Contract Administration Flashcards

1
Q

What are the roles of a contract administrator?

A
  • Acting as an impartial third party that ensures Employer and Contractor fulfills its obligations in accordance with the contract.
  • Contract supervision and administration
  • Issuing instructions and variations
  • Approval of contractor’s documents
  • Monitoring progress and quality
  • Certifying payments
  • Time and delay management
  • Dispute resolution
  • Issuing taking over certificate
  • Managing defects liability period
  • Risk and claim management
  • Communication and reporting
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Did this adhered to the change control process on your project, if not what is the standard process?

A

Yes, a client instruction has been issued. A change must be instructed by the client/contract admin in this regard.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

In fitout project, how do you treat contractor’s payment application?

A

I review the contractual terms with regards to payments.
I review the contractor’s payment application and ensure that all supporting documents are in place
I inspect the works on site to verify the actual works completed in the interim.
After assessment, I would discuss clarification with contractor if required.
I would issue the payment certificate within 28 days of the contractor’s application
I keep track and ensure that payments are released to the contractor 28 days after the payment certificate.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the payment timeline in this project?

A

The contractor’s payment application has to be submitted on a monthly basis. The client reviews the application and agrees the valuation with contractor. The payment need to done after 21 days from receipt of contractor’s application.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How did you treat retention and advance payment recovery in this project?

A

Depending on the type contract, typically 10% of the contract sum is released after receipt of performance guarantee, and is recovered depending on particular conditions stated in the contract, typically 5-10% of the value of the works done.
Retention is also recovered at % stated in the contract for every interim payment typically 5%. Once taking over certificate is issued after completion of works, half of the retention will be released and the other half once DLP is lapsed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly