Conflict Avoidance Flashcards
1
Q
JCT D&B ADR
A
- Negotiation (informal).
- Mediation (formal - not binding).
- Adjudication (formal – binding).
- Arbitration (legally binding).
- Litigation (legal judge binding).
ADR – All previous are examples except LITIGATION.
2
Q
Best approach to project Conflict Avoidance
A
- Proactive management,
- Clear documentation,
- Collaborative contractor relationship,
- Client management,
- Clear payment terms,
- meeting minutes,
- programmes,
- cost reports,
- Clear change processes.
3
Q
Partnering
A
- Project wide co-operation.
- Open communication.
- Multi-party Contract incorporating principles.
- JCT Constructing Excellence; Risk registers,
- Risk allocation,
- KPI’s
4
Q
Negotiation –
A
- Competitive (low-ball) vs Principled (mutual gain).
- Clear outcomes
- Challenge
- Listen
- Research
- Walk away
- Patience
- See their point of view
- Focus on their pressure (time/cost)
5
Q
Mediation –Conciliation
A
- Does not give opinion/ recommendation. Independent perspective to facilitate settlement.
- Directs parties to agree on the issue on the basis of what a likely award might be.
- Conciliation; Similar but makes a RECOMMENDATION. NOT usually binding.
6
Q
Adjudication process
A
- Stat requirement under HGCRA or Scheme for Construction Contracts.
- Invoked at any time.
5 days’ notice, appoint Adjudicator. - 2 days to confirm availability.
- 7 days to submit evidence.
- Adjudicator decision in 28 days (can be extended with party permission).
- Binding until further escalated to Arbitration or Litigation.
- Introduced under ‘Housing Grants, Construction & Regeneration Act 1996
7
Q
Arbitration
A
- Must be option in contract.
- Private hearing (not in public eye).
28 days to appoint single (14 for 2+). - Short hearing; Inspecting work, materials etc.
Written statements.
1-day hearing.
Can agree to extend.
Award in 1 month. - Documents only;
No need for hearing.
Submit statement and submit formal reply to each other.
Further questioning or hearing may be requested.
1-month decision. - Full Procedure;
Comprehensive process used only when previous deemed not sufficient to investigate issue. - Cost; Losing party bares costs and Arbitrator can apportion settlement at their own discretion.
8
Q
Pre-Action Protocol
A
- Encourage ADR –
- Ensure both parties have all info –
- Allow settlement offers
9
Q
Litigation
A
- Formal process undertaken through public (Technology and Construction court)
- Public Eye (bad publicity - parties can be perceived as uncollaborative)
- Expensive.
- Time consuming.
- Binding subject to appeal.
10
Q
Expert Witness
A
Provide opinion based one:
- experience,
- knowledge
- expertise.
- Independent, impartial and unbiased
11
Q
I appreciate the benefit of encouraging parties to resolve disputes away from litigation.
A
ADR
- Quicker
- Less expensive
- Private
Summary of Litigation
⦁ Formal process undertaken through public process.
⦁ Technology and Construction court.
⦁ Public Eye.
⦁ Expensive.
⦁ Time consuming.
⦁ Binding subject to appeal.