KEY ISSUE ONE Flashcards

1
Q

KI1 - What was allowed for in the contract in terms of the basement space?

A

GIFA was roughly 44m2
Height was roughly 1.99m

GIFA to be roughly 35m2
Height to be roughly 1.83m

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

KI1 - Did you provide costs for all three options?

A

Option 1 - 30k
Option 2 - 40k
Option 3 - 20k (saving in basement propping - 2 weeks)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

KI1 - The basement was infilled, how was this done, and were there any structural considerations in relation to this?

A
  • Break out existing slab
  • Formwork created at pile locations
  • Mass fill concrete basement level
  • Imported fill & compact to pile locations
  • Formwork to ground beam perimeter prior to second pour
  • Fill from stockpiles
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

KI1 - You mention that you advised your client on the impact on the structure of each of the basement options, are we qualified to give structural advice?

A

No, not covered by PI Insurance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

KI1 - If we gave bad advice, which insurances are in place to protect us and the client?

A

PI Insurance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

KI1 - How did you assess the impact on programme of each of the options?

A
  • Project manager / Contractor, close collaborative working. Interjecting / contributing where possible.
  • If pushed further… critical path analysis, close scrutiny of submitted programmes
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

KI1 - How would unknown factors to the ground or ground conditions be dealt with

A

Contractor risk, no provision in an unamended JCT, follows common law.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly