Commercial Management Flashcards

1
Q

What is a the role of the commerical manager?

A
  • maximise the potential of a business in terms of profitability.
  • monitors, or controls,internal processes such as production, and manages external relationships with customers, clients and trading partners
  • monitors financial performance (both forecast and achieved)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are main areas of commercial management?

A
  • Estimates, value engineering, supply chain management, valuing work, cash flow analysis
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Provide commercial decisions that improved cost efficiency?

A

EVA, cost/value analysis, risk and contingency allowances, digital solutions, consider just-in-time delivery to avoid storages, consider leasing v purchases of equipment,

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Provide mitigation against material price increases?

A

Paying upfront to avoid price fluctuations, looking for suppliers company-wide rather than per project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How are rates build up?

A

Labour, plant, materials and subcontractors, along with allowances for insurance, bonds, site overhead, risk and contractors’ profit

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the five columns comprising a price?

A

Labour, plant, material, subcon, other

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How is overhead typically calculated?

A

According to NRM1, OH are initially estimate by % against the works estimate. As the scope are getting defined, the prices are defined further.

The amount of company overhead recovery is generally determined by
expressing the budgeted annual overheads as a percentage of budgeted turnover and applied as a proportion of the cost of individual contracts.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is cost/value reconciliation?

A

Comparing the internal valuation with the costs incurred

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How would you prepare CVR? How do you ensure that it is up to date?

A
  • I would determine the cumulative costs date, cutoff date may coincide with agreed accounting period
  • I would check the fluctuationms all works in progress are accounted, risk items have been agreed
  • I will determine the current profitability vs original budgeted values
    Keep up to date
  • Forecast revenue on variations must be reported only when agreed.
  • Reduced profit is expected if VO are paid on account
  • Risk/contingency are retained
  • Regular arrange meeting to conclude agreement on VOs to avoid backlogs
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Are there any other techniques available?

A

Cost to complete exercise, EVA, Use of IT

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the EVA?

A

Earned value analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

How would you mitigate project that is behind programme?

A
  • Review the current status of the programme
  • Reviewing staffing/resource levels to gain efficiencies
  • Discuss balancing of programme sequence as catch up plan
  • Check possibility of accelaration against additional costs to be incurred
  • Check for programme float to absorb delay
  • Review cause of delay, to check EOT is applicable.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is an accrual?

A

It is made within financial systems taking into account anticipated invoices that are not yet paid
Liability due to subcon vs amount paid to date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What process would you put in place when making contra charges?

A
  • Supporting documents such photographs, invoices, etc.
  • Records of any material replacement, attendances to assist subcon
  • Issue early warning to subcon to allow rectification
  • Agree with subcon before deductions
  • Deal contra charges on payment certificate, pay less notices or final accounts separately
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is back to back exercise?

A

It is when similar contractual mechanism are applied to supply chain of the main contractor, to ensure cashflow and monitoring of works done throughout the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Why are accounts are in cumulative values?

A

To ensure the full extent of financial info is accounted and to avoid potential double counting if invoices are made in period

17
Q

What contract administration would you implement in commercial management?

A
  • Utilize payment schedules
  • Run final accounts considering adjustments, claim, variations
  • Regularly review revised drawings to ensure variations are captured
18
Q

How would resolve subcon final accounts?

A
  • Maintain running final accounts
  • prepare subcontract, final account submission, details of VO and takeoff measures
  • Run through agreed and pending adjustment in meeting
  • Circulate final ccount statement after decisions and agreement are made
19
Q

How are subcontractor payment assessed?

A

For lumpsum/remeasurable - shall be measured and agreed with Operations Manager
For cost plus/target sum - should be supported with substantiation

20
Q

How did you review and corrected a cash flow structure in an Atrium Mall?

A

I started reviewing the subontract (advance payment and payment terms), programme, budget, element of works against the existing cash flow structure. It has been apparent that cash distribution is not in line with the programme, therefore the cash allocation needs to be aligned.

21
Q

What are the typical considerations when setting up a cashflow?

A

Contract, programme, budget, element of works

22
Q

Why is the financing required despite of advance payment?

A

The advance payment can not covered the initial expenditure to produce the precast elements in the factory.

23
Q

How did you able to identify the errors in the cashflow?

A

The cash allocation has not been reflected correctly in the programme.

24
Q

How did you conduct selection of subcontractors?

A
  • I formed a list of subcontractors we have worked with, also reached out to other subcontractors with similar experience and obtained EOI to interested parties.
  • PQQ has been conducted to interested contractors where a list of subcontractor tenderers are made.
  • I prepared the pricing document to assist the operations manager in issuing tender.
  • After receiving returns, I review their offers and apply necessary normalisation to ensure all part of the works are budgeted accordingly.
  • I then prepared the commercial tender report outlining the commercial tender process and sent it to our operations manager for review, in parallel with technical components of the tender.
25
Q

What is the vendor management in place?

A

Maintaining list of service/goods providers depending on trades.

26
Q

What is subcontracting? What the advantages and disadvantages?

A

Subcontracting is a business practice where a company (the main contractor) hires another company or individual (the subcontractor) to complete a part of a project or provide services that the main contractor cannot or does not wish to handle internally
Adv - cost efficiency, access to expertise, flexible and scalable, reduced risk and liability
Disadv - Loss of control, risk of poor quality, confidentiality risk, dependency, higher cost in longer term

27
Q

What is a nominated subcontractor?

A

subcontractor nominated by Employer and stated under contract. MC will be responsible for the performance of the subcontractor

28
Q

What are the different payment/valuation methods?

A

Stage Payments, Milestone Payment, Payment from an activity schedule; Third party certification

29
Q
A