Planning: Cost Management Flashcards

1
Q

The process of defining how the project costs will be estimated, budgeted, managed, monitored, and controlled

A

3.11 Plan Cost Management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

A component of a project or program management plan that describes how cost will be planned, structured, and controlled.

A

Cost Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

A technique used to evaluate identified options in order to select the options or approaches to use to execute and perform the work of the project.

A

Alternative Analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

A methodology that combines scope, schedule, and resource measurements to assess project performance and progress.

A

Earned Value Management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

The measure of work performed expressed in terms of the budget authorized for that work.

A

Earned Value (EV)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

The expected total cost of completing all work expressed as the sum of the actual cost to date and the estimate to complete.

A

Estimate at Completion (EAC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

The expected cost to finish all the remaining project work.

A

Estimate to Complete (ETC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

The process of developing an approximation of the monetary resources needed to complete project work.

A

3.12 Estimate Costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

All costs incurred over the life of the product by investment in preventing nonconformance to requirements, appraisal of the product or service for conformance to requirements, and failure to meet requirements.

A

Cost of Quality (CoQ)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Techniques used to select a course of action from different alternatives.

A

Decision-Making Techniques

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Expenses that are not dependent on the level of goods or services produced by the business. They tend to be time-related, such as rents being paid per month.

A

Fixed costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Expenses that change in proportion to the activity of a business. When activity is decreased, less raw material is used, so spending for raw materials falls.

A

Variable costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

A cost that can be directly related to producing specific goods or performing a specific service.

Ex: wages of an employee engaged in producing a product

A

Direct costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Costs that are not directly attributable to a particular project, such as heat and light (overhead).

A

Indirect costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

-25% to +75%

initial cost estimate range of accuracy

typically used during Initiation when details are not yet developed

A

Rough Order of Magnitude

(Estimating terminology)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

-5% to +10%

A

Definitive Estimate

(Estimating terminology)

17
Q

Prevention and appraisal costs

A

Cost of Conformance

18
Q

Internal and external failure costs

A

Cost of Non-conformance

19
Q

Formula for BETA Distribution (PERT)

A

[Optimistic + (4 x Most Likely) + Pessimistic] / 6

20
Q

Formula for Triangular Distribution

A

[Optimistic + Most Likely + Pessimistic] / 3

21
Q

Formula for Range of the Estimates

A

Expected Activity Cost +- Activity Standard Deviation

22
Q

Purpose bring To develop an approximation of the monetary resources needed to complete project activities.

A

Estimate Costs process

23
Q

Purpose being To aggregate the estimated costs of individual activities or work packages to establish an authorized cost baseline.

A

Determine Budget process

24
Q

What includes the quantitative assessments of the probable costs required to complete the project work?

A

Activity Cost Estimates

25
Q

The process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline.

A

Determine Budget

26
Q

A component of the project management plan that describes how project resources are acquired, allocated, monitored, and controlled.

A

Resource Management Plan

27
Q

A repository in which outputs of risk management processes are recorded.

A

Risk Register

28
Q

Summing the lower-level cost estimates associated with the various work packages for a given level within the project’s WBS or for a given cost control account.

Process of rolling up costs through each level of the WBS

A

Cost Aggregation

29
Q

Documents and data on prior projects include project files, records, correspondence, closed contracts, and closed projects.

A

Historical Information

30
Q

Using parametric or analogous estimate models based on past experiences can aid in predicting total project costs.

A

Historical Information Review

31
Q

The process of comparing the planned expenditure of project funds against any limits on the commitment of funds for the project to identify any variances between the funding limits and the planned expenditures.

A

Funding Limit Reconciliation

32
Q

The approved version of the time-phased project budget, excluding any management reserves, which can be changed only through formal change control procedures and is used as a basis for comparison to actual results.

A

Cost Baseline

33
Q

Forecast project costs to be paid that are derived from the cost baseline for total or periodic requirements, including projected expenditures plus anticipated liabilities.

A

Project Funding Requirements

34
Q

What is the difference between the Cost Baseline and Project Budget.

A

Cost Baseline does not include Management Reserves, and Project Budget includes everything.