Project Finance Flashcards

1
Q

What are the different types of financial control procedures?

A

1) Cashflow forecasts
2) Cost reporting (cost to completion)
3) Life cycle costing
4) Applications for payment
5) Monthly liabilities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is a cashflow forecast and when would it be used?

A

A financial planning tool used to show the predicted flow of cash in and out of a project for the duration of the project and is typically updated on a monthly basis.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the advantages of a cashflow forecast to the employer?

A

1) Planning expenditure to receive relevant funding
2) Identify months with shortfalls and address
3) Used as a sense check for monthly valuations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the purpose of cost reporting to project completion?

A

1) To identify outturn costs and track the trajectory of the project
2) To identify week performing areas and address accordingly
3) To understand whether the project is under or over performing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is life cycle costing?

A

A method of measuring the lifetime costs of an asset or project by adapting the design to adopt a more holistic view of the costs associated with the asset throughout its lifetime, as opposed to just the initial costs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is an application for payment?

A

An application for payment is a document issued to by the Contractor to the Client which states the amount of money they believe to be due at the agreed valuation date.

It should include the following:

Prelims
Measured works
Materials on site
Variations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are monthly liabilities?

A

Monthly liabilities is a submission issued by all projects which captures the costs a project is liable for at the end of each month. This is not a snapshot of what has been paid, but a snapshot of the amount owed and therefore includes unpaid invoices and unagreed variations.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is a CVR?

A

Cost Value Reconciliation

The process of reconciling actual cost against value in order to determine the overall profitability.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is a CRF and what are the outputs?

A

The CRF stands for contract review form which is a monthly project review to determine the performance of a business. It discusses the outputs such as commercial, Programme, health and safety, client feedback and quality.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the process of reviewing planned outputs against actual outputs called?

A

Earned value analysis

The process of reviewing the progress made and the commercial impact to forecast the final costs and completion date based on trend analysis.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are the three main components of earned value analysis?

A

PV (Planned Value) - The planned value of works complete based on time in isolation
EV (Estimated Value) - the actual value of works complete
AC (Actual Cost) - The actual cost incurred

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What can Earned Value analysis identify?

A

1) Under/overspends
2) Project delays

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is CPI in the context of earned value management?

A

Cost performance index - The method of calculating cost efficiency of a specific project?

CPI = EV / AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is SPI in the context of earned value management?

A

Schedule performance index - A measure of planned progress (EV) against actual progress

SPI = EV / PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What does a CPI value of greater than 1 show?

A

The project is performing well against budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What does a CPI value of less than 1 show?

A

The project is performing poor against budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What does a SPI value of greater than 1 show?

A

The project is ahead of schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What does a SPI value of less than 1 show?

A

The project is behind schedule

19
Q

What is planned output?

A

The planned percentage of works complete at a certain point in time

20
Q

What is planned value?

A

The expected costs at a point in time based on the planned output

21
Q

What is actual output?

A

The actual percentage complete at a certain point in time

22
Q

What are actual costs?

A

The actual amount of costs incurred at a point in time

23
Q

What is the difference between a cost and cashflow forecast?

A

A cost flow forecast is a measure of the forecasted cost outflow over a period of time, whereas a cashflow looks at both the cost incurred and cash received to determine the net cash position.

24
Q

When would you use a cost flow forecast rather than a cashflow forecast?

A

A costflow forecast is used to help determine the cashflow forecast, it is used specifically toward the beginning of a project when the value of works is minor yet you have incurred costs for staff, materials, design etc.

25
Q

What is a risk allowance?

A

A monetary or programme allowance made for the occurrence of uncertain events materalising

26
Q

What would determine the amount allowed for risks in a construction project?

A

A true valuation of the risk occurring multiplied by the probability and severity factor of it occurring.

27
Q

You mention your monthly project finance cycle, please can you take me through this?

A

1) Weekly BPR, issued every Tuesday included labour, plant and materials costs
2) CIM1, the cumulative liability for cost heads is reported on the last working day of each month
3) CIM2, the monthly reporting of the net cash position at a point in time, submitted the first week end of each month
4) Contract Review - monthly review of profit and loss of the project based on forecasted cost against forecast value

28
Q

How would you forecast costs?

A

1) Identify past trends and continue into future
2) Review programme activities and make allowances for the associated costs
3) Speak with package manager to determine what activities are likely to be complete

29
Q

What is the benefit of a short term cashflow forecast?

A

Short term cashflow forecasts are more focused on near future activities and are therefore give a more accurate representation of costs. This allows the business to address any high cost months which arise from bottle necked programmes.

30
Q

You mentioned that you advise your client on the expected cashflow position, what is the purpose of this and is it a contractual requirement?

A

This was not a contractual requirement, but a goodwill gesture to maintain a good working relationship. The client was a private and therefore obtained funding from the bank to pay for the works complete to my company. Given I worked for the contractor I was much closer to the detail and was best placed to advise on the completion of key activities.

31
Q

When would you show an increase when reporting costs?

A

If the cost was genuine and there was no contingency available or the contingency allowance was needed for other future costs.

32
Q

When would you offset a cost increase with contingency?

A

If the contingency covered the nature of the cost increase or if the full contingency of another heading was not going to be used.

33
Q

When would you report a saving during the project lifecycle?

A

Due to the nature of construction, I would move any savings made into a contingency pot to cover any future cost incurred, I would then show the saving towards the end of the project lifecycle?

34
Q

Please could you explain your understanding of the term resilience?

A

Resilience is a lump sum contingency pot to deal with any unexpected costs.

35
Q

You mention that you do cashflow forecast both internally and externally, can you please explain how your reporting’s might differ?

A

Internally i may have to consider whether to client always pays on time, weather they are flexible or rigid within payments, willingness ti pay on account.

36
Q

Can you advise of a time you have had to advise senior commercial leadership of an increase the EFC?

A

During the construction of the residential project I worked on, we incurred significant water ingress through rainfall. At the time there were no allowances made for the repair of the damage. I therefore reported this in our EFC as well as a forecast for future damage as the building was not water tight.

37
Q

Can you advise of a time you have had to advise senior commercial leadership of an increase the EFC?

A

During my case study, i recognised that the subcontractor we had fixed a cost with was under delivering despite charging a premium. Knowing an alternative subcontractor was willing to carry out the same works on dayworks based on a 3 week programme, i recognised an opportunity to reduce the costs whilst mitigating the risk of further delays.

38
Q

What methods could you adopt to avoid cost increases on your project?

A

1) Robust control of costs
2) Use of provisional sums with client
3) Value engineering

39
Q

How would you estimate a contingency for your project?

A

I would calculate this based on a percentage of each works package dependent on the complexity of the scope and the risks involved, the higher of both of these the higher the % I would apply.

If the contingency was specific, I would try to forecast a contingency based on the known facts. For example, on the residential project i knew there would be future water damage, so I took a view on the areas that weren’t water tights and made an allowance based on the contract some of said areas for reworks.

40
Q

Can you please tell me what you would change about the way you currently report on costs on your project?

A

I would ensure there is absolute alignment with the project WBS code when raising new orders for materials and plant. I would make the headings clear, and ensure that all codes are approve by the owner of the feeder sheet from commercial before the order being placed. This would give us a clear indication of whether we were likely to go over the budget, enabling my project to focus on key overspends.

41
Q

How would you report on the costs of a performance bond?

A

This would be considered a sundry cost which should have a budget allocated against it.

42
Q

What are your companies rules around reporting unimplemented/unagreed change?

A

Only report on value when it is highly probable that it will be implemented (80% or more sure)

43
Q

What are your companies rules around reporting insurance claims?

A

Only report on value when it is almost certain (95% or more)

44
Q

Outside of your write ups, please can you provide another example of when you have demonstrated good project finance skills?

A

1) NTT procured a lot of specialist MEP materials
2) Important review this in depth
3) Created my own materials EFC
4) Included budget + client change against orders let, CTD, and EFC
5) This was managed and advised to the commercial director on a monthly basis