Project Manager’s ____ last as long as the project they manage and applies only to that project
A
authority
1
Q
Writing a Project Charter
When the project is approved, the final step of the ____ process is writing a project charter
A
initiating
2
Q
For that reason, it is important that people understand what the project manager is ____ to do
A
authorized
3
Q
Team members need to understand the ____ authority
A
project manager’s
4
Q
_____ publishes the project charter to formally announce the project and to communicate the responsibility and authority that you have as assigned project manager
A
Project sponsors
5
Q
This document includes:
- project name
- purpose of the project
- one sentence summary of goals and objectives
- name of the project manager
- the project manager’s responsibility
- the extent of project manager’s authority e.g. requesting for resources and signing contracts
- formal declaration of sponsors
A
Project Charter