Project Finance Flashcards

1
Q

What would be included in a cost report/financial statement

A

Exec Summary
Contract sum
Variations
Valuations
Cashflow and s curve
Risk allowances/Contingency
Proposed final account

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

You have mentioned interim payments, can you please explain the timescales for payments with regard JCT.

A

(-)7 days - MC issue valuation
0 days - Due date
+5 days - CA Issue payment cert
+ 9 days - Client issue a pay less notice
+14 days - final date for payment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Can you briefly explain how contingency is calculated and develops through the RIBA stages

A

This typically refers to costs, and is an amount that is held in reserve to deal with unforeseen circumstances.

Often expressed in terms of percentages usually reducing as the project progresses up to contract.

For example:
- 15% at feasibility stage

  • 10% in elemental cost plan
  • 5% on the contract value

Covers 4 main areas of risk;
1. Design Development Risk
2. Construction Risk
3. Employer Instruction Risk
4. Employer Other Risk

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is a provisional sum

A

If employer is unsure if works are to be completed so can be taken out.
Where works are programmed and will be performed but there is a lack of design or information to price accurately.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the importance of a cash flow forecast?

A

Checks budget
Forecast final account
Track progress against cashflow

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How would you manage the costs on a risk register as a project progresses?

A

Release contingency according to cashflow as risks are realised / not realised

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the difference between a defined provisional sum and undefined provisional sum

A

Defined must be allowed for in the programme

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the purpose of providing clients with financial statements?

A

Advise on project expenditure to enable them to make financial decisions and stay informed with project changes, documents our advice

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the JCT Standard Form ‘Valuation Rules’?

A

Contract Rates: where work is of similar ‘character’ to work in the original Contract Documents then the valuation of the variation shall be consistent with rates, prices or amounts of work in the proceed document.

Fair Rates and Prices: Where work is not of a similar ‘character’ then it should be valued at ‘fair rates and prices’.

Dayworks: Method of valuing work which cannot properly be valued by measurement.

Contractor’s quotations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How are prelims dealt with in valuations

A

Broken down into fixed costs and time related costs and assessed as such rather than a %.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

How is retention dealt with in valuations

A

Retention is deducted as per the retention bond value in the contract docs. Retention is halved once PC is reached.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

How are prov sums dealt with in valuations

A

If the works have been completed that are associated with the prov sum and the works formally instructed they can be included.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Considerations when advising client on Cashflow

A

’- Holidays and cyclic events such as winter weather
- Retention (including static end for defect rectification period)
- Certification Period (Due Date to CA issuing payment cert)
- Payment Period (Payment Cert to Payment) - usually 14 days
- Sectional completion/partial possession (individual s curves and retention releases)
- Risk (either spread over S curve or using dates on risk register)
- Prov sums (these are a risk as could be over or under the value and make the cashflow in-accurate)
- Fees and development costs (Consultants fees, direct costs, VAT, materials on site)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Reasons for variance in Cashflow

A

Lower
- Site conditions
- Adverse weather
- Programme issues
- Various delays
Higher
- Front end loading
- Variations
- Ahead of programme
- Distressed contractor
- Cashflow not accurate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What would you include in a cashflow in addition to the direct cost of the works?

A

Retention
Variations
Prov Sums
VAT (maybe but complicated)
Materials on site

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What would you omit in a cashflow in

A

Anything as long as noted to the client
VAT
Materials off site

17
Q

Effect of Loss and Expense Claims on Cashflow

A

Update cashflow for best case and worse case loss and expense additions.
Also include for any likely programme extensions if EOT as well.
Update cashflow regularly as to when the claim will likely be paid.
Could be after PC

Cashflow can be used to assist in Loss and Expense claim. I.e. if actual expenditure does not differ greatly from the contractors cashflow. A contractor could also use a cashflow to point out that

18
Q

Effect of Liquidated Damages on Cashflow

A

Do not include in Cashflow until extent has been formally agreed with the contractor.
Could artificially reduce liability to contractor in terms of construction costs
Note that because this is a genuine pre estimated calculation of loss overall the project should not see a saving as the LAD’s cover costs seen elsewhere because of the delay.

19
Q

Effect of VAT on Cashflow

A

Usually not included at this is subject to the clients circumstances and requires outside advise.

20
Q

Effect of procurement route on cashflow

A

Traditional
- Separate construction costs from design fees and risk allowances

Design and Build
- Include element of design fees and risk allowance into construction costs

Cost Reimbursable/Target Costs
- Not lump sum so cashflow forecast would initially be based on target cost
- Cashflow must be updated regularly when actual costs are known from pain/gain.

Construction Management (Packaged works)
- Follows similar to traditional but with multiple cashflows for each package
- Payment terms may be different for each package
- Payment dates will differ
- Construction manager fee to be considered

21
Q

Can you explain the importance of a contractor noting they are behind cashflow?

A

Notes that they are behind schedule or the cashflow requires review

22
Q

“Contractor gives you a cash flow forecast and you notice they are behind, what do you advise your client?”

A

That they might be behind programme or back loading.

23
Q

If you had a contract sum and a programme from a contractor, how would you produce a cash flow forecast?

A

Assign contract sum against the programme tasks, produce cost incurred per month.

24
Q

Why do you think a cash flow forms an S’Curve?

A

Enabling works cost little then bigger packages such as steel and superstructure, costs then reduce towards end for finishes and fit out.

25
Q

Difference between Cost and price

A

Cost - cost of labour works and plant
Price - What the client will pay

26
Q

Loss and Expense - Is OH+P included

A

Only entitled to claim for loss of profit. Cant be seen to loss.

27
Q

What is purpose of financial report

A

Advise on project expenditure to enable them to make financial decisions and stay informed with project changes, documents our advice

28
Q

What effects outturn of construction costs

A

Fixed cost - No impact
Provisional Sums - Costs updated (+/-) when defined and undefined prov sums are firmed up
Provisional Quantities - Where quantities are firmed up
Prime cost sums - Where specification is firmed up
Daywork allowances - When allowances for labour, plant and materials are firmed up
Variations - Instructions, anticipated instructions, loss and expense, risk allowances (contingency) and fluctuations.

29
Q

How is VAT dealt with in cost reporting

A

Always excluded

30
Q

What is change control procedure JCT

A

CA notifies MC of change.
Issue variation quotation (amount adjustable to contract sum and any loss or expense)
A fair and reasonable amount to produce the quotation
Client has 7 days to notify if not agreeable, if agreeable CA instructs.

31
Q

What is a prime cost sum

A

NRM1 - Where the specification i.e. the tile brick has not been defined. But what has been firmed up is the associated BWIC and labour associated.

32
Q

What is a provisional quantity

A

The provisional quantities of work whose specification is known, but the exact amount has yet to be determined.

33
Q

What are the JCT timescales for submitting a Final Account

A

Contractor should submit by maximum 6 months
Final account should be agreed in 3 months following issue

34
Q

What should be issued with final accounts

A

Substantiation to variation figures
Sub contractor quotes
Daywork sheets
Loss and expense claims with build up
Build up of fluctuations

35
Q

What would be included in a fee proposal

A

Fee
Description works
Company profile
Scope of services
Experience/CV’s
Anticipated programme
When its valid from and to
PI insurance