Planning: Schedule Management Flashcards
The processes required to manage timely completion of the project.
Project Schedule Management
The process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.
3.6 Plan Schedule Management
What is this the key benefit for?
It provides guidance and direction on how the project schedule will be managed throughout the project.
3.6 Plan Schedule Management
A component of the project or program management plan that establishes the criteria and the activities for developing, monitoring, and controlling the schedule
Schedule Management Plan
Thresholds indicating allowable schedule variation before action must be taken
Control thresholds
The process of identifying and documenting the specific actions to be performed to produce the project deliverables.
‘3.7 Define Activities’
A documented tabulation of schedule activities that shows the activity description, activity identifier, and a sufficiently detailed scope of work description so project team members understand what work is to be performed.
Activity list
Multiple attributes associated with each schedule activity that can be included within the activity list
can include: activity codes, predecessor activities, successor activities, logical relationships, leads and lags, resource requirements, etc.
Activity Attributes
A distinct, scheduled portion of work performed during the course of a project.
Activity
VERBS!
A list of significant points or events in a project
ex: submission of a prototype to the FDA
Milestone list
The process of planning near-term activities in great detail and longer-term activities at a high level.
Iterative, ongoing process, and is a form of progressive elaboration
Rolling-Wave Planning
The work defined at the lowest level of the WBS for which cost and duration are estimated and managed.
Work Package
NOUNS!
Any unique and verifiable product, result, or capability to perform a service that is required to be produced to complete a process, phase, or project
Deliverable
Activities are never included in the ___.
Activities are shown separately on the ___.
WBS
Activity List
The process of identifying and documenting relationships among the project activities.
3.8 Sequence Activities
A graphical representation of the logical relationships among the project schedule activities.
Project Schedule Network Diagram
A method used in Critical Path Methodology (CPM) to build a network diagram showing activity relationships
Precedence Diagramming Method (PDM)
Name and describe the four types of PDM relationships.
- Finish-to-start: A finishes before B starts (most common)
- Start-to-finish (A starts before B finishes (rarely used)
- Finish-to-finish: A finishes before B finishes
- Start-to-start: A starts before B starts
What does PDM stand for and what is it also known as?
Precedence Diagraming Method
Activity on Node (AON)
What are the four types of Dependencies?
Mandatory (aka hard logic or hard dependencies)
Discretionary (aka soft logic or preferred dependency)
External
Internal
Dependency that is contractually required, physical limitations, etc.
Mandatory dependency
(aka hard logic or hard dependency)
Dependency where there is a preferred order or logic
(focus on these when you need to re-sequence tasks)
Discretionary dependency
(aka soft logic or preferred dependency)
Dependency outside the project team’s control
ex: must wait for FDA approval before proceeding with next steps in development
External dependency
Dependency generally within the control of the project team.
Internal dependency
The amount of time whereby a successor activity can be advanced with respect to a predecessor activity.
Lead
The amount of time whereby a successor activity will be delayed with respect to a predecessor activity.
Lag
an information system consisting of the tools and techniques used to gather, integrate, and disseminate the outputs of project management processes.
Project Management Information System (PMIS)
Visual representation of the relationships between schedule activities.
Project Schedule Network Diagrams
The process of estimating the number of work periods needed to complete individual activities with estimated resources.
‘3.9 Estimate Activity Durations’
The total number of work periods required to complete an activity or WBS component, expressed in hours, days, or weeks.
Duration
The number of labor units required to complete a schedule activity or WBS component, often expressed in hours, days, or weeks
Effort
Supporting documentation outlining the details used in establishing project estimates such as assumptions, constraints, level of detail, ranges, and confidence levels.
Basis of Estimates