Project Finance Flashcards
What are the different types of financial control procedures?
1) Cashflow forecasts
2) Cost reporting (cost to completion)
3) Life cycle costing
4) Applications for payment
5) Monthly liabilities
What is a cashflow forecast and when would it be used?
A financial planning tool used to show the predicted flow of cash in and out of a project for the duration of the project and is typically updated on a monthly basis.
What are the advantages of a cashflow forecast to the employer?
1) Planning expenditure to receive relevant funding
2) Identify months with shortfalls and address
3) Used as a sense check for monthly valuations
What is the purpose of cost reporting to project completion?
1) To identify outturn costs and track the trajectory of the project
2) To identify week performing areas and address accordingly
3) To understand whether the project is under or over performing
What is life cycle costing?
A method of measuring the lifetime costs of an asset or project by adapting the design to adopt a more holistic view of the costs associated with the asset throughout its lifetime, as opposed to just the initial costs.
What is an application for payment?
An application for payment is a document issued to by the Contractor to the Client which states the amount of money they believe to be due at the agreed valuation date.
It should include the following:
Prelims
Measured works
Materials on site
Variations
What are monthly liabilities?
Monthly liabilities is a submission issued by all projects which captures the costs a project is liable for at the end of each month. This is not a snapshot of what has been paid, but a snapshot of the amount owed and therefore includes unpaid invoices and unagreed variations.
What is a CVR?
Cost Value Reconciliation
The process of reconciling actual cost against value in order to determine the overall profitability.
What is a CRF and what are the outputs?
The CRF stands for contract review form which is a monthly project review to determine the performance of a business. It discusses the outputs such as commercial, Programme, health and safety, client feedback and quality.
What is the process of reviewing planned outputs against actual outputs called?
Earned value analysis
The process of reviewing the progress made and the commercial impact to forecast the final costs and completion date based on trend analysis.
What are the three main components of earned value analysis?
PV (Planned Value) - The planned value of works complete based on time in isolation
EV (Estimated Value) - the actual value of works complete
AC (Actual Cost) - The actual cost incurred
What can Earned Value analysis identify?
1) Under/overspends
2) Project delays
What is CPI in the context of earned value management?
Cost performance index - The method of calculating cost efficiency of a specific project?
CPI = EV / AC
What is SPI in the context of earned value management?
Schedule performance index - A measure of planned progress (EV) against actual progress
SPI = EV / PV
What does a CPI value of greater than 1 show?
The project is performing well against budget
What does a CPI value of less than 1 show?
The project is performing poor against budget
What does a SPI value of greater than 1 show?
The project is ahead of schedule