Conflict Avoidance Flashcards

1
Q

JCT D&B ADR

A
  • Negotiation (informal).
  • Mediation (formal - not binding).
  • Adjudication (formal – binding).
  • Arbitration (legally binding).
  • Litigation (legal judge binding).
    ADR – All previous are examples except LITIGATION.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Best approach to project Conflict Avoidance

A
  • Proactive management,
  • Clear documentation,
  • Collaborative contractor relationship,
  • Client management,
  • Clear payment terms,
  • meeting minutes,
  • programmes,
  • cost reports,
  • Clear change processes.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Partnering

A
  • Project wide co-operation.
  • Open communication.
  • Multi-party Contract incorporating principles.
  • JCT Constructing Excellence; Risk registers,
  • Risk allocation,
  • KPI’s
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Negotiation –

A
  • Competitive (low-ball) vs Principled (mutual gain).
  • Clear outcomes
  • Challenge
  • Listen
  • Research
  • Walk away
  • Patience
  • See their point of view
  • Focus on their pressure (time/cost)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Mediation –Conciliation

A
  • Does not give opinion/ recommendation. Independent perspective to facilitate settlement.
  • Directs parties to agree on the issue on the basis of what a likely award might be.
  • Conciliation; Similar but makes a RECOMMENDATION. NOT usually binding.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Adjudication process

A
  • Stat requirement under HGCRA or Scheme for Construction Contracts.
  • Invoked at any time.
    5 days’ notice, appoint Adjudicator.
  • 2 days to confirm availability.
  • 7 days to submit evidence.
  • Adjudicator decision in 28 days (can be extended with party permission).
  • Binding until further escalated to Arbitration or Litigation.
  • Introduced under ‘Housing Grants, Construction & Regeneration Act 1996
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Arbitration

A
  • Must be option in contract.
  • Private hearing (not in public eye).
    28 days to appoint single (14 for 2+).
  • Short hearing; Inspecting work, materials etc.
    Written statements.
    1-day hearing.
    Can agree to extend.
    Award in 1 month.
  • Documents only;
    No need for hearing.
    Submit statement and submit formal reply to each other.
    Further questioning or hearing may be requested.
    1-month decision.
  • Full Procedure;
    Comprehensive process used only when previous deemed not sufficient to investigate issue.
  • Cost; Losing party bares costs and Arbitrator can apportion settlement at their own discretion.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Pre-Action Protocol

A
  • Encourage ADR –
  • Ensure both parties have all info –
  • Allow settlement offers
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Litigation

A
  • Formal process undertaken through public (Technology and Construction court)
  • Public Eye (bad publicity - parties can be perceived as uncollaborative)
  • Expensive.
  • Time consuming.
  • Binding subject to appeal.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Expert Witness

A

Provide opinion based one:

  • experience,
  • knowledge
  • expertise.
  • Independent, impartial and unbiased
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

I appreciate the benefit of encouraging parties to resolve disputes away from litigation.

A

ADR

  • Quicker
  • Less expensive
  • Private

Summary of Litigation

⦁ Formal process undertaken through public process.
⦁ Technology and Construction court.
⦁ Public Eye.
⦁ Expensive.
⦁ Time consuming.
⦁ Binding subject to appeal.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly