Design Economics & Cost Planning Flashcards
Inflation
- TPI - Cost Plan Date - Tender return date.
- CPI - Tender return date - Construction mid-point date
Cost Plan NRM1
- Facilitating works,
- Building Works,
- Preliminaries,
- OH&P –
WORKS COST ESTIMATE – - Project Design Team Fee,
- Other Project Costs –
BASE COST ESTIMATE – - Design Development Risk,
- Construction Risk,
- Employer Change risk,
- Employer other risk –
COST LIMIT EXC. INFLATION - Tender Inflation,
- Construction Inflation
COST LIMIT INC INFLATION
Calculating unit rates from first principles
- Tiling 10m2 =
- Labour; 16 hours @ £15ph=£240
- Materials; Tiles, grout, adhesive = £300
- Total £540
- 5% OHP= £567
- 10m2 = £57/m2
Building Works:
- 0 Facilitating works - Demolition, ground improvement, asbestos removal
- 1 Substructure – Foundations, Ground Floor Slab, Piling
- 2 Superstructure – Frame, Roof, Upper Floors, External & Internal Walls, External & Internal Doors,
- 3 Finishes – Wall, Floor, Ceiling
- 4 Fittings, Furnishings and Equipment (FFE) – Kitchens, Bathrooms, Furniture
- 5 Services – Heating, Electrics, Ventilation, Lighting, Waste
- 6 Prefabricated Buildings– Guard House, bath pods (student resi/budget hotel)
- 7 Work to Existing Buildings – Support to adjacent buildings
- 8 External Works – Roads, Paving, Planting, External Services (Utilities), Drainage
Preliminaries
- Items that cannot be attributed to a specific element (building works NRM 1).
- E.g. Staff,
- welfare,
- temp. services,
- security,
- safety,
- site records,
- completion requirements,
- cleaning,
- insurance.
- 12% Prelims on Meole Brace
- Increase if challenging city centre site
OH&P
- Head office admin and MC’s return on capital investment.
Design Development Risk
- Risks associate with Design Development;
- planning change,
- legal agreements,
- stat reqs,
- tender delays
- e.g. design novelty (untested),
- inadequate/unclear info (site investigation),
- use of provisional sums
Typical Cost Plan Exclusion
- VAT,
- Land acquisition,
- Land remediation tax relief,
- insurances,
- finance costs
NRMs
- 1; Order of cost estimating and Cost Planning
- 2; Detailed measurement for building works
- 3; Building maintenance works
RIBA stages
- 0 Strategic - Identify Client requirements, feasibility (budget and risks) Cost Model (£/m2)
- 1 Preparation - Project brief & outcomes, quality aspirations, further feasibility, site info and surveys, programme, project execution plan Order of Cost Estimate
- 2 Concept - Arch concept design, outline specification Formal Cost Plan 1
- 3 Spatial - Developed design and costing Formal Cost Plan 2 x detailed foundation, M&E layouts, finishes schedule
- 4 Technical - Developed arc, eng, civil design, building systems PTE
- 5 Construction
- 6 Handover
- 7 In Use
Cost Plan Delivery
- Standard format NRM 1
- Assumptions, Exclusions, Basis
- comp checked,
- peer review,
- emailed pdf copy,
- phone call - discuss anything
Cost Planning Purpose
- Feasibility (Proceed?)
- Facilitate Design Choice (spec level)
- Cost management (Budget limit)
- Anticipate Tender Returns
Cost Plan Contents
- Executive Summary,
- Cost Reconciliation,
- Elemental Summary
- Elemental Breakdown,
- Basis/Assumptions/Exclusions
- Inflation Statement
Value Engineering
Value Management
- VE Process that seeks to deliver the same requirements but at a lower cost.
- VM Clearly communicates the clients requirements by identifying what is a need and
- what is a want and aligning these with the budget.
- Needs first wants second.
I am aware of how Estimating and Cost Planning should be approached under the guidance of RICS New Rules of Measurement 1 (Building Works).
Building Works:
1 Substructure – Foundations, Ground Floor Slab, Piling
2 Superstructure – Frame, Roof, Upper Floors, External & Internal Walls, External & Internal Doors,
3 Finishes – Wall, Floor, Ceiling
4 Fittings, Furnishings and Equipment (FFE) – Kitchens, Bathrooms, Furniture
5 Services – Heating, Electrics, Ventilation, Lighting, Waste
6 Prefabricated Buildings – Guard House, bath pods (student resi/budget hotel)
7 Work to Existing Buildings – Support to adjacent buildings
8 External Works – Roads, Paving, Planting, External Services (Utilities), Drainage