Procurement & Tendering Flashcards

1
Q

Can you please name the different forms of procurement?

A

1) Traditional
2) Design and build
3) Construction Management
4) Management Contracting

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Can you summarise what traditional procurement consists of?

A

The client appoints consultants to carry out the full design of the works and it is employed directly by the architect. On completion of the design, the employer appoint a main contractor to carry out the construction of the works.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Can you summarise what D&B procurement consists of?

A

The client sets a list of Employers requirements (ER) and invites a series of main contractors to tender for the design and issue the Contractors Proposals (CP’s), the winning tenderer is appointed to carry out the design and construction. The selected Contractor then appoints design consultants to carry out the detailed design. In this route, the design and construction risk sits with the contractor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Can you summarise what construction management procurement consists of?

A

The Employer appoints a designer, Trade Contractors and a Construction Manager to manage the Trade Contractors. The Construction Manager has no contractual links with the Trade Contractors and is simply paid a fee by the Employer to coordinate the works. Through this route, the Employer bears both the design and construction risk.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Can you summarise what management contracting procurement consists of?

A

The Employer employs design consultants and a management contractor to employ trade contractors. The management contractor is paid based on the construction costs + fee, so carries no risk.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the advantages of construction management procurement?

A

1) Employer has means of redress through contractual relationships with trade contractors
2) Design and construction runs parallel which makes for an early start on site date and shorter programme
3) Employer maintains control with design
4) Employer has a direct contract with all parties
5) Direct contracts attract less fee on fee

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the disadvantages of construction management procurement?

A

1) Price certainty not achieved until final trade package is let
2) More responsibility for the employer so more work and risk

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the advantages of management contracting procurement?

A

1) Design and construction runs parallel which makes for an early start on site date and shorter programme
2) The management contractor will provide buildability input
3) Single point construction responsibility through management contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is partnering?

A

1) Broad term used to describe a collaborative management approach
2) Purpose of implementing it is to create openness and trust
3) This in turn forms good employer/contractor relationships
4) Ownership of risk is spread across the parties, less blaming and more proactive thinking
5) Brings lots of advantages to the table

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are the advantages of partnering?

A

1) Less conflict
2) Improved communication & client care
3) More alignment gives better predictability of time and costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is a framework agreement?

A

An overarching agreement for the procurement of goods, work or services that a a party enters into with one or more suppliers to establish governing terms. It usually ranges between 2-10 years but is determined by the buyer.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are the advantages of a framework agreement?

A

1) Builds stronger relationships
2) Speeds up the rate of procurement
3) Leads to repeat business
4) Rates are agreed upfront

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are the disadvantages of a framework agreement?

A

1) Party members can become complacent
2) Can restrict new members which may be more innovative products

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Can you give an example of a time a framework agreement might be set up?

A

When a business is carrying out repeat work such as the commissioning of a building where they may wish to reduce procurement duration by calling materials off.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are the main three tendering options for a construction process?

A

1) Single stage tender
2) Two-stage tender
3) Negotiated tender

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is a single stage tender?

A

When a number of contractors are invited to tender based on a set of identical tender documents issued at RIBA stage 4 (detailed design).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What is a two stage tender?

A

Stage 1 - When the employer provides an outlined design in which contractors then compete to become preferred contractor status. The preferred tenderer then joins on a consultancy basis to assist with the early stage, thus entering into a PCSA (pre-construction services agreement).

Stage 2 - Once the design has developed, the contractor enters into a detailed negotiation with employer to agree the final contract price and conditions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What is a negotiated tender?

A

When the employer knows the Contractor they want to carry out the works from the outset, thus inviting only one contractor to negotiate the tender value.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What are the advantages of a single stage tender?

A

1) Employer benefits from a competitive tender process which leads to more competitive pricing
2) The Employer has more cost certainty as the winning tenderers costs is fixed based on the known design

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What are the advantages of a two stage tender?

A

1) Contractors buildability input
2) Contractor has more time to understand the scope
3) Forms an early relationship
4) Employer has involvement with subcontractor selection
5) Opportunities for value engineering and risk mitigation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What are the advantages of a negotiated tender?

A

1) Simplicity & speed, removes need for tender process
2) Employer can choose based on their own experiences
3) Allows early contractor involvement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What is a bona fide tender?

A

A bid which has been submitted in good faith in accordance with the conditions of bidding requirements and confirms that no collusion has taken place.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

What are the main considerations for an Employer when selecting the most appropriate procurement route?

A

1) Clients experience
2) Appetite for risk
3) Project priorities (time, cost, programme)
4) Complexity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Which method of procurement did you use when tendering for the metal doors package on kings cross S5.

A

Single stage tender with both the curtain walling subcontractor and a preferred metal door subcontractor who had been used on a neighboring project who had given good feedback.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

Can you run me through the process of procuring metal doors through the metal door subcontractor?

A

1) Scope analysed and allocated to the appropriate parties based on works risk
2) Door which interfaced with curtain walling subcontractors works, were issued to them for pricing
3) Stand alone doors, were issued to the metal door subcontractor
4) I issued them with a marked up GA & elevation drawing, the specification, programme requirements, key project information, and a pricing document to fill in and return
5) The tender return was then analysed against our budget, and was checked to determine any omissions or issues
6) Once agreed, I drafted the contract and issued to the subcontractor for their review.
7) We then had a meeting to agree the terms and conditions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

How did you go about determining the scope of works for the procurement of a firestopping package?

A

The subcontract was tendered on a re-measurable basis as a single stage tender to 3 different companies. At the time only the ground floor and mezzanine builders work hole schedule was available. I therefore issued both schedules to the subcontractor for pricing a set of rates based on the different penetrations and sizes. The overall best value subcontractor including but not limited to the lowest rate was selected on a remeasurable basis and would be paid based on works complete at the agreed penetration rates.

27
Q

What is a re measurable contract and when might it be used?

A

When a subcontractor is appointed based on an agreed set of rates, and works are paid on works complete against the agreed rates. This is used when the scope can be described clearly, but the quantity cannot.

28
Q

Give two advantages of a remeasurable contact?

A

1) Enables early start on site date
2) Unit rates are pre-agreed

29
Q

Give two disadvantages of a remeasurable contact?

A

1) Final value is not known until all works are complete
2) More administration works as works are reassessed on a periodic basis

30
Q

Can you please take me through the gateway 1,2 and 3 and why does it exist?

A

The procurement gateway process which our London Underground permitted us to execute under the main contract. The purpose of it was to remain transparent throughout the procurement process and ensure they were involved with the tender process.

Gateway 1 - Shares the companies considered on the tender list, their DNBI scores and accreditations and package budget with the client. Also gives, the client an opportunity to put forward any other recommended sub-contractors

Gateway 2 - This is where the tender return prices are shared with the employer.

Gateway 3 – This is a recommendation report which is issued to the employer advising on our holistic view of which sub-contractor is best placed to carry out the works based on considerations including: cost, experience, quality procedures, h&s and interviews.

31
Q

What is compete for and why is it used?

A

It is a free service that allows businesses to compete for contract opportunities for major infrastructure projects. It was brought in to keep public procurement opportunities in one place, provide more opportunities for the supply chain and promote transparency.

32
Q

How do you ensure all tenders are fair?

A

1) Provide all tenderers with the same level of information
2) Give all tenderers the same amount of time
3) Issue any tender query responses to all tenderers

33
Q

You mention during gateway 1 you carried out some background checks, can you tell me what kind of checks you would carry out?

A

1) Credit reports to understand financial stability
2) Recent performance feedback

34
Q

Could you please give me one method of carrying out financial checks with a subcontractor? How does this work?

A

Dunn & Bradsheet Report (DnB) - generates a credit score based on the size of the company and information provide on a company’s balance sheet.

35
Q

Would you ever appoint a subcontractor if they scored low on a a D&B report?

A

Typically no as it would pose a great financial and Programme risk, however there could be exceptional circumstances such as the subcontractor being highly experiences and well recommended from an operational perspective. If this was the case, i would negotiate the use of a performance bond or seek a PCG.

36
Q

What would you do if you noticed one of the tenderers had mispriced something or missed it completely?

A

The tenderer should be given the opportunity to correct the error or price the missing scope, should this extend the tender period all tenderers window should be extended.

37
Q

What was you checking for during the tender review in gateway 2?

A

1) Mathematical errors
2) Errors in pricing
3) Omission
4) Specification compliance
5) Check compliance of CP’s against ER’s
6) Resolve any qualifications

38
Q

What were your initial thoughts when reviewing the tenders? What did you advise the client?

A

We had some reservations over the quality and H&S standards of the lowest price tenderer which ultimately led to eliminating them. This left two companies at a similar price, both were interviewed by myself and the package manager. Both were good, but one had a streamlined process for QA checks and was well recommended. Since my project, the subcontractor has become a highly used subcontractor and has been recommended several times by the project manager.

39
Q

What would happen if the client had strong objections to selecting a specific subcontractor?

A

I would gently remind the employer that the subcontractor was not a named/nominated subcontractor and therefore they do no reserve the rights to select the tenderer. However, i would respect their opinion and justify my reasons for selection, i would then try to come to a reasonable compromise.

40
Q

What is a domestic subcontractor?

A

A subcontractor that is selected, procured and awarded at the discretion of the contractor.

41
Q

What is a nominated subcontractor?

A

This is when a particular subcontractor is pre-selected by the employer and then imposed by the contractor. Put in place when:

  • Early input has already been provided by specialist supplier
  • Materials are on a long lead time, early appointment prior to contractor selection (novation)

It is usually put in place when the employer has already worked with the subcontractor at the earlier stages of a project where the specialist subcontractor has provided input which has helped drive the project.

42
Q

What is a named subcontractor?

A

A term that replaced nominated subcontractors in JCT contracts, which gave the contractor the rights to reject the named contractor if they had reasonable grounds to do so.

43
Q

What is a purchase order and when would one be used?

A

A document issued by the buyer to seller which outlines their intentions to purchased certain products at an agreed price. Used in the procurement of materials for construction projects where the install is likely to be carried out separately through a subcontractor or direct labour.

44
Q

What is a universal clamp?

A

A product which is used to fix two peices if formwork together.

45
Q

What is formwork?

A

A temporary mold in which concrete is poured into so that it can set to the required shape.

46
Q

What is a buy-back clause?

A

When a seller of a product agrees to repurchase the product at a predermined price within a certain timeframe subject to the condition of the material.

47
Q

How would you respond if a particular works package was rapidly growing at a rate which exceeded your budget?

A

1) Explore the idea of retendering to obtain a more competitive price
2) If not possible, i would request substantiation for the increases to identify any unnecessary costs
3) Explore value engineering options, i.e similar performing products at cheaper rates.

48
Q

What costs would the there be during a PCSA stage?

A

PCSA stage is the appointment of a contractor on a consultancy basis to help develop the design, so costs would largely be design orientated such as:

  • Design fees
  • Survey costs
  • Insurance costs
49
Q

What is a cover price in a tender submission.

A

When a contractor submits an inflated tender price knowing it will be unsuccessful in order to collude with competition and drive the overall price up.

The act of cover pricing is illegal in accordance with the competition act 1998 and guilty party’s can be fined up to 10% of their annual turnover.

50
Q

Is there any documents which can be included within a tender pack to deter the act of collusion?

A

Anti collusion statements - A declaration to from a subcontractor or contractor stating that they have not breached the competition act 1998

51
Q

Can you please explain the relationship between choices of procurement routes and tender prices?

A

Traditional - More cost certainty and lower premium due to no design risk allowances

D&B - Less price certainty as design changes will result in price increases, contractor will also charge a premium to cover design risks.

Construction management - No cost certainty, as costs are not known until last trade package is let. Although no design premium as employer appoints an architect

Management contracting - No cost certainty, as costs are paid on actual costs + fee.

52
Q

Can a form of subcontract differ from the main contract and why?

A

Yes, the contractor may opt to use a bespoke form of contract, to accommodate favorable terms such as risk allocation and payment. A bespoke contract is more favorable by the party proposing it.

53
Q

Are you aware of any tendering guidelines?

A

1) RICS professional guideline
2) Tendering Strategies

54
Q

Who bares the quantity risk on a bill of quantities when issued to a subcontractor for pricing?

A

The employer, the subcontractor only bares the risk on the rate provided which is fixed unless the scope changes.

55
Q

If a tenderer issued qualifications with their tender what would you do?

A

1) Review each qualification to check if it aligns with the Employers requirements
2) If the tenderer had any queries or clarifications, I would ensure that information was shared with all tenderers to ensure fairness
3) I would check that the products and processes align with the specification and LOR’s minimum requirements.

56
Q

Have you ever given advise on a procurement route on your project?

A

Yes, as evidenced in my case study i advised that we split the supply and install for the intumescent paint of structural steelwork with two separate subcontractors. In doing this, we were able to reduce material delivery times and avoid paying a premium on the install element due to risk.

57
Q

What is the ECI process?

A

Early Contractor Involvement process, the process of appointing a Contractor at an early design stage to act as a consultant.

58
Q

What advise would you give to a client who was considering a two stage tender?

A

1) Programme - Allows the contractor to provide an early idea of the construction programme
2) Contractors buildability input
3) Early prices of works packages
4) Employers buy-in to subcontract packages
5) Potential to novate
6) Provides opportunity to drive out cost and increase value

59
Q

In relation to the procurement of the builders clean package on NLE, how did you ensure the advice you were giving to the client was accurate and based on a fair tender process?

A

1) I ensured the financial checks were accurate by using dun and Bradsheet reports
2) I ensured that I used and followed the RICS guidance note ‘Tender strategies, 1st edition’
2) I ensured all tenders were comparable by giving the same pricing document and using normalisation where anything had been missed.
3) I gave all tenders the same amount of time and information
4) I interviewed each of them to fully understand if their processes and proposals were accurate

60
Q

What factors did you consider when providing the recommendation to the client?

A

1) Best value
2) Recommendations from others
3) Sign of systems for quality and valuation
4) Financial scorings

61
Q

What work did you carry out to produce the hire vs purchase analysis?

A

1) Understood the length of time we would need the formwork
2) Understood the quantum we would need
3) Contacted the supplier to understand the rate we would receive based on our quantum
4) Multiplied the rate by the quantity
5) Multiplied the hire rate by the quantity by the hire rate by the duration
6) Compared the total figures
7) It was cheaper to purchase over hire even without the buyback option

62
Q

Can you give me some examples of risks on the project you work on?

A

NTT

1) Risk of louvre blades not aligning properly with phase 1 which was built by others, Contractors CDP which we failed to transfer to specialist subcontractor
2) Underestimation of spools

63
Q

Outside of your write ups, please can you provide another example of when you have demonstrated good procurement practices?

A

1) NTT Builders clean
2) Experience in procuring previous builders clean package
3) This one was much lower specification
4) Advised it may be better value to conduct in house
5) Cot exercise proved this
6) Works were agreed to be carried out in-house