How much is concrete?
£150/m3
How much is rebar?
£1,200/t
How much is universal steel?
£2,100/t
How much is fabricated steel?
£2,400/t
How much is a blockwork wall?
£50/m2
How much is a paint finish?
£10/m2
How much are cavity barriers?
£50/m
How much is a sedum roof?
£400/m2
How much is Chinese granite paving?
£120/m2
How much is yorkstone paving?
£220/m2
How much is a plasterboard wall?
£60/m2
Typical allowance for sub-contractor prelims?
15% - 25% trade dependent
Typical allowance for main-contractor prelims?
17% - 25% project dependent (complexity)
Typical allowance for D&B risk allowance?
5%
Typical allowance for construction contingency?
5%
Typical allowance for OH&P?
5%
BREEAM requirement for Soho Place & Wedge House?
both excellent
What does the RICS believe are the three disruptive trends for the future of surveying?
Technology – data protection and handling - trust
Sustainability – driving construction to be better and how developments incorporate this
Talent / skills – recruiting the right people to challenge conventions and evolve correctly
Are you aware of any reports regarding teamwork?
The Latham Report – Constructing the Team 1994
How many faculties are there in the RICS?
17 – e.g QS, PM, Auctioneers, Rural, Commercial property, geomatics
RICS Brexit Paper?
RICS response to immigration skills white paper
Brexit: What Next – sets out potential scenarios
What happens if foreign workers leave the UK
What else has the RICS done to prepare for Brexit?
Formed a Joint Institutes Brexit Group – RIBA, CIOB and RTPI
RICS standards are globally applicable so will be relevant regardless of outcome
RICS regulation independent and worldwide so unaffected too
What are the RICS black books for?
Black books are a suite of guidance notes setting the best practice
What are the RICS Guidance notes?
Best practise – not compulsory but in the case of negligence it will be noted if followed
What are the RICS Practise notes
Compulsory – members must comply with them to maintain the highest professional standards
COMP and Property Measurement
How much is a Fan coil unit?
£6k
How much was an active fan tile?
£1k
What is this months MODUS on?
The Smart Issue - how technology can effect the built environment
Africa / Asia town planning for new cities
Urban Health
How was brexit risk dealt with in Soho Place?
Category 1 Packages - Fixed the exchange rate for 2 years
Category 2 Packages - used a collar (+ or - 3% was LOR risk)
Prov. sum of £100k for storage fees to enable orders to be placed and materials held in UK for just in time deliverys
What is the wall to floor and net to gross of Soho Place?
N:G = 71% total, 85% office floors W:F = 42%
What was the net to gross ratio for the Coworking?
79% on the floors
Aware of any Building Regulation updates?
Part B - Fire Safety
Grenfell fire - Hackitt review focussed on high rise buildings (10+ stories)
the Cube fire in bolton was low rise (6 stories)
so may focus on all buildings
What is included in the Hackitt report?
Creation of a Joint Competent Authority (JCA) (local authority, fire / rescue services and HSE)
Clearer dutyholders
better testing / sign off process
replacing desktop studies with real life testing
does not bad use of combustible materials
What is Labour’s 2019 election manifesto promising re. the industry?
100,000 new council houses per year
£1bn fire safety fund to fit sprinklers and replace combustible cladding on council blocks
Extend HS2 from Birmingham to Scotland
Carbon zero home standard
What is Lib Dem’s 2019 election manifesto promising re. the industry?
300,000 new homes a year by 2024
zero carbon homes and non-domestic buildings by 2021
How can you ensure no illegal workers on site?
include reference to modern day slavery act
Home Office can conduct a raid - BPS 2019
Current market conditions
contractors market
need to make contracts more appealing
how would you make contract terms more appealing to a contractor?
remove onerous conditions;
liquidated damages reduced,
reduce payment terms
How much is a softspot?
hard to cost - size dependent etc
rough cost £5 - 10k
What weight is a steel frame for a commercial office?
70 - 80kg/m2