What processes belong to Initiating Process Group?
4.1 Develop Project Charter
13.1 Identify Stakeholders
What processes belong to Planning Process Group?
4.2 Develop Project Management Plan
5.1 Plan Scope Management, 5.2 Collect Requirements, 5.3 Define Scope, 5.4 Create WBS
6.1 plan schedule management, 6.2 define activities, 6.3 sequence activities, 6.4 sequence activities, 6.5 develop schedule
7.1 plan cost management, 7.2 estimate costs, 7.3 determine budget
8.1 plan quality management
9.1 plan resource management, 9.2 estimate activity resources
10.1 plan communications management
11.1 plan risk management, 11.2 identify risks, 11.1 perform qualitative risk analysis, 11.5 plan risk responses
12.1 plan procurement management
13.2 plan stakeholder engagement
What processes belong to Executing Process Group?
4.3 Direct and Manage Project Work
4.4 Manage Project Knowledge
8.2 Manage Quality
9.3 Acquire Resources, 9.4 Develop Team, 9.5 Manage Team
10.2 Manage Communicatons
11.6 Implement Risk Responses
12.2 Conduct Procurements
13.3 Manage Stakeholder Engagement
What processes belong to Monitoring & Controlling Process Group?
4.5 monitor and control project work, 4.6 perform integrated change control
5.5 validate scope, 5.6 control scope
6.6 control schedule
7.4 control costs
8.3 control quality
9.6 control resources
10.3 monitor communications
11.7 monitor risks
12.3 control procurements
13.4 monitor stakeholder engagement
What processes belong to Closing Process Group?
4.7 close project or phase