Client Care Flashcards

1
Q

Significance of RICS Client Care

A
  • Fundamental to surveying industry (no clients = no work)
  • Reputation is based on the enhanced service and protection RICS surveyors provide
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Specialism

A
  • Identify work outside of your specialism
  • e.g. VAT. Legal disputes falls outside standard scope of service
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What would you outline to CLient when confirming Fees?

A
  • T&C’s (Insurance, Payment, Dispute resolution)
  • Scope,
  • Exclusions,
  • Assumptions (programme)
  • Calculate cost; Individual resource, rate, time, scope, profit
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

QS Scope
(Limits of PI insurance)

A
  • Pre-Contract;
  • Feasibility estimate,
  • tendering & procurement advice,
  • cost plan development,
  • tender documents,
  • tender process
  • Post-contract;
  • Valuations,
  • variations control/costing, #
    SUPLLEMNTARY
  • contract admin (EA)
  • VE,
  • life cycle reports,
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Appointment doc

A
  • Details,
  • warrantY Obligations, ,
  • payment terms,
  • scope of services,
  • additional services/ EXCLUSIONs
  • termination,
  • fees
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Invitation to Tender (ITT)

A
  • Cleary sets out tender process for contractor.
  • Certificate of bona fide tender can help in sorting out contractors who may not be willing to commit / do not have capacity.
  • Can aids in creating competition by discounting contractors not serious early on.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Significance of Site investigation and Statutory requirements
Impact on cost and programme

A
  • Basis for design and overall programme.
  • Establish if ground needs remediation or specialist foundations?
  • If existing building it should be confirmed Asbestos is not present.
  • Confirm planning pre-commencement conditions are satisfied. e.g. is there any biodiversity or species protection measures required?
  • Failing to understand components such as this could significantly impact on cost and programme so clarification of investigation should be sought from the outset.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Procurement reports

A
  • Meole Brace;
  • Exec summary,
  • Intro,
  • Outline – D&B, Con. Man, Trad Comparison and Risk allocation,
  • Conclusion/ Recommendation
  • Advise the client on what the best approach to take based on their requirements.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Establishing a client’s objectives

A
  • Wrexham;
  • cost and design risk to contractor
  • Fixed programme,
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Calculating fees for professional services

A
  • Whitwell; Resource required for initial report
  • time & cost (seniority e.g. GEC vs Director). Ongoing
  • Site visits,
  • meeting,
  • information request and review,
  • compilation of report
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Client feedback

A

CX App
⦁ 10 Questions
⦁ 1-10 scale w comments

⦁ Once or twice a year.
⦁ Regularly but not so frequently that becomes a chore

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Change control process

A
  • Change from ER’s; Design, Quality or Quantity or Imposition (site access, working hours, reduced working area)
  • Employer makes EA aware
  • Change Proposal to Contractor
  • Contractor Price, OHP, Programme - has 14 day (21 SBC)
  • Accepted or Negotiated
  • Instruction by EA
  • Contractor confirms within 7 days
  • takes effect from 7 days of confirmation
  • If Contractor does not comply Employer/EA can give notice
  • 7 days post notice 3rd party can be appointed
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

UPS Final Account Negotiation

A
  • Gap between Contractor and my assessment
  • Most of the disparity related to a dispute in relation to an L&E claim whereby the Contractor was claiming for 5 weeks of disruption to their works following an Early Use instruction allowing a follow on contractor to store their materials on site.
  • I disputed the extent of their claim as the Early Use instruction had been agreed with them and had only impacted on their ability to deliver the works for 2 of the 5 weeks (M&E cabin located at new car park)
  • I outlined situation to the client who confirmed that they were keen to conclude the final account and confirmed they would accept 50% of the current disparity (circa £100k)
  • I initially went back to the contractor stating that 30% i.e. £30k would be acceptable
  • MC came back at 50%
  • 40% was eventually agreed bettering clients position by 10%
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Complaints process

A
  • Expression of dissatisfaction.
  • Stage 1; Client formalises complaint in writing.
  • Company acknowledges in 7 days and
  • respond within 21 and notify PI.
  • Stage 2; Redress scheme
  • Arcadis - Scheme for Arbitration Services
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Cost Report - Client Update
On the project I regularly issued the cost reports to the Client to provide clarity over the project finance status along with any associated changes.
Outline inclusions

A
  • Minimum expectation to provide monthly cost report –
  • outlining variations (agreed, negotiation, risk)
  • Apportion expenditure above contract sum into Employer Change, Construction
  • Prov sum,
  • Claims,
  • Programme.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly