Case Study/Fire Regulations Flashcards

1
Q

You mention cashflow forecasting to the client, why was this necessary?

A

This was not a contractual requirement, more of a goodwill gesture for our client. We had a better understanding of when the Programme would become cash intensive, so was best placed to advise on the likely project expenditure. This was used by the client to obtain funding from the bank.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
1
Q

Can you give three amendments to the JCT contract for your project?

A

1) Payment terms from 14 days to 21 days
2) The addition of a relevant event specific to the outbreak of an epidemic/pandemic and Brexit
3) The employer may retain £10,000 where the contractor fails provide all O&M to a satisfactory standrd.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Was there any recourse to recover the costs associated with the specification change in fire protection requirements? If so, what were they?

A

The contract we operated under was a JCT design and build contract, meaning the employer had no design responsibility as the architect was employed under the contractor. This meant we could not recover the change in specification as a variation.

However, it could be argued that a competent architect should have understood the fire rating requirements from the outset which would have negated the need for retrospective fire protection. This could be deemed an act of negligence which could be recovered through our PI insurance. However, the costs were reduced significantly, which did not make such a claim worthwhile.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Did you consider the instruction issued to the firestopping subcontractor, and later the painting subcontractor a relevant event and why?

A

Whilst an instruction does qualify as a relevant event, in this case the impact on the completion date was nil as a separate team would manage the works concurrent to the existing team, meaning the completion date would not be impacted.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

How did you go about agreeing the original quotation from the firestopping subcontractor?

A

I referred to the valuation hierarchy in clause 5.6 of the subcontract.

The application of fire protection through paint had not be priced before within the subcontractors order, thus, there were no rates with the schedule of rates to fall back on. Due to the urgency and risk around the works the subcontractor issued a quotation which was subsequently accepted by us.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How did you agree the cost of the paint and supply, did you have a breakdown from the original quote?

A

The subcontractor issued a quotation for £50k. 50% of this was made up of labour and materials, and the other 50% was made up of preliminaries. Knowing the works were urgent, we were happy to pay for the prelims to ensure their existing works were not delayed and we knew the labour had an allowance for risk due to access restraints. The works were urgent and we could not afford to waste time picking apart the quotation given our expensive LAD costs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Can you please explain why it took 3 months to conclude this issue?

A

The first 6 weeks were spent chasing the firestopping subcontractor to carry out the works they were obliged to do. We then spent 3-4 weeks reviewing the best suited solution to move forward. There was then a period where we had to wait for a manufacturers report to establish whether the materials purchased were correct.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

In your instruction to the painting subcontract, why was the cost stated as ‘TBA’ and not agreed upfront?

A

The subcontractor was unwilling to commit to a price given the restricted access and difficulty painting around services. We therefore agreed to capture the costs after on a daywork basis.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

For your key issues – did you consider cost impact? And did this form reasoning for your decision?

A

Cost was of course considered, the programme requirements was prioritised which ultimately impacted the wider costs due to LAD’s.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Did building control advise on a solution to fire protect the steelwork?

A

Yes, they advised on using intumescent paint as per their report. However this was before they the works were complicated with surrounding MEP works.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Why did you wait until the steel was built before obtaining third party verification of the adequacy of the specified fire ratings?

A

We trusted the competence of our design consultant at tender stage. The fact that the fire rating was insufficient was a technical oversight, which was a lesson learnt going forward.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Did the cost of the firestopping works not factor into your assessment when advising your team that option 3 was the best option?

A

Yes it did, however the main priority in this situation was programme and health and safety, the fact that I was able to reduce the original cost was an added bonus to my company.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Was the three-week period to complete the works and start date from the issuance of the instruction not agreed with the Sub-Contractor prior? What surety does writing a start date of “ASAP” give you?

A

The 3-week programme was agreed informally and was incorporated within the instruction without objection from the subcontractor so was deemed accepted. The start on site date however was subjective and in hindsight should have been clearer. If I was to do it again, I would ensure a completion date is stated within the instruction and obtain the subcontractors commitment in formal writing where possible.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the significance of issuing an EWN under a JCT contract?

A

An early warning is not a mechanism within the JCT suite of contracts and was introduced in NEC contracts as a risk management tool. With that I mind, I feel it can only be a beneficial to both parties if used correctly. In this instance, it was not used correctly as the risk had already passed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Can you please tell me about some of the legislation around the fire protection of steelwork in the UK?

A

Building regulations (approved document B)
Building Safety Act 2022 (specific to high rise buildings)
Fire Safety Act 2021 (includes all multi occupated buildings)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Can you please tell me how grenfell has changed the way the construction industry has had to adapt?

A

Brought in the following:

1) Prohibition of combustible materials to the external facade
2) Mandated the use of EAS’s (evacuated alert system) for over 18 metre buildings
3) Mandated the need for a secure information box for over 18 metre buildings
4) Gave occupants more of a say
5) Mandated the need for sprinkler systems in buildings above 11 metres

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Knowing the works were defective, did you ever issue a defects notice and why?

A

No, it is the contractors responsibility to identify and rectify defects to works during the construction phase and in the rectification period. However, if the Employer identifies a defect during the rectification period, he may specify in a schedule of defects and instruct the contractor to make good. In this case, we identified the defect and made good.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Given this case study went on for 3 months, does this mean your project was delayed by 3 months? If so, can you please explain the consequences of this?

A

On the face of it, yes the works would have been delayed by 3 months. This meant, that unless we accelerated in other areas of work, we would have incurred a total of £864k of LAD’s, as well as prolongation costs.

However, there were other delays concurrent to this, meaning the Programme was not specifically delayed by this event.

The LAD’s were reduced to £250k as part of a final account agreement, after the employer was unable to substantiate that the LAD’s were a genuine estimate of the loss incurred as a result of the delay.

18
Q

What is the relevant building regulation in relation to fire safety and how is impacted when events such as Grenfell happen?

A

1) Approved document B
2) Updated when a new act is brought in to align with best practice recommendations
3) For example it was updated on 1st December 2022, following the Hackett review and building safety Act.

19
Q

What are the aims of approved document B?

A

1) Safe means of escape
2) Stability of a building to be maintained during a fire
3) Finishes to building must resist flames and not spread
4) Fire & smoke must not spread to concealed spaces
5) External walls and ceilings must not spread fire onto neighbouring buildings
6) Fire fighters must have easy access to the building

20
Q

Can you please tell me specifically which peace of legislation specifically sets a requirement for protection structural steelworks as per your case study?

A

Yes, approved document B (fire safety), requirement B3 (internal fire spread - building structure).

21
Q

What is the purpose of approved documents?

A

Set out what, what may be accepted as reasonable provision for compliance with the relevant requirements of the Building Regulations to which they refer to.

22
Q

When was approved document B updated to respond to the events that happened during grenfell?

A

01/12/2022

23
Q

What is an EAS in a building?

A

Evacuated Alert System

Designed in accordance with British standards to mass evacuate an entire floor or building. Used when a stay put policy is not sufficient.

24
Q

Can you explain how an EAS works specifically?

A

It is fitted in each flat in a block and allows the fire rescue service to identify specifically which floors and areas the first is on to evacuate and respond accordingly.

25
Q

What is a secure information box?

A

A securely protected box which includes key information to the fire rescue service during an emergency:

1) Contact details for all residents with access to the building
2) Floor plans of the entire building
3) A single page block plan which identifies key fire fighting equipment and facilities such as dry risers

26
Q

Can you please provide an example of a banned product as a result of the update on building regulations?

A

Anything below euroclass A2. Includes materials such as timber frames, external fascia & soffit boards.

27
Q

What is the purpose of a sprinkler system in a building?

A

Detects a fire through high heat (not smoke), and automatically discharges water to suppress the fire.

28
Q

Can you please tell me the upper and lower band of euroclasses?

A

F - Lower End (no performance requirements)
A1/A2 - No contribution to fire

29
Q

Are there any exceptions to the ban on combustible materials to external facades?

A

Yes, examples below:

1) Cavity trays
2) Doors frames and doors
3) Fibre optic cables
4) membranes
5) Window frames and glass

30
Q

What buildings does the building Act 2022 apply to?

A

1) Buildings 18m or above in height
2) Buildings 7 storeys or higher

31
Q

What requirements did the building Act 2022 bring in?

A

1) Ensures duty holders are compliant with the latest building regulations
2) Increased the number of duty holders
3) Fines and imprisonment for non compliance with building regulations
4) Time limit to report faults extended
5) Closed cases can now be reopened

32
Q

What is the standard rectification period for building contracts?

A

12 months following practical completion

33
Q

What is intumescent paint?

A

A specialised coating that provides high-performance fire resistant properties.

34
Q

How does intumescent paint work?

A

When subject to fire, the paint undergoes a transformative process called intumescence. During this process, the paint film expands, creating a foam like layer which acts as a heat shield between the steel and the fire, thus significantly slowing down the transfer of heat. This significantly delays the the period in which the steel begins to lose its structural strength.

35
Q

What are the benefits of intumescent paint?

A

1) Compliant with all updated fire regulations
2) Can be applied at manufacture stage or in-situ
3) Easy to apply

36
Q

Was there any compliance issues with painting over existing intumescent paint?

A

Yes, this is known as a topcoat. However, only approved top coats can be applied, hence the importance of the manufacturers report.

37
Q

Are there any disadvantages to applying intumescent paint?

A

1) Must be maintained

38
Q

How was client care demonstrated throughout?

A

The client was always invited to attend any site visits with building control, in the event that they wasn’t available, the findings would always be shared with the client. When the issue came to light, it was reflected in our Programme and addressed in the client meeting which we had monthly.

39
Q

What are the certifications required to apply intumescent paint?

A

The applicator must have the relevant certification and must be able to demonstrate that they can certify the relevant thickness of the paint.

40
Q

Do you think that the method in which steelwork was procured, prevent best value?

A

I was not involved with the procurement of the steelwork package, but I know my company would have followed the correct tender process to provide best value. Regardless of how we procured this package, the steelwork subcontractor would only have allowed for 60 minutes of fire protection as that is what the specification called for. In hindsight, we could have tapped into their expertise to establish whether they believed whether 60 minutes was sufficient.

41
Q

What controls did you have in place to control dayworks cost?

A

1) Sign off from package manager on the day of the works
2) Photographs of the works at the start and end of the day
3) Records of what has been complete in the day
4) Cross check with aurora
5) Daily updates on works progress to provide best chances of meeting programme

42
Q

What form of contract did you have with the designer on your project?

A

JCT short form consultancy appointment