Project Cost Management Flashcards
Actual cost (AC)
udemy- The actual amount of monies the project
has spent to date.
pmbok- Actual cost is the realized cost incurred for the work performed on an activity during a specific time period.
Analogous estimating
udemy- An approach that relies on historical information to predict the cost of the current project. It is also known as top-down estimating and is the least reliable of all the cost-estimating approaches.
pmbok- a technique for estimating the duration or cost of an activity or a project using historical data from a similar activity or project.
Bottom-up estimating
udemy- An estimating approach that starts from zero, accounts for each component of the WBS, and arrives at a sum for the project. It is completed with the project
team and can be one of the most time-consuming and most reliable methods to
predict project costs.
pmbok- Bottom-up estimating is a method a component of work
Budget estimate
udemy- This estimate is also somewhat broad and is used early in the planning
processes and also in top-down estimates. The range of variance for the
estimate can be from –10 percent to +25 percent.
Commercial database
udemy- A cost-estimating approach that uses a database, typically software-driven, to create the cost estimate for a project.
Contingency reserve
udemy- A contingency allowance to account for overruns in costs. Contingency
allowances are used at the project manager’s discretion and with management’s approval to counteract cost overruns for scheduled activities and risk events.
pmbok- Contingency reserves are the budget within the cost baseline that is allocated for identified risks. Contigency reserves are often viewed as the part of the budget intended to address the known-unknowns that can affect a project.
Cost aggregation
udemy- Costs are parallel to each WBS work package. The costs of each work
package are aggregated to their corresponding control accounts. Each
control account then is aggregated to the sum of the project costs.
pmbok- Summing the lower-level cost estimates associated with the various work packages for a given level within the project’s WBS or for a given cost control account.
Cost baseline
udemy- A time-lapse exposure of when the project monies are to be spent in relation to cumulative values of the work completed in the project.
pmbok- The approved version of the time-phased project budget, excluding any management reserves, which can be changed only through formal change control procedures and is used as basis for comparison to actual results.
Cost budgeting
The cost aggregation achieved by assigning specific dollar amounts for each of the scheduled activities or, more likely, for each of the work packages in the WBS. Cost budgeting applies the cost estimates over time.
Cost change control system
A system that examines any changes associated with scope changes, the cost of materials, and the cost of any other resources, and the associated impact on
the overall project cost.
Cost management plan (follow up with udemy on this)
The cost management plan dictates how cost variances will be managed.
Cost of poor quality
The monies spent to recover from not adhering to the expected level of quality. Examples may include rework, defect repair, loss of life or limb because safety precautions were not taken, loss of sales, and loss of customers. This is also known as the cost of nonconformance to quality.
Cost of quality
udemy- The monies spent to attain the expected level of quality within a project. Examples include training, testing, and safety precautions.
pmbok- All costs incurred over the life of the product by investment in preventing nonconformance to requirements, appraisal of the product or service for conformance to requirements, and failure to meet requirements.
Cost performance index (CPI)
udemy- Measures the project based on its financial performance. The formula is CPI
= EV/AC.
pmbok- a measure of the cost efficiency of budgeted resources, expressed as a ratio of earned value to actual cost.
Cost variance (CV)
udemy- The difference of the earned value amount and the cumulative actual costs
of the project. The formula is CV = EV – AC.
pmbok- the amount of budget deficit or surplus at a given point in time, expressed as the diffrence between earned value and the actual cost
Definitive estimate
udemy- This estimate type is one of the most accurate. It’s used late in the planning
processes and is associated with bottom-up estimating. You need the WBS in order to create the definitive estimate. The range of variance for the estimate can be from –5 percent to +10 percent.