GENERAL Flashcards

1
Q

Why was JCT Intermediate contract used?

A
  • Traditional Procurement
  • Works fully designed, detailed documents provided, employer responsible
  • Fairly detailed contract provisions, no complex service installations
  • Proposed works simple in nature, involving recognised basic trades
  • Mid sized project
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What would you say the disadvantages of JCT are?

A
  • More reactive than proactive
  • Complex language, can be challenging to understand
  • Standardised, not easily adaptable
  • Can be costly
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Why do you think a single stage tender was selected?

A

As it was Traditional:
- Most competitive price
- Most linear form of tendering

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Did you not think that the project being a heritage asset could have benefited from early contractor involvement by using a two stage?

A
  • Shell & Core only - not usual heritage conditions
  • Not a listed building
  • If two stage traditional, contractor has no incentive to mitigate risk, most risk client side
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Can you talk me through the process of assessing a L&E claim

A
  • Check if its a relevant matter
  • Check that is actual loss incurred
  • Once ascertained, should be added to the contract sum immediately and paid in next payment
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Loss and expense claims, how is loss proven?

A
  • Sub-divide into constituent parts of the loss
    • Prolongation - Look at additional hire charges
    • Disruption labour - Check sign in book
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

I note you stated the building is a non designated heritage site, what does this mean & are there any planning implications

A
  • Degree of significance
  • Merits consideration in planning because of heritage interest
  • Designated heritage assets are Usually listed
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

In the UK, who decides whether a building is a heritage asset?

A

Historic England

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

You mention that the project was a heritage asset. How did you go about sourcing rates for your cost estimates?

A
  • In house cost data
  • Market test where possible
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

At the start of the presentation, you noted managing risk as part of your role. How did you specifically manage risk on this project?

A
  • Commercial management of risk.
  • Contingency in cost report linked to risk register
  • A lot of risks that were early in programme were realised
  • Contingency based off post-mitigated figures. Had to communicate that more contingency would be required
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Was there a reason more site investigations hadn’t been undertaken before commencing works on site?

A
  • There’s always limitations to site investigation
  • Contractor started digging and found an obstruction / something in the ground
  • Had to wait for site investigation report
  • Needed a main contractor to dig trial pits / bore holes
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Given the age of the building what were the risks that might be present?

A
  • Asbestos is main one, pre 2000
  • Building life of materials
    • Roofing (30 years tiles)
    • Structure (150 years)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

You mentioned you took the project on from Stage 5, did you review the initial allowances, contract sum and any prov sums?

A
  • Communication with leaving CM (overlap before he left), RLB were PM, met project team, QA reviews of work
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

You mention that you had a Contract Sum of circa £900k and an estimated Final Account of £1.1m, how did you manage the client expectations throughout the project on the outturn cost of the project?

A
  • Regular communication through cost reporting / progress meetings
How well did you know this?
1
Not at all
2
3
4
5
Perfectly