Project Finance Flashcards

1
Q

What are the pricing mechanism to arrive to a contract sum?

A

Bill of quantities, activity schedule, schedule of rates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the factors affecting outturn of the cost?

A

Fixed costs, variable costs, variations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is cost reporting?

A

The purpose of cost reporting is to inform the client the likely outturn cost of the construction project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the three levels of cost reporting?

A

construction cost report, project cost report, programme cost report, detailed cost report

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the expected content of a construction cost report? Project cost report?

A

construction cost report - contract sum, adjustments of variations, adjustments of variable costs, adjustments of fluctuations, claim for loss/expense, adjustment on risk allowance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How often should cost reporting be reported?

A

Common practice is to value the works on a monthly basis, therefore it is recommended that cost reports are updated and issued on a monthly basis.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How is contingency generally reported and updated?

A

General risk allowance maintenance method, General risk allowance progressive release method

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is risk? And how what is the role of QS in risk management?

A

Risk is the potential for an event or condition to impact the project’s objectives, including cost, schedule, quality, or scope.
QS roles as follows:
1) Helps in identifying, assessing and monitoring risks
2) Valuing risks under risk registers
3) Allowing contingency allowance to cover risks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How would carry out risk analysis and assessment?

A

Identify, assess, mitigate, monitor and review

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is expected monetary value method?

A

EMV=ProbabilityofRiskEvent×MonetaryImpactofRiskEvent

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

In fitout refurbishment project, how did you prepare a cost report?

A

1) Gather the pricing document arriving to contract sum
2) Reflect the contract sum, adjustment of measurable works, variable costs, variations, fluctuations, claims and risk allowances
3) Reflect these against budgets

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

How did you prepare a payment register? What is it for?

A

Payment register aids in monitoring cashflow to ensure that payments are made in timely manner. I would refer to the contract as to plot the payment timelines and populate a register from it.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

In a bahrain government project, what are required in claiming for provisional sum?

A

Reference provisional sum details, instruction from the engineer, cost breakdown, invoices or payment vouchers from supply chain, contractual compliances

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Is there any early warning mechanism in the contract? How is this dealt with?

A

Identify issues early, prompt notification, hold early warning meetings, implement mitigation measures, document and monitor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is a cash flow report?

A

It is prediction of the flow of cash in and out of a project over time. It ensures sufficient funds available to meet project obligation at a given a time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How would you produce a cash flow report?

A

-Collect essential data such as contract, schedule, pricing schedules, payment terms
- Split values into elements and consider programme into its distribution
- Obtaning drawdown schedule from stakeholder will aid
- Alternative is to use previous cashflow from similar scheme

17
Q

What was your advice here other than logging changes?

A

Monitor the implementation of LVR changes, to ensure adequate budget has been allocate to accommodate these changes.