Procurement and Tendering Flashcards

1
Q

What is Traditional Procurement

A
  • Design seperated from construction
  • Client appoints consultant to design
  • Contractors then invited to tender
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

+/- Traditional Procurement

A

Advantages
* Retain control design
* Better price certainty
* Completed before design - all tenders based on same thing
Disadvantages
* Project duration could be longer due to extended pre contract design
* Design risk sits with client
* No input from contractor
* No overlap between design and construction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Types of Traditional Procurement

A

Lump sum (Low client risk)
Re-measure (Medium client risk)
Cost Reimburse (High client risk)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

When might Traditional be appropriate

A
  • Employer has specific design requirements
  • Cost certainty is important
  • When programme may not be client priority
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is Design & Build Procurement

A
  • Main contractor appointed to both design and construct
  • Client issued Employers Requirements, MC responds with Contractors Proposal
  • Design risk transferred to contractor
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

+/- Design and Build Procurement

A

Advantages
* Single point responsibility for D&B
* Contractor takes risk for D&B
* Can SOS sooner
* Harness expertise from MC
Disadvantages
* Relies on quality and detail in clients brief and employers requirements
* May be premium built in for MC risk
* Harder to compare returns
* Less control of aesthetics and quality

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

When might Design and Build be appropriate

A
  • Need SOS early
  • Client wishes to minimise risk
  • Complex projects benefit from contractor input
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are Employers Requirements

A
  • Produced by client
  • Sets out requirements in relation to project
  • What design and construction is basedon
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are Contractors Proposals

A
  • Prepared by contractor, response to ERs
  • Design produced based on ER which will need further development
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Is D&B good for refurbishment projects

A

Yes as risk of existing building is with contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is Construction Management

A
  • Trades contracted to client
  • Client directly appoints multiple trades
  • Client has Construction Manager to programme and coordinate the works
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

+/- Construction Management

A

Advantages
* Speed to SOS
* Shorter as overlap D&B
* CM can contribute to design and project planning
* Prices may be lower due to direct contract with trades
Disadvantages
* No price certainty until last package been let
* Risk with client
* Client has losts of consultants and contractors to manage

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Why might Construction Management be appropriate

A
  • Large complex projects
  • Early SOS
  • Flexibility in design
  • Price certainty before not key
  • Client experienced
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is Management Contracting

A
  • Trades contracted to Management Contractor
  • MC appoints trades
  • MC paid fee based on construction costs
  • MC has contractual link with each trade and is responsible for overall works
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

+/- Management Contracting

A

Advantages
* Shorted as overlap with D&B
* Contractors can contribute to design
* Single point responsibility (MC)
Disadvantages
* No price certainty until last package let
* Change in design to later packages may effect packages already let
* Little incentive from MC to reduce cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Why might Management Contracting be appropriate

A
  • Input from MC
  • Early SOS
  • Flexibility in design
  • Cost certainty not priority
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What decides the Procurement Route

A

Clients objectives and key drivers in terms of Time, Cost, Quality and Risk allocation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What is Procurement

A

Overall act of obtaining goods and services

19
Q

What is Tendering

A

Method of obtaining a price and resources necessary to carry out required works

20
Q

What is Single Stage Tender

A
  • Usually dont at RIBA stage 4
  • Tenders price for whole construction works
  • Compete on identical information
  • Returns analysed in terms of cost and quality
21
Q

+/- Single Stage

A

Advantages
* Client gets lump sum cost
* Competitive pricing
Disadvantages
* No input from contractor
* Relies on detailed and well thought out design and tender docs
* Programme implication to include tender period

22
Q

If you had a £25mil new build on a D&B contract with a single stage tender, how long would you allow for the tender period

A
  • Tender period largely depends on complexity of the project
  • 10 - 12 weeks as it may take time to interpret the ERs
23
Q

What is Two Stage Tender

A

Stage 1
* Tender enquiry documentatin issued to tenderers
* Preferred MC chosen on quality of bid, quality of team, prelims and OH&P
* Preferred contractor joins team on consulting basis using Pre construction services agreement
Stage 2
* Preferred contractor works with team to complete the design
* Once design has progressed, contractor enters into detailed contractor negotiation to agree price

24
Q

+/- Two Stage

A

Advantages
* Early MC appointment to gain technical input
* Early SOS (design & tender overlap)
* Increased opportunity to VE and identify risk (Traditional)
Disadvantages
* Lack of cost certainty at second stage
* Additional fee for pre construction
* Potential for negotiation stage to fail
* No incentive for contractor to mitigate risk (Traditional)

25
Q

What is Pre Construction Services Agreement

A

Allows client to employ contractor before main construction contract

26
Q

What is Buildability

A
  • Ability for a design to be constructed and maintained efficiently and safely
  • Typically refers to early pre construction advice from a contractor
27
Q

Advantages on Buildability

A
  • Improves efficiency in construction
  • Can save programme and cost
  • Make building more efficient to maintain
28
Q

What is Negotiated Tender

A

Where single contractor is approached and appointed based on experience and expertise

29
Q

+/- Negotiated Tendering

A

Advantages
* Simple, no tender analysis
* Quick form of tendering
* Client has flexibility over choice
Disadvantages
* Less cost certainty before commitment
* Premiuim paid due to lack of competition (difficult to prove value for money)

30
Q

What is a Form of Tender

A
  • A formal statement the contractor fills in
  • MC to put company name, address and sum
  • Formal acknowledgement
31
Q

When seeking tenderers, in addition to price what else would you look for

A
  • Track record
  • Proposed team
  • CVs
  • Methodology
  • Programme
32
Q

When tenders have been submitted, what should be examined

A
  • Arithmetical errors
  • Pricing errors
  • Pricing methods
  • Qualifications
  • Check form of tender
  • Compare against ER
33
Q

What happens if tender is late

A
  • If public sector, documents cannot be accpeted
  • If private, client may accept but would recommend they not
34
Q

How to deal with errors in JCT

A

Option 1 - Standby or withdraw
Option 2 - Standy or correct if genuine error

35
Q

Dangers of accepting a low tender

A
  • May not priced all works
  • Lower quality
  • May try to recover costs once on site elsewhere
36
Q

What would you do if you considered a contractor tendering may be in financial difficulty

A
  • Check companies accounts
  • Request references
  • Consider a performance bond
  • Consider PCG
  • Raise concern with client
37
Q

On what ground would you advise to re tender

A
  • Not enough returns
  • Tender procedure believe to be compromised
  • Design changes been too significant
38
Q

If in a contractors return they have an item marked as provisional, what would you do

A

See further info, ask for it to be removed

39
Q

Recommended Contract for particular Procurement Route

A

Traditional (Lump Sum)
JCT Standard w/ and w/o quants
JCT Intermediate
JCT Minor Works
NEC Option A

Traditional (Re-measurement)
JCT Standard w/ Approx quants
JCT Measured Term
NEC Option B

Design and Build
JCT Design and Build
JCT Major Project Construction
NEC Option A-E

40
Q

Purpose of PTE

A
  • Last cost check before tender
  • Design should be sufficiently developed
  • Used to compare against returns
41
Q

If delivery programme is tight, how can you give comfort to contractor regarding damages

A

Contract can include LAD free period - e.g. first 3 weeks no levied

42
Q

If the team has asked for an alternative programme in return and the alternative is longer, would you expect costs to increase

A

By asking a contractor to complete a project in a period which is too short, you could be paying premium e.g. acceleration.
Therefore if programme extends you could pay less as you are not paying OOH works

43
Q

Are you aware of any guidance notes issued by RICS associated with tendering strategies

A

Tendering Strategies 1st Edition