Formulas Flashcards

1
Q

The Complete Performance Index (TCPI)

A

(BAC - EV) / (BAC - AC)

> 1 harder to complete; < 1 easier to complete

Estimate At Completion (EAC) is the estimated total amount of money needed to be put into the project based on the information available today.

Budget At completion (BAC) is the sum of all budgets established for the work to be performed.

Schedule Performance Index (SPI) is the ratio between Earned Value (EV) and Planned Value (PV), to reflect whether the project work is ahead of, on, or behind schedule in relative terms.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Planned Value (PV)

A

percent of the work complete of where the project should be * budget at completion (BAC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Actual Costs (AC)

A

actual monies spent

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Earned Value (EV)

A

percent complete * budget at completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

cost variance (CV)

A

earned value (EV) - actual costs (AC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

schedule variance (SV)

A

earned value (EV) - planned value (PV)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

cost performance index (CPI)

A

earned value (EV) / actual costs (AC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

schedule performance index (SPI)

A

earned value (EV) / planned value (PV)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

estimate at completion (EAC)

A

budget at completion (BAC) / cost performance index (CPI)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

estimate to complete (ETC)

A

estimate at completion (EAC) - actual costs (AC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

variance at completion (VAC)

A

budget at completion (BAC) - estimate at completion (EAC)