M&C: Cost Management Flashcards
The process of monitoring the status of the project to update project budget and manage changes to the cost baseline
Control Costs
Budgeted value of work planned to be done
Planned Value (PV)
Budgeted value of work actually completed
Earned Value (EV)
Actual cost of work completed
Actual Cost (total) (AC)
Total cost baseline +/- approved changes
Budget at Completion (BAC)
Updated total cost forecast (based on progress)
Estimate at Completion (EAC)
Expected costs remaining (now until end)
Estimate to Complete (ETC)
Expected Variance over/under budget
Variance at Completion (VAC)
The amount of budget deficit or surplus at a given point in time, expressed as the difference between the earned value and the actual cost
Negative (bad)
Positive (good)
Zero (on target)
Cost Variance
A measure of schedule performance expressed as the difference between the earned value and the planned value
Negative (bad)
Positive (good)
Zero (on target)
Schedule Variance
A measure of the cost efficiency of budgeted resources expressed as the ratio of EV to actual cost
Under 1 (bad)
Over 1 (good)
1 (on target)
Cost Performance Index
Formula for Cost Variance
EV - AC
Formula for Schedule Variance
EV - PV
Formula for Cost Performance Index
EV / AC
A measure of schedule efficiency expressed as the ratio of EV to PV
Under 1 (bad)
Over 1 (good)
1 (on target)
Schedule Performance Index