Procurement & Tendering Flashcards
Can you please name the different forms of procurement?
1) Traditional
2) Design and build
3) Construction Management
4) Management Contracting
Can you summarise what traditional procurement consists of?
The client appoints consultants to carry out the full design of the works and it is employed directly by the architect. On completion of the design, the employer appoint a main contractor to carry out the construction of the works.
Can you summarise what D&B procurement consists of?
The client sets a list of Employers requirements (ER) and invites a series of main contractors to tender for the design and issue the Contractors Proposals (CP’s), the winning tenderer is appointed to carry out the design and construction. The selected Contractor then appoints design consultants to carry out the detailed design. In this route, the design and construction risk sits with the contractor.
Can you summarise what construction management procurement consists of?
The Employer appoints a designer, Trade Contractors and a Construction Manager to manage the Trade Contractors. The Construction Manager has no contractual links with the Trade Contractors and is simply paid a fee by the Employer to coordinate the works. Through this route, the Employer bears both the design and construction risk.
Can you summarise what management contracting procurement consists of?
The Employer employs design consultants and a management contractor to employ trade contractors. The management contractor is paid based on the construction costs + fee, so carries no risk.
What are the advantages of construction management procurement?
1) Employer has means of redress through contractual relationships with trade contractors
2) Design and construction runs parallel which makes for an early start on site date and shorter programme
3) Employer maintains control with design
4) Employer has a direct contract with all parties
5) Direct contracts attract less fee on fee
What are the disadvantages of construction management procurement?
1) Price certainty not achieved until final trade package is let
2) More responsibility for the employer so more work and risk
What are the advantages of management contracting procurement?
1) Design and construction runs parallel which makes for an early start on site date and shorter programme
2) The management contractor will provide buildability input
3) Single point construction responsibility through management contractor
What is partnering?
1) Broad term used to describe a collaborative management approach
2) Purpose of implementing it is to create openness and trust
3) This in turn forms good employer/contractor relationships
4) Ownership of risk is spread across the parties, less blaming and more proactive thinking
5) Brings lots of advantages to the table
What are the advantages of partnering?
1) Less conflict
2) Improved communication & client care
3) More alignment gives better predictability of time and costs
What is a framework agreement?
An overarching agreement for the procurement of goods, work or services that a a party enters into with one or more suppliers to establish governing terms. It usually ranges between 2-10 years but is determined by the buyer.
What are the advantages of a framework agreement?
1) Builds stronger relationships
2) Speeds up the rate of procurement
3) Leads to repeat business
4) Rates are agreed upfront
What are the disadvantages of a framework agreement?
1) Party members can become complacent
2) Can restrict new members which may be more innovative products
Can you give an example of a time a framework agreement might be set up?
When a business is carrying out repeat work such as the commissioning of a building where they may wish to reduce procurement duration by calling materials off.
What are the main three tendering options for a construction process?
1) Single stage tender
2) Two-stage tender
3) Negotiated tender
What is a single stage tender?
When a number of contractors are invited to tender based on a set of identical tender documents issued at RIBA stage 4 (detailed design).
What is a two stage tender?
Stage 1 - When the employer provides an outlined design in which contractors then compete to become preferred contractor status. The preferred tenderer then joins on a consultancy basis to assist with the early stage, thus entering into a PCSA (pre-construction services agreement).
Stage 2 - Once the design has developed, the contractor enters into a detailed negotiation with employer to agree the final contract price and conditions.
What is a negotiated tender?
When the employer knows the Contractor they want to carry out the works from the outset, thus inviting only one contractor to negotiate the tender value.
What are the advantages of a single stage tender?
1) Employer benefits from a competitive tender process which leads to more competitive pricing
2) The Employer has more cost certainty as the winning tenderers costs is fixed based on the known design
What are the advantages of a two stage tender?
1) Contractors buildability input
2) Contractor has more time to understand the scope
3) Forms an early relationship
4) Employer has involvement with subcontractor selection
5) Opportunities for value engineering and risk mitigation
What are the advantages of a negotiated tender?
1) Simplicity & speed, removes need for tender process
2) Employer can choose based on their own experiences
3) Allows early contractor involvement
What is a bona fide tender?
A bid which has been submitted in good faith in accordance with the conditions of bidding requirements and confirms that no collusion has taken place.
What are the main considerations for an Employer when selecting the most appropriate procurement route?
1) Clients experience
2) Appetite for risk
3) Project priorities (time, cost, programme)
4) Complexity
Which method of procurement did you use when tendering for the metal doors package on kings cross S5.
Single stage tender with both the curtain walling subcontractor and a preferred metal door subcontractor who had been used on a neighboring project who had given good feedback.
Can you run me through the process of procuring metal doors through the metal door subcontractor?
1) Scope analysed and allocated to the appropriate parties based on works risk
2) Door which interfaced with curtain walling subcontractors works, were issued to them for pricing
3) Stand alone doors, were issued to the metal door subcontractor
4) I issued them with a marked up GA & elevation drawing, the specification, programme requirements, key project information, and a pricing document to fill in and return
5) The tender return was then analysed against our budget, and was checked to determine any omissions or issues
6) Once agreed, I drafted the contract and issued to the subcontractor for their review.
7) We then had a meeting to agree the terms and conditions