Plan Projects Flashcards
True or false: Most projects begin with blueprints.
True.
Which of the following best describes what project specifications are?
a. A book about project details
b. Information about building components to be installed
c. The official document that states a specific construction activity has been approved
d. A detailed description of the work, materials, and techniques that should be used to complete the work
d. A detailed description of the work, materials, and techniques that should be used to complete the work.
What components are commonly detailed in a schedule?
a. Flooring
b. Interior finishes
c. Roofing material
d. Doors and windows
d. Doors and windows
True or false: Most construction projects do not require a permit.
False.
True or false: Permits can usually be issued with little notice.
False.
Before any work commences, what document should be completed at the job site?
A work site safety survey.
If a change in the original scope of work arises, what form should be filed?
Change order.
True or false: Scheduling with all trades must be part of the project planning.
True.
Why are permits required for certain construction-related jobs?
For safety concerns.
Why is it important to plan for all tools and equipment needed for a job?
a. To be efficient
b. To be cost effective
c. So time is not wasted
d. All of the above
d. All of the above.
What is required to plan the inventory of a project, in addition to security, storage, and
delivery?
Labelling.
Once a project is complete, what drawing should be created?
As-built drawing.
If there is an unclear aspect of a project, what document can be used for clarification?
Request for information.
True or false: All workers and supervisors must take care to ensure safety practices are in place at every stage of handling different materials.
True.
Why is the storage and accessibility of materials important?
a. So the material is well organized
b. So the material will be secured properly
c. So the material can be accessed when needed
d. All of the above
d. All of the above.
True or false: Proper timing and sequencing of material deliveries does not affect efficiency.
False
What is essential to check when transporting materials?
The load is secure.
True or false: Labels may contain information about the safe transporting of a product.
True.
Which of the following products requires controlled disposal?
a. Lumber
b. Plastics
c. Asbestos
d. Scrap metal
Asbestos.
True or false: Efficiency when selecting material-handling procedures is not important.
False.
True or false: Asbestos is found in many building products.
True.
Who sets regulations on handling hazardous materials in NS?
?
What is the best storage solution for a long-term project?
Portable container.
When shipping a load of painted railings to a job site, what should be considered?
a. Make sure the paint is protected properly.
b. Make sure the railings are scheduled to arrive on site.
c. Make sure the railings are secured properly in the truck.
d. All of the above.
d. All of the above.