PMP Review Flashcards
What are Functional, Projectized and Matrix Orgs?
Functional - One where team members work for a department; may be loaned to a project at times and the PM has little to no power
Projectized - PM is manager of projects and resources and has complete authority
Matrix - Combo with functional managers and project managers; PM has more power in Strong Matrix, equal in Balanced, and less in Weak
Delphi Technique
Gathering expert opinion without participants knowing who else is being polled; prevents biasing opinions or groupthink
Nominal Group Technique
Brainstormed ideas are voted upon and ranked by priority
Planned Value (PV)
Planned % Complete * Budget (BAC)
Actual Value (AV)
Actual % Complete * Budget (BAC)
Actual Cost (AC)
Sum of actual costs
Cost Variance (CV)
EV - AC
0 means project on budget
Negative means variance and over budget
Positive means under budget
Schedule Variance (SV)
EV - PV
0 means project on schedule
Negative means variance and behind schedule
Positive means ahead of schedule
Cost Performance Index (CPI)
EV ÷ AC
Equal to or greater than 1 indicates a favorable condition
Less than 1 indicates an unfavorable condition
Schedule Performance Index
EV ÷ PV
Equal to or greater than 1 indicates a favorable condition
Less than 1 indicates an unfavorable condition
Estimate At Completion (EAC)
BAC ÷ CPI or
AC + (BAC - EV)
Actual cost to date plus an estimate of costs for remaining authorized work to provide an accurate projection of cost at the completion of the project.
Estimate to Completion (ETC)
EAC - AC
Forecast of how much more money will need to be spent to complete the project.
Variance At Completion (VAC)
BAC - EAC
Shows the difference between the budget (BAC) and estimated cost (EAC)
To-Complete Performance Index (TCPI)
(BAC-EV) ÷ (BAC-AC)
A projection of cost performance that a project must achieve on the value of the remainder of the project work to achieve a specified end result.
Pareto Chart
Assists in prioritizing corrective actions as the issues with the greatest impact are displayed in order. (Quality Mangement)