M&C: Integration Management Flashcards

1
Q

Those processes required to track, review, and regulate the progress and performance of the project;

identify any areas in which changes to the plan are required;

and initiate the corresponding changes

A

Monitoring and Controlling Process Group

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Collect project performance data, produce performance measures, and report and disseminate performance information

A

Monitor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Comparing actual performance with planned performance, analyzing variances, assessing trends to effect process improvements, evaluating possible alternatives, and recommending appropriate corrective action as needed

A

Control

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

A quantifiable deviation, departure, or divergence away from a known baseline or expected value

A

Variance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

An actual condition that is different from the expected condition that is contained in the baseline plan

A

Variation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

A limiting factor that affects the execution of a project, program, portfolio, or process

A

Constraint

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Name the three constraints in the Triple Constraints model.

A

Cost, Time, Scope

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

The process of tracking, reviewing and reporting the progress to meet the performance objectives defined in the PMP

A

Monitor and Control Project Work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

A technique for determining the cause and degree of difference between the baseline and actual performance

A

Variance Analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

A technique used to evaluate identified options in order to select the options or approaches to use to execute and perform the work of the project

A

Alternative Analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

A financial analysis tool used to determine the benefits provided by a project against its costs

A

Cost-Benefit Analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

An analytical technique used to determine the basic underlying reason that causes variance or a defect or a risk.

A

Root Cause Analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

An analytical technique that uses mathematical models to forecast future outcomes based on historical results

A

Trend Analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Estimates or predictions of conditions and events in the project’s future based on information and knowledge available at the time the schedule is calculated

A

Schedule Forecasts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Analyzing cost status relative to cost baseline, to determine whether cost performance is still within tolerable limits

CPI, EAC, and CV may be used when EVM is employed)

A

Cost Forecasts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

A methodology that combines scope, schedule, and resource measurements to assess project performance and progress

A

Earned Value Management

17
Q

Purpose being to monitor the status of the project to update project progress and manage changes to the schedule baseline

A

Control Schedule

18
Q

Purpose being to monitor the status of the project and product scope, and manage changes to the scope baseline

A

Control Scope

19
Q

Purpose being to review all change requests, approve changes and manage changes to deliverables, OPAs, project documents, and the PMP

A

Perform Integrated Change Control

20
Q

Purpose being to track, review, and report the progress to meet the performance objectives defined in the PMP

A

Monitor and Control Project Work

21
Q

Analyzes schedule progress relative to schedule baseline to determine whether schedule performance is still within tolerable limits

A

Schedule Variance (SV)

22
Q

Process of reviewing all change requests;

approving changes and managing changes to deliverables, project documents, and the PMP;

and communicating the decisions

A

Perform Integrated Change Control

23
Q

A component of the PMP that establishes the change control board, documents the extent of its authority, and describes how the change control system will be implemented.

A

Change Management Plan

24
Q

A formally chartered group responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project, and for recording and communicating such decisions

A

Change Control Board (CCB)

25
Q

A set of procedures that describes how modifications to the project deliverables and documentation are managed and controlled

A

Change Control System

26
Q

Manual or automated tools to assist with change and/or configuration management.

At a minimum, the tools should support the activities of the CCB

A

Change Control Tools

27
Q

A collection of procedures used to track project artifacts and monitor and control changes to these artificats

A

Configuration Management System

28
Q

Configuration Management activity:

Selection and identification of a configuration item.

A

Identification

29
Q

Configuration Management activity:

Information is recorded and reported as to when appropriate data about a configuration item should be provided.

A

Status accounting

30
Q

Configuration Management activity:

Comparison of requirements with the results of tests and analyses.

A

Verification and audit