Contract Practise Flashcards
What does JCT stand for?
Joint Contracts Tribunal
What are some of the contracts in the JCT family?
1) Standard building contracts
2) Minor works building contract
3) Design & build contract
4) Construction management contract
5) Repairs & maintenance contract
What are the key characteristics that influence what contract is used?
1) Size & value of the project
2) Appetite for risk
3) Experience of the client
4) Project priorities (time, quality, cost)
What are relevant events?
A set of events which would cause a delay to the contractor through no fault of their own, entitling the contractor to an extension of time thus moving the contract completion date.
Can you provide three examples of a relevant event?
1) Exceptionally adverse weather
2) Force Majeure
3) Impediment/prevention/default by the employer
What is force majeure?
1) An act of god which is out of the contractors control such as natural disasters
Can you give three examples of a force majeure event?
1) Act or threats of terrorism
2) Riots/strikes
3) War
What happens when a relevant event occurs?
1) Contractor notifies the employer with a notice of delay
2) Contractor identifies the material circumstances of the delay and the relevant event related
3) He provides an assessment of the time impact where possible
4) The contractor reviews the notice of delay and responds as soon as reasonably possible
5) He either concludes his rejection of the notice of delay or acceptance including the extension of time granted.
If a relevant event is accepted does this entitle the contractor to automatic loss and expense?
Not always, the event must also be a relevant matter to warrant recovery of loss and expense.
What are relevant matters?
A relevant matter is a matter which materially impacts the progress of works. If a relevant occurs it may entitle the contractor to recover any loss and expense as a result of any impediment or prevention, bringing them back to the commercial position they would have been in had the matter not occurred.
Give three examples of a relevant matter?
1) Prevented access to part of the site
2) Delays to design information or instructions
3) Disruption caused by works carried out by the employer
What is the difference between a relevant event and a relevant matter?
A relevant event entitles the contractor to additional time, whereas a relevant matter entitles the contractor to additional costs.
What is a loss & expense claim?
An attempt by the contractor to recover costs ascertained as a direct impact of any failure caused by employer, usually delays.
Name three common heads of claim for loss and expense?
1) Prolongation
2) Productivity loss
3) Additional storage costs
Can the contractor refuse to give partial possession to the employer?
Yes, the contractor must consent to giving partial possession but it cannot be unreasonably withheld. The Contractor may withhold if giving partial possession may hinder their ability to complete the remainder of his work.
Name three implications of partial possession?
1) Contractor no longer liable for LAD’s relevant to that area of works
2) half of the retention to be released for that area of works
3) Contractor is no longer responsible for any damage to that area of works
4) The employer is responsible for the insurance of that element of works
What is the difference between sectional and partial completion of the works?
Sectional completion is preplanned and agreed in the contract before the works commence, whereas partial completion is requested during the construction phase of the works.
What are the main options for insuring the works under a JCT contract?
Option A - Contractor take out joint names all risk insurance for the works
Option B - Employer takes out joint names all risk insurance for the works
Option C - Employer takes out all risk insurance for the works and insures against specified perils for the existing structure
What is a Contractors ‘All Risk’ insurance?
1) Insurance that covers physical loss or damage to the works being undertaken
2) Sometimes referred to as ‘Car Insurance’
3) The policy cover will pay for the repair or replacement of the damaged works
What is a specified Peril?
Significant events which may occur on site causing significant damage to the works
Includes things like:
1) Flood through burst water pipes
2) Fires
3) Earthquakes
What is a subrogation?
A concept whereby an insurer who has paid out on loss, can step into the shoes of the claimant in order to sue the guilty party for the loss caused.
What is joint names insurance policy?
1) A type of joint insurance (2 or more parties)
2) Under a joint names policy the insurer has no right to subrogate against any of the insured parties
What does NEC stand for?
New Engineering Contracts
What does ECC stand for?
Engineering and construction contract
Please give an overview of NEC ECC contract?
1) Can be used for any business sector, but better suited for large/long lasting projects where collaboration is key to the project success.
2) No reference to the QS in the contract
3) PM assumes full responsibility on behalf of employer
4) Consider to be more administrative due to EWN, NCE program obligations
5) Contract requirement to issue periodic program for acceptance
6) Risk management tools in place to avoid high costs associate with change
From your personal experience, can you give 3 advantages of using an NEC ECC contractor over the JCT?
1) The requirement to issue monthly programs makes it more clearer who is at fault for delays, avoiding long drawn out disputes at final account stage.
2) The proactive use of early warning helps avoid or mitigate risks before they occur which saves cost and time.
3) It is written in plain English and includes time scales for actions to both parties which forces both parties to act quickly and agree change programs swiftly.
What are the 6 main options of NEC contracts?
Option A - Fixed price activity schedule
Option B - Fixed price bill of quantities
Option C - Target cost with activity schedules
Option D - Target cost with bill of quantities
Option E - Cost reimbursable
Option F - Management contract
Can you give an overview of an NEC option A contract please?
Fixed price activity schedule
1) Contractor prices project at a point in time at a fixed price with the contractor taking on full risk of the construction activities
2) Contract value can only be amended through implemented compensation events
3) Payments is only made against completed activities within the activity schedule
4) Suitable for more simple traditional or design and build contracts
Can you give an overview of an NEC option B contract please?
Fixed price bill of quantities
1) Contractor fixes their price carrying all construction risks.
2) Contractor can claim based on the % of works complete for each bill of quantities item.
Can you give an overview of an NEC option C contract please?
Target cost with an activity schedule
1) The target cost is agreed based on the defined costs + fee, but the outturn financial risk are shared between the Employer and Contractor.
2) The target cost may increase or decrease based on implemented compensation events
3) The employer may disallow costs that are not in accordance with the schedule of cost components
4) Should the final cost exceed the agreed target cost, the employer will share the pain based on the agreed split
5) Should the final cost fall below the agreed target cost, the employer will share the gain based on the agreed split
Can you give an overview of an NEC option D contract please?
Target cost with bill of quantities
Same as option C but with bill of quantities instead.
Can you give an overview of an NEC option E contract please?
Cost reimbursable contract
1) Often referred to as cost plus
2) Employer takes on financial risk as the Contractor is paid for all cost incurred + an agreed fee to cover overheads and profit
3) Often used when the nature of works are difficult to define from the outset such as urgent alteration or repair works
Can you give an overview of an NEC option F contract please?
Management Contracts
1) Contractors defined costs are reimbursed with a fee paid
2) Works are designed/constructed by multiple subcontractors who are managed by the management contractor
What are the secondary options under NEC3 ECC?
1) Dispute resolutions
2) X Clauses
3) National legislation
4) Z clauses
Can you name 5 X clauses within an NEC contract?
1) Price adjustment for Inflation
2) Parent company guarantees
3) Sectional completion
4) Delay damages
5) Retention
6) Performance bond
7) KPI’s
8) Changes in the law
9) Partnering
10) Advanced payment to contractor
What are the default dispute resolution procedures within an NEC contract?
1) Adjudication
2) Litigation/Arbitration
What two forms of national legislations are referred to in the NEC additional clauses?
1) Housing and Grants, construction and regeneration act 1996
2) The contracts right of third parties act 1999
Can you give an overview of the Housing and grants, construction and regeneration act 1996?
Otherwise known as the construction act, brought in to regulate payment and streamline the dispute procedure. It introduced:
1) Right to regular payments
2) Right to a detailed payment notice for works complete
3) Right to suspend works for non payment
4) Right to adjudicate
5) Disallowed pay when paid clauses
Can you give an overview of the contracts right of third parties act?
Gives right to a person who is not not party to a contract to enforce rights under the contract where the contract confers a benefit to them.
What are Z clauses in an NEC ECC contract?
A z clause is a set of amendments to the standard NEC contract, this can be through the form of amendment, omission or addition of new clauses.
What are the three types of Programme float?
1) Total float
2) Terminal float
3) Time risk allowances
Can you explain what total float is?
1) The time an activity can be delayed from its early start date without delaying planned completion.
2) Available to either the employer or contractor on a first come first serve basis
Can you explain what time risk allowance is?
1) The amount of risk allowed by the contractor for not completing the activity in the minimum time possible due to unforeseen circumstances
2) It is owned by the contractor and cannot be used to mitigate the effect of a CE
Can you explain what terminal float is?
1) The duration between planned completion and contract completion
2) It is owned by the contractor and cannot be used to mitigate the effect of a CE
3) If planned completion comes forward to unused TRA, the early completion can be banked as terminal float
How can a contract completion date be changed in an NEC or JCT contract?
NEC - ICE or acceleration
JCT - EOT or acceleration
How can the planned completion date change?
1) Anything can change it
2) For example variations, not reaching productivity output, delay of materials.
how does programme differ in NEC and JCT contracts?
1) Programme is not a contract document in JCT unlike NEC
2) In NEC contracts, programme is used to assess and agree compensation events.
In an NEC contract, can you give three key responsibilities of the project manager?
1) Change the works information
2) Issue contract documents such as instructions, communications and payment notices.
3) Monitor the execution of the project and ensure all parties adhere to the contract
In an NEC contract, can you give three key responsibilities of the supervisor?
1) Responsible for ensuring the contractor is compliant with the works information
2) Raises defect notices & is authorised to instruct the inspection of a defect
In an NEC contract, can you give three key responsibilities of the employer?
1) Give site access to the contractor
2) Take out necessary insurance provisions
3) Make payments in accordance with the contract
What is the works information in an NEC contract?
1) Specifies and describes the contractors works
2) Sets out any constraints
3) It should be clear and concise to mitigate the risk of any misinterpretation which would cause conflict
Name 3 things you’d find in the employers works information in an NEC contract?
1) Specification and drawings
2) Technical information
3) Requirement and constraints
What is a compensation event?
An event which are not usually the fault of the contractor, if they occur it
would impact the contract price or programme.
Where in the NEC ECC contract would you find compensation events and can you give three examples of on?
Clause 60.1 of the NEC3 contract
1) Change to the works information
2) The inspection of a potential defect
3) Acceleration of the works
In NEC ECC contracts, what is the period a contractor has to notify a compensation event, and what is the consequence if they issue later?
1) 8 weeks
2) The contract would be time barred and it would not be deemed a compensation event in the court of law
3) The only exception is where the PM or supervisor issues and instruction or certificate, changes and earlier decision or corrects an assumption
Will a PMI always result in an compensation event?
No, the PM may instruct the contractor to issue a revised programme or remove someone from site.
What is an early warning notice?
A notification from either party making the other aware of a potential risk event which if materialises could impact the costs or impact progress.
What clause refers to early warning notices in NEC contracts and what does it state?
Clause 16.1
The contractor and project manager give an early warning by notifying the other as soon as either becomes aware of any matter which could increase costs, delay completion, delay meeting a key date or impair performance.
What are the key updates from NEC3 to NEC4?
1) Gender neutral, he replaced with they
2) Risk register now called early warning register
3) Term employer has become client
4) Term works information has become scope
5) Now only one fee rather than subcontract, design, direct etc.
What are they key differences between NEC and JCT contracts? Please name 3
1) NEC is focused on collaboration as per clause 10.1 “both parties must act mutual trust “
2) NEC is more proactive at managing risks through the use of early warnings.
3) NEC deals with time and cost changes differently through RE & RM whereas NEC deals with the two jointly through compensations events
4) NEC is more Programme driven as the programme is a contract document with penalties in place if one is not issued.
5) JCT uses provisional sums whereas NEC does not.
6) NEC is written in plain English whereas JCT is not.
What is a contract?
A legally binding promise signed by 2 or more parties which sets out the rights and obligations of both parties.
What four elements must a contract contain in order to be deemed a valid contract?
1) Offer
2) Acceptance
3) Consideration
4) Intention to create legal relations
Please can you define express terms?
Terms that are expressly agreed between the two parties
Please can you define implied terms?
Terms that are not expressively agreed within the contract but are implied by common law or statute
What is tort?
1) A civil wrong
2) Part of the civil law
3) Concerned with loss or harm
What is the local democracy, economic development and construction act 2009?
1) Came into force in England and Wales
2) Amended the construction act 1996
3) Change the way contracts were entered into and amended the existing payment and adjudication regime