Procurement and Tendering Flashcards

1
Q

How did you manage tender queries at UHL?

A

Tender Addendums and schedules

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Contents of tender report at UHL?

A

Executive summary
Received tender costs
Adjusted tender costs
Process used to normalise
Tender qualifications
Tender correspondence
Tender addendum schedule
Tender query schedule
Recommendation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Why single stage for Henderson’s?

A

Advantages
- Client gets a lump sum cost for all the works.
- Competitive pricing
- Used at Riba Stage 4 so full design
Disadvatages
- No input from contractors
- Relies upon detailed and well thought out design and tender docs
- Harder for client to introduce change without undermining the lump sum

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Pros and cons of Two Stage Tendering

A

Advantages
- MC can influence design and buildability and reduce design/construction risk.
- Ability to overlap design and tendering so quicker.
- Some competition in first stage over negotiated tendering.
Disadvantages
- Lack of competition in second stage
- Lack of cost certainty when MC taken to second stage.
- Increased programme to accommodate tender period (although there is overlap)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How do you deal with arithmetical errors in a tender return?

A

As per the instructions in the Instructions To Tenderers
JCT dictates the following
Option 1 - Contarctor must stand by error or withdraw
Option 2 - Contractor given opportunity to stand by or correct if a genuine error

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the main types of procurement?

A

Traditional
Design and Build
Management Contracting
Construction Management
Framework Agreements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is a Pre Construction Services Agreement (PCSA)

A

Enable clients to employ contractors before the main construction contract commences. Typically they are part of a two-stage tender process, used in the first stage to procure contractor involvement in the design process.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Novation

A

A novation agreement is the process whereby contractual rights and obligations (i.e both benefits and burdens) of a contract are transferred from one party to another.

In the case of D&B this means design rights and obligations are passed from client to MC after initial stages are complete

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the difference between Management Contracting and Construction Management?

A

Management Contracting
- Employer appoints MC
- MC appoints trades through work contracts
- Develops construction programmes and assist in costings and tender arrangements

Construction Management
- Employer directly appoints trades
- CM coordinates trade contracts
- CM coordinates schedules

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Give me an example of when you would advise using a two-stage tender

A

Complex design where you may require buildability input

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What would you typically include within a tender pack?

A

a. Form of tender
b. Works information
c. Draft contract
d. ITT
e. Pricing template etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

How would you treat a tender return which is received late? Would this differ for public or private clients?

A

Public - Automatically excluded (exceptions: force majeure)
Private - Can accept if it does not disrupt process or decline to maintain fairness

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Can you explain what normalization is?

A

Used during evaluation of tenders
- Where tenders are adjusted to create more significant separation between bidders
- Goal is to create clear distinction between bids

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is a tender report used for?

A
  • Summarise results of the tendering process
  • Provides detailed evaluation of bids received
  • Report helps client make informed decision
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is two stage tendering?

A
  • First stage to agree
    • The preconstruction fee
    • The management and
    • The OH&P to be applied to the second stage packages.
  • Second stage to procure the packages and agree fixed costs.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What factors would you take into account when advising a Client on a procurement route?

A
  • Time, Cost and Quality
  • Client experience and specific project factors
17
Q

What is a Bona Fide Tender Certificate?

A

A form to be filled in confirm the tender has been submitted in good faith

18
Q

Is E-tendering and an E-auction the same?

A

No.
- E-tendering is the submission of the tender online via portal or other
- E-auction will be where the other tendering parties can see where they are placed and can enter a reverse auction to revise their price with a BAFO process. (Best and final offer)

19
Q

What goes into a tender recommendation?

A
  • Executive Summary
  • Introduction - the background to the contract
  • The scope of the contract
  • Pre-qualification criteria
  • The tender evaluation criteria
  • Reasons for rejection of unsuccessful tenders
  • Reasons for the recommendation
  • Summary of any post-tender negotiations
  • Comparison with the pre-tender estimate
  • Any implications for the project
20
Q

How was the UHL- Post Mortem tender scored? Why do quality and pricing percentage splits change for each tender, why do clients choose different splits?

A

Client requirements and drivers of the scheme.

21
Q

You note frameworks, what impact on the tender process can using a framework have as opposed to an open market tender process?

A

Set framework rules and rates agreed with contractor, percentages for oncosts also typically agreed prior to engaging. Portal for the framework is used and contractors have to access through.