Financial Control / Cost Reporting Flashcards
What are the different types of contingency?
Design - % if the concept budget allowed for design changes
Construction - % of the concept budget allowed for unforeseen changes during construction
Project – Design Contingency + Construction Contingency
Why would a cashflow be below the target cash flow?
Site conditions Adverse weather Resequencing of works Materials being stored off site (and not claimed for) Project behind programme Materials not being delivered on time Cashflow not accurate
What is a provisional sum?
Money included in the contract for work that cannot be fully defined at time of tender or work that is not sure if required (i.e. hazardous excavation)
What is the difference between a defined and undefined provisional sum?
Defined – A provisional sum of which an allowance is carried for programme and prelims
Undefined – No allowance for programme or prelims is allowed for within the contract sum
What is a final account?
A fair valuation of all works undertaken by the contractor
Includes all variations, provisional sums and loss and expenses
What are risks on construction projects?
External risks – economic, legal, political
Procurement risks
Choice of contract
Financial risks – exchange rate, funding
Site risks – occupied site, planning difficulties, unforeseen problems – ground conditions
Client risks – inappropriate consultant team, poor brief / coordination, incomplete design
Construction and delivery risks – weather, constructability, H&S
What are the risks in NRM?
Employers change risks
Employers other risks
Construction risks
Design development risks
What is the purpose of a Cost Report?
Monitor and manage cost throughout the project
Inform client on actual project cost against the budget
What would you include in a Cost Report?
Executive Summary Cost Summary Report Basis Contingency / risk Analysis Cash Flow Forecast Final account - VIP Variations to date Pending variations
What can a cash flow show?
If a project is running ahead / behind of programme
Project is failing
Contractors are experiencing problems / possible liquidation
The cost report compares actual cost against the budget, what is the budget?
Cost of work under the construction contract
Cost of work not under the construction contract (client advised) – contingency
NRM defines it as the PTE
How do you agree a variation?
Use a contract rate / similar BOQ item
Use a star rate – based on experience of what is far and reasonable
Use dayworks – Prime Cost + Labour + Plant + % addition
Should VAT be included within a cost report and why?
No, I am not qualified to advise on the VAT included on various items
What are the different payment mechanisms?
Stage payment
Milestone payments
Payment against activity schedule
Valuation of works done on site to date
How do the different payment mechanisms effect cashflow forecasting?
Level of predictability varies according to the payment mechanism
Stage payments – high predictability, low accuracy of work done
Milestone payments – high predictability, low accuracy of work done
Payment against activity schedule – okay predictability, okay accuracy of work done
Valuation of works done on site to date – Lowest predictability, high accuracy
What is a cashflow used for?
Monitor incoming and outgoing of cash on the construction project
Inform the client on when payments are required
Inform client / lender of when to release funds
Obtaining loans and bank monitoring
Contractor progress monitoring
Managing cash within a business
Forecasting business performance
Stakeholder management