Contract Administration Flashcards
What are the roles of a contract administrator?
- Acting as an impartial third party that ensures Employer and Contractor fulfills its obligations in accordance with the contract.
- Contract supervision and administration
- Issuing instructions and variations
- Approval of contractor’s documents
- Monitoring progress and quality
- Certifying payments
- Time and delay management
- Dispute resolution
- Issuing taking over certificate
- Managing defects liability period
- Risk and claim management
- Communication and reporting
Did this adhered to the change control process on your project, if not what is the standard process?
Yes, a client instruction has been issued. A change must be instructed by the client/contract admin in this regard.
What is the payment timeline in this project?
The contractor’s payment application has to be submitted on a monthly basis. The client reviews the application and agrees the valuation with contractor. The payment need to done after 21 days from receipt of contractor’s application.
How did you apply contract administration in an office development project in Germany?
An invoice for additional works has been fully invoiced to the client without prior review. Together with the legal technical advisor, I acted impartialy by advising the client to release on account payment of 80% of the claim in accordance with BGB Clause 650c, while the value of the works is being agreed and any excess payment will be deducted in the next interim payment.
In fitout project, how do you treat contractor’s payment application?
I review the contractual terms with regards to payments.
I review the contractor’s payment application and ensure that all supporting documents are in place
I inspect the works on site to verify the actual works completed in the interim.
After assessment, I would discuss clarification with contractor if required.
I would issue the payment certificate within 28 days of the contractor’s application
I keep track and ensure that payments are released to the contractor 28 days after the payment certificate.
How did you treat retention and advance payment recovery in this project?
Depending on the type contract, typically 10% of the contract sum is released after receipt of performance guarantee, and is recovered depending on particular conditions stated in the contract, typically 5-10% of the value of the works done.
Retention is also recovered at % stated in the contract for every interim payment typically 5%. Once taking over certificate is issued after completion of works, half of the retention will be released and the other half once DLP is lapsed.