Project Financial Control Flashcards
Financial Control
- Understand current liability as well as the future position
Typical use of cash flow
- Monitor progress of onsite works against programme
- e.g. is the contractor requesting more or less than the original cash flow and
- how is site progress in relation to the programme.
Outline what an S-Curve
- The S shows low expenditure initially with site setup and enabling works being undertaken.
- the majority of the curve involves the most significant outlay and then the
- final section tapers off as the number of trades reduces and snagging is completed.
Purpose of Financial Reporting
- Identify likely final account costs based on current and likely future expenditure.
Contents of a financial report
- Contract Sum
- Variations
- agreed,
- under negotiation
- potential
- Risk allowance expenditure (UPS 2.5% construction and 1.5% employer change)
- Provisional Sum Expenditure,
- Claims,
- Actual Anticipated Cashflow,
Anticipating Variations
- Keeping up to date with the project by communicating with the contractor to understand any issues that might arise.
- E.g. UPS dayworks for breaking out drainage; Provisional Allowance subject to identification of extent of works
- Site level issue
- Prov Sum for Kitchens
What is cost control ?
- Establishing a clear process for how variations are agreed.
- E.g. contractor raises issue or omission.
- Client/EA/QS review issue.
- Ensures all parties become aware of changes
Financial Meetings
- Monthly meetings to review key change.
- Financial reports clearly identified what was agreed,
- what was being negotiated and if an item was only an allowance.
Design risk allocation can be determined through the appropriate choice of procurement route.
- Traditional - Design control but risk held by Client but can impact programme & costs
- D&B - Passed to MC
- CM - Client holds control and risk. Flexible until packages are let.
I am aware of how construction costs are typically forecasted
- Monitor progress of onsite works against programme
- e.g. is the contractor requesting more or less than the original cash flow and
- how is site progress in relation to the programme.
I am aware of the four types of Risk Allowances as set out in New Rules Measurement 1
- Design Development Allowance Levels - Stage 0-1 – 20%, Stage 2 – 15%, Stage 3 – 10%, Stage 4 – 5%
- Employer Change Risk – Largely dependent on the type of Client. For example; are they a commercial developer who is unlikely to make significant post contract changes or are they an occupier who may not have much construction experience and may decide to make significant post contract changes (UPS).
- Employer Other – Similarly to the last point it depends on the client. However, the risk refers to postponement, acceleration and funding issues so can’t readily be foreseen.
- Construction Risk - Construction risk should be allowed for dependent on the unknown elements of the project. Is there an abundance of information for the project or are there still unknown elements of the work or how it is to be carried out? Allowances can vary greatly depending on the risk of a project. Typically an allowance would be in the region of 5-10%. Refurbishment projects typically attract higher allowances due to unknown scope.
I am aware of the mechanisms which are set out within the JCT Design and Build 2016 contract for facilitating change.
- Change from ER’s; Design, Quality or Quantity or Imposition (site access, working hours, reduced working area)
- Employer makes EA aware
- Instruction/EAI (if immediate) or Estimate
- Change Proposal to Contractor
- Contractor Price – Accepted or Negotiated
- MC include OHP, design fees, H&S, programme impact
- Instruction by EA
- Contractor confirms within 7 days
- takes effect from 7 days of confirmation
- If Contractor does not comply Employer/EA can give notice
- 7 days post notice 3rd party can be appointed
I appreciate how financial control and cost reporting can help Clients in understanding the financial status of a project.
Can just Financial Control or Cost Reporting be used? Best worked in conjunction with each other
Q - How might the D&B change process differ to the JCT Standard Building contract?
- Client Direction
- Design Team (D&B MC employs Designer)
- QS Estimate
- MC Quote
- Negotiate
- Instruction CAI
I prepared cost reports on the project including variations along with their current status’ allowing me to effectively manage costs
- Understanding the financial status of the project enabled me to communicate to the client what risks were outstanding and what the likely financial implications were.
- My understanding assisted the client in being able to make decisions that would aid in the successful overall delivery of the project.
- The UPS distribution warehouse project was procured traditionally, and the client was to occupy the building.
- I found that the reporting process was more involved than projects I had worked on where the client was a commercial developer who regularly undertakes construction projects.