Procurement and Tendering Flashcards
What does a letter of intent do?
Method of instructing a contractor to proceed with work before a contract is formally entered into
Why would you choose Alternative 1?
OJEU tendering to narrow down from 100s of bids, ensures people stick to bids
What is partial possession?
When an area achieves practical completion, it can be occupied by the client
Half the retention must be released
Defect liability period begins
Insurance passes to the client
Contractor is not obliged to allow partial possession but cannot reasonably withhold permission
What is the difference between Management Contracting and Construction Management?
Management Contracting – client employs main contractor who employs sub-contractors
Construction Management – Client directly employs sub-contractors (direct contract)
How would you equalise tender returns?
Mean of the other tenders
Highest of the tenderers
Cost plan rate
What is an RFI?
Request For Information
A way for the tenderer to clarify queries with the design team
Do you know of an e-tendering service?
The RICS has one
What procurement route would you advice to a client who wanted the lowest cost achieved?
Open Tendering or construction management
What factors effect choice of procurement route?
Nature of project Scope of works Experience of the client Accountability Cost certainty requirement Start / completion date requirements Level of post contract change expected
What is a PQQ
Pre-Qualification Questionnaire
What are the advantages of 2 Stage Tendering?
Cost certainty
Buildability advice
Programme certainty
What are the positives of D&B?
Places the risk on the contractor Single point of responsibility Cost certainty Increased buildability Can be faster as early packages can be started before the design is finalised
What external factors should be considered when selecting a procurement route?
Changes to costs / availability of finance Interest rates Inflation changes Upcoming legislation Availability / demand of specialists
What does the JCT tendering practise note include?
2017
Public and private sector procurement is clearly split
Time for response is now the same as the OJEU notice periods
PQQ now 30 days
Tender period for public procurement now 35 days
What are the 4 routes of procurement?
Traditional Design and Build Construction Management Management Contracting Design Build Finance Operate (PFI and PPI)
What is Hybrid Procurement?
Non-Conventional procurement method
Soho Place – Large quantity of packages procured at first stage rather than just OH&P
Façade contractor novated across to the contractor
What is construction management?
Employer places a direct contract with each trade contractor and utilises the experience of a construction manager (main contractor) to act as a consultant and coordinate the works
Appropriate on large complex projects
What are the negatives of D&B?
Lack of competitiveness in second stages
Longer tender period
Lose control of the design
Quality control carried out by contractor
What would you do if a tenderer submits a qualified tender?
Give them the opportunity to amend the tender without amending the price making the bid compliant. If they refuse, then the bid will be deemed non-compliant and rejected
What is the difference between Management Contractor and Traditional?
MC – cost + fee / % (prime cost)
Traditional – fixed cost
What are the benefits of a framework agreement?
They allow a client to reduce timescales, learning curves and risks when continually commissioning construction
What would you include in a Tender report?
Executive summary Introduction List of tenders received Tender period Qualification identified Post tender adjustments Programme Revised tender sum Issues to be resolved Tender returns vs PTE / budget Recommendation
What are the OJEU thresholds for public procurement?
c.£181k for services
c£4.5m for works
What is the purpose of a PQQ?
Establish the suitability of prospective tenderers based on their record and technical capability
What is included within a Tender pack?
Invitation to Tender Instruction to Tenderers Certificate of Bona Fide Tender Scope of Works Tender Drawings and Specification / Employers Requirements Programme requirements As-Built information if fitout Environmental Considerations
What makes up a letter of intent
Acceptance of contractors offer and description of works
Value / contract sum
Duration and completion dates
Description of the form of contract and warranties / performance bond
Date of contract signing
Copyright
What are the positives of traditional?
Most competitive
Most linear form of tendering
Fixed price before contract signing
What are the risks of including provisional sums?
Is a sum on money set aside for works which may not be carried out, scope of work is not known so can’t give a firm price
Too many provisional sums reduce cost certainty