Contract Practice Flashcards
What is a Loss and Expense claim and how would you go about reviewing
A matter where the client is responsible that affects the progress of the work
Review if relevant matter
Cost incurred so cant claim for OH+P, only loss of profit.
What goes into Contract Docs
The contract itself
Contract Particulars
Pre Construction Information
Pricing Document - Contract Sum
Prelims Document
Contract Drawings
Specifications
Tender Correspondence
Tender Queries
Tender Addendums
Give some examples of contract particulars you included in your JCT Contract.
Pricing Document
Base Date
Date of possessions
Date for Completion
CDP
LAD’s
Rectification Period
Fluctuations
Interim Payments - (first date for payment)
NEC Options
Option A: Priced contract with activity schedule.
Option B: Priced contract with bill of quantities.
Option C: Target contract with activity schedule.
Option D: Target contract with bill of quantities.
Option E: Cost reimbursable contract.
Option F: Management contract.
Option G: Term contract
Whats are LAD’s
- Liquidated and ascertained damages
- Predetermined and agreed between parties in contract
When may a JCT minor works contract be appropriate for a project?
- Short duration straight forward construction
- JCT guidance says value up to £100k but simple in nature
- Lump sum - design completed prior
- Employer provides spec, design and sow
What is on an interim payment certificate?
- Valuation date
- Issue date
- Gross val
- Retention percentage and amount
- Less than previous amount
- Payment
- Employer details
- Contractor details
What is a Relevant Matter? What is a relevant event?
Relevant Matter - Events that entitle contractor to loss and expense
Relevant Event - Events that entitle contractor to an EOT
How do you review contractor variations
- check scope
- check validation
- check rates
- check measures
If a client asked for assistance with calculating a sum for LD’s, how would you approach it
Cant advise on a value, but can advise on how they might get to a “estimation of genuine loss
How does JCT differ from NEC
- EW and risk register encourage proactive approach on NEC, JCT is more reactive
- CEs deal with money and time, JCT has variations for money and L&E/EOT for time
- No QS mentioned in NEC
- Programme is contract doc in NEC
- Short periods of reply on NEC which incentivises responses
- NEC concise and plain english
Who administers a JCT SBC? DB? NEC Contract?
JCT SBC - CA
DB - EA
NEC - PM
If a client is late to pay a contractor, what could the contractor do?
Contractor can notify to suspend the works
How would you advise your Clients on using standard v bespoke forms of Contract
Standard contracts
Pros
- Widely recognised & understood within the industry
- More cost effective and time efficient
Cons
- May not cover all unique aspects of project
Bespoke
Pros
- Tailored to specific requirements
- Can address specific risks
Cons
- Usually more expensive
- Time consuming to draft
What is the Housing Grants, Construction and Regeneration Act 1996? (Known as the Construction Act)
Intended to ensure that payments are made promptly throughout the supply chain and that disputes are resolved swiftly. Provisions of the act include:
- The right to be paid in interim, periodic or stage payments
- The right to be informed of the amount due, or any amounts to be withheld
- The right to suspend performance for non-payment
- The right to adjudication
- Disallowing pay when paid clauses