Contract Practise Flashcards
What does JCT stand for?
Joint Contracts Tribunal
What are some of the contracts in the JCT family?
1) Standard building contracts
2) Minor works building contract
3) Design & build contract
4) Construction management contract
5) Repairs & maintenance contract
What are the key characteristics that influence what contract is used?
1) Size & value of the project
2) Appetite for risk
3) Experience of the client
4) Project priorities (time, quality, cost)
What are relevant events?
A set of events which would cause a delay to the contractor through no fault of their own, entitling the contractor to an extension of time thus moving the contract completion date.
Can you provide three examples of a relevant event?
1) Exceptionally adverse weather
2) Force Majeure
3) Impediment/prevention/default by the employer
What is force majeure?
1) An act of god which is out of the contractors control such as natural disasters
Can you give three examples of a force majeure event?
1) Act or threats of terrorism
2) Riots/strikes
3) War
What happens when a relevant event occurs?
1) Contractor notifies the employer with a notice of delay
2) Contractor identifies the material circumstances of the delay and the relevant event related
3) He provides an assessment of the time impact where possible
4) The contractor reviews the notice of delay and responds as soon as reasonably possible
5) He either concludes his rejection of the notice of delay or acceptance including the extension of time granted.
If a relevant event is accepted does this entitle the contractor to automatic loss and expense?
Not always, the event must also be a relevant matter to warrant recovery of loss and expense.
What are relevant matters?
A relevant matter is a matter which materially impacts the progress of works. If a relevant occurs it may entitle the contractor to recover any loss and expense as a result of any impediment or prevention, bringing them back to the commercial position they would have been in had the matter not occurred.
Give three examples of a relevant matter?
1) Prevented access to part of the site
2) Delays to design information or instructions
3) Disruption caused by works carried out by the employer
What is the difference between a relevant event and a relevant matter?
A relevant event entitles the contractor to additional time, whereas a relevant matter entitles the contractor to additional costs.
What is a loss & expense claim?
An attempt by the contractor to recover costs ascertained as a direct impact of any failure caused by employer, usually delays.
Name three common heads of claim for loss and expense?
1) Prolongation
2) Productivity loss
3) Additional storage costs
Can the contractor refuse to give partial possession to the employer?
Yes, the contractor must consent to giving partial possession but it cannot be unreasonably withheld. The Contractor may withhold if giving partial possession may hinder their ability to complete the remainder of his work.
Name three implications of partial possession?
1) Contractor no longer liable for LAD’s relevant to that area of works
2) half of the retention to be released for that area of works
3) Contractor is no longer responsible for any damage to that area of works
4) The employer is responsible for the insurance of that element of works
What is the difference between sectional and partial completion of the works?
Sectional completion is preplanned and agreed in the contract before the works commence, whereas partial completion is requested during the construction phase of the works.
What are the main options for insuring the works under a JCT contract?
Option A - Contractor take out joint names all risk insurance for the works
Option B - Employer takes out joint names all risk insurance for the works
Option C - Employer takes out all risk insurance for the works and insures against specified perils for the existing structure
What is a Contractors ‘All Risk’ insurance?
1) Insurance that covers physical loss or damage to the works being undertaken
2) Sometimes referred to as ‘Car Insurance’
3) The policy cover will pay for the repair or replacement of the damaged works
What is a specified Peril?
Significant events which may occur on site causing significant damage to the works
Includes things like:
1) Flood through burst water pipes
2) Fires
3) Earthquakes
What is a subrogation?
A concept whereby an insurer who has paid out on loss, can step into the shoes of the claimant in order to sue the guilty party for the loss caused.
What is joint names insurance policy?
1) A type of joint insurance (2 or more parties)
2) Under a joint names policy the insurer has no right to subrogate against any of the insured parties
What does NEC stand for?
New Engineering Contracts
What does ECC stand for?
Engineering and construction contract