Project Finance Flashcards

1
Q

What would be included in a cost report / financial statement

A

Exec Summary
Contract sum
Variations
Valuations
Cashflow and s curve
Risk allowances/Contingency
Proposed final account

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

You have mentioned interim payments, can you please explain the timescales for payments with regard JCT (standard and D&B)

A

No less than 7 days before due date- MC issue valuation (D&B - Val is up to due date)

0 days - Due date
+5 days - CA Issue payment cert
+ 9 days - Client issue a pay less notice
+14 days - Final date for payment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is a provisional sum

A
  • An allowance included for:
  • Not sufficiently defined, designed or detailed to allow accurate costing
  • Work that employer may / may not want carried out
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the importance of a cash flow forecast?

A

Plan expenditure
Forecast final account
Track progress against cashflow

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How would you manage the costs on a risk register as a project progresses?

A

Release contingency according to cashflow as risks are realised / not realised

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the difference between a defined provisional sum and undefined provisional sum

A

Defined must be allowed for in the programme and prelims

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the purpose of providing clients with financial statements?

A
  • Provide financial overview for client
  • Inform likely outturn cost of project
  • Understand potential savings / additional funds
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the JCT Standard Form ‘Valuation Rules’?

A

Contract Rates: where work is of similar ‘character’ to work in the original Contract Documents then the valuation of the variation shall be consistent with rates, prices or amounts of work in the proceed document.

Fair Rates and Prices: Where work is not of a similar ‘character’ then it should be valued at ‘fair rates and prices’.

Dayworks: Method of valuing work which cannot properly be valued by measurement.

Contractor’s quotations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How are prelims dealt with in valuations

A

Broken down into fixed costs and time related costs and assessed as such rather than a %.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How are prov sums dealt with in valuations

A

If the works have been completed that are associated with the prov sum and the works formally instructed they can be included.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Considerations when advising client on Cashflow

A
  • Holidays (eg winter / xmas)
  • Retention (end of defect period)
  • Certification period
  • Payment period
  • Sectional completion / Partial possession (Retention)
  • Risk
  • Prov sums
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Reasons for variance in Cashflow

A

Lower
- Site conditions
- Adverse weather
- Programme issues
- Various delays

Higher
- Front end loading
- Variations
- Ahead of programme
- Distressed contractor
- Cashflow not accurate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What would you include in a cashflow in addition to the direct cost of the works?

A

Retention
Variations
Prov Sums
VAT (maybe but complicated)
Materials on site

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What would you omit in a cashflow

A

Anything as long as noted to the client
VAT
Materials off site

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Effect of Loss and Expense Claims on Cashflow

A
  • Update for best and worse case LOE additions
  • May include EoT if necessary
  • Update for when claim will be paid
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Effect of Liquidated Damages on Cashflow

A
  • Dont include until agreed with contractor
  • Doesnt act as saving as it is genuine loss client has received - balances out
17
Q

Effect of VAT on Cashflow

A

Usually not included at this is subject to the clients circumstances and requires outside advise.

18
Q

Effect of procurement route on cashflow

A

Traditional
- Separate construction costs from design fees and risk allowances

Design and Build
- Include element of design fees and risk allowance into construction costs

Cost Reimbursable/Target Costs
- Not lump sum so cashflow forecast would initially be based on target cost
- Cashflow must be updated regularly when actual costs are known from pain/gain.

Construction Management (Packaged works)
- Follows similar to traditional but with multiple cashflows for each package
- Payment terms may be different for each package
- Payment dates will differ
- Construction manager fee to be considered

19
Q

Can you explain the importance of a contractor noting they are behind cashflow?

A

Notes that they are behind schedule or the cashflow requires review

20
Q

“Contractor gives you a cash flow forecast and you notice they are behind, what do you advise your client?”

A

That they might be behind programme or back loading.

21
Q

If you had a contract sum and a programme from a contractor, how would you produce a cash flow forecast?

A

Assign contract sum against the programme tasks, produce cost incurred per month.

22
Q

Why do you think a cash flow forms an S’Curve?

A

Enabling works cost little then bigger packages such as steel and superstructure, costs then reduce towards end for finishes and fit out.

23
Q

Difference between Cost and price

A

Cost - cost of labour works and plant
Price - What the client will pay

24
Q

Loss and Expense - Is OH+P included

A

Only entitled to claim for loss of profit. Cant be seen to loss.

25
Q

What effects outturn of construction costs

A

Fixed cost - No impact
Provisional Sums - Costs updated (+/-) when defined and undefined prov sums are firmed up
Provisional Quantities - Where quantities are firmed up
Prime cost sums - Where specification is firmed up
Daywork allowances - When allowances for labour, plant and materials are firmed up
Variations - Instructions, anticipated instructions, loss and expense, risk allowances (contingency) and fluctuations.

26
Q

How is VAT dealt with in cost reporting

A

Always excluded

27
Q

What is change control procedure JCT

A
  • Contractor notified of change
  • Contractor issues variation
  • QS to review
  • 7 days to notify if not agreeable, if is then CA instructs
28
Q

What are the JCT timescales for submitting a Final Account

A
  • Contractor should submit by maximum 6 month
  • Final account should be agreed in 3 months following issue
29
Q

What should be issued with final accounts

A

Substantiation to variation figures
Sub contractor quotes
Daywork sheets
Loss and expense claims with build up
Build up of fluctuations

30
Q

How are provisional sums expended

A
  • CA issues instruction
  • Prov sum omitted and replaced with actual cost
31
Q

How are provisional sums dealt with in final account

A
  • CA should have issued instruction to omit all prov sums
  • Instruction to show add and omit
32
Q

How does NEC deal with provisional sums

A
  • Unamended NEC doesnt provide use of prov sums
  • NEC approach - if unclear and price cant be provided, item excluded until defined
33
Q

Can contractor claim additional prelims or EOTwhen firming provisional sums

A

No, if defined it should have been allowed for in programme and prelims

34
Q

Contractor has made large and in your opinion unrealistic claim for L&E, how would you deal with it

A
  • Highlight concern with figure submitted
  • Assume CA has agreed claim is valid, carry out due diligence checks and assess
  • Update client regularly until resolved