Contract Administration - TO COMPLETE Flashcards
Can you explain a few of the key differences between the JCT and NEC suite of contracts?
- NEC uses 6 main options and secondary options / JCT uses separate contracts
- NEC written in laymen terms
- No QS mentioned in NEC only PM
- NEC tries more collab approach
- NEC = CEs / JCT = Variations, L&E and EoT
- NEC had periods of reply
- Programme is a contract doc in NEC
- NEC uses EW (proactive) JCT is more reactive
How is the Programme managed differently in NEC as opposed to JCT?
Programme is a contract document which the contractor has to submit or monies can be withheld.
Can you explain how you would implement a change control procedure in D&B?
Use the change control procedure set out in the contract
- D&B contractor would submit a CRF to myself and the EA
- EA agrees whether change
- I then agree cost and recommend to EA
- EA gets approval from Client and then issues an instruction for the change.
What are the dangers of working on a bespoke contract?
It’s bespoke so less understood to all parties. Great care must be taken when administering
Role of Contract Administrator under JCT?
- Administers the construction contract
- Must act honestly and reasonable
- Issues instructions & EOT
- Certifies sums due
- Assesses delay and grants time and cost relief
How does the role of Employers agent differ from contract administrator?
- EA is seen as clients advisor
- Required to protect clients interest (CA must act impartially)
What is Practical Completion?
The works are generally considered to be practically complete when there are no outstanding defects and the building can be put to its intended use.
What would you do if the contractor has not completed by the pc date?
If I were acting as either the CA or EA I would advise the client to issue a non-completion certificate.
If date fixed after the notice then date cancels out the notice. Issue another if necessary. Client must give notice of intention to the contractor to deduct LAD’s. 5 days before the date of final payment.
Novation
When the rights and obligations of one party are transferred to another party.
Assignment
- Transfer of a right from one party to another.
- E.g. transferring a collateral warranty to a tenant on completion.
Novation vs Assignment
Assignment does not transfer burden, novation transfer both rights and obligations, creates a new contractual relationship
Items in a valuation
- Measured works
- Variations
- Claims ascertained
- On site materials
- Off site materials (if included in the contract provisions)
- Preliminaries
- OH&P
- Retention
- Deductions for previous payments
What are the main parts of JCT
- Recitals
- Articles
- Contract Particulars
- Attestation
- Conditions
- Schedules
How can you accelerate
Change working method, double shifting, extended hours
Difference between CA and employers agent
CA - Traditional
EA - Design and Build
Payment provisions under JCT Standard 2016
Application for payment - No less than 7 days before due date
Due date - 7 days after the application for payment
Interim Certificate - Issue by CA 5 days after the due date
Pay Less Notice – 5 days before final payment
Final Payment - 14 days after due date
Payment under JCT D&B 2016
Same as the standard but the valuation is up to the due date.
Due date - day of valuation and when the valuation it said to valid from
Interim Certificate - Issue by CA 5 days after the due date
Pay Less Notice – 5 days before final payment
Final Payment - 14 days after due date
Payment provisions under JCT D&B 2016
Option A - Stage Payments
Option B - Periodic payment (valuation to date)
Same payment provisions regardless of option
What is included in a payment cert
Due date
Final date for payment
Gross valuation
New valuation
Retention statement
If the project wasn’t completed on PC date, as CA what would you issue?
Certificate of non-completion
What does cert. of non-completion mean to the contractor?
They are liable to pay LAD’s
What does cert. of non-completion mean to the employer?
They can claim for liquidated damages