshold, then project control processes and corrected actions will be enacted.
Crashing
udemy- A schedule compression approach that adds more resources to activities on the critical path to complete the project earlier. When crashing a project, costs are added because the associated labor and sometimes resources (such as faster equipment) cause costs to increase.
pmbok- A technique used to shorten the schedule duration for the least incremental cost by adding resources.
Critical path
udemy- The path in the project network diagram that cannot be delayed, otherwise the project completion date will be late. There can be more than one critical path.
Activities in the critical path have no float.
pmbok- The sequence of activities that represents the longest path through a project, which determines the shortest possible duration
Discretionary dependencies
udemy- These dependencies are the preferred order of activities. Project managers should use these relationships at their discretion and should document the logic behind the decision. Discretionary dependencies allow activities to happen in a preferred order because of best practices, conditions unique to the project
work, or external events. Also known as preferential or soft logic.
pmbok- A relationship that is established based on knowledge of best practices within a particular application area or an aspect of the project where a specific sequence is desired.
Early finish
Udemy- The earliest a project activity can finish. Used in the forward pass procedure to discover the critical path and the project float.
pmbok- In the critical path method, the earliest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic, the data date, and any schedule constraints.
Early start
udemy- The earliest a project activity can begin. Used in the forward pass procedure to discover the critical path and the project float.
pmbok- In the critical path method, the earliest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic, the data date, and any schedule constraints.
External dependencies
udemy- As the name implies, these are dependencies outside of the project’s control. Examples include the delivery of equipment from a vendor, the deliverable
of another project, or the decision of a committee, lawsuit, or expected new law.
pmbok- A relationship between project activites and non-project activities.
Fast tracking
Udemy- A schedule compression method that changes the relationship of activities. With fast tracking, activities that would normally be done in sequence are allowed to be done in parallel or with some overlap. Fast tracking can be accomplished by hanging the relation of activities from FS to SS or even FF or by adding lead time to downstream activities. However, fast tracking does add risk to the project.
pmbok- A schedule compression technique in which activities or phases normally done in sequence are performed in parallel for at least a portion of their duration.
Finish-to-finish (FF)
Udemy- An activity relationship type that requires the current activity to be finished before its successor can finish.
pmbok- A logical relationship in which a successor activity cannot finish until a predecessor activity has finished.
Finish-to-start (FS)
Udemy- An activity relationship type that requires the current activity to be finished before its successor can start.
pmbok- A logical relationship in which a successor activity cannot start until a predecessor activity has finished.
Fragnet
udemy- A representation of a project network diagram that is often used for outsourced portions of a project, repetitive work within a project, or a subproject. Also called a subnet.
Free float
udemy- This is the total time a single activity can be delayed without affecting the early start of its immediately following successor activities.
pmbok- The amount of time that a schedule activity can be delayed without delying the early start date of any successor or violating a schedule constraint
Hard logic
udemy- Logic that describes activities that must happen in a particular order. For example, the dirt must be excavated before the foundation can be built. The foundation must be in place before the framing can begin. Also known as a mandatory dependency.