Non-Class 120 VAC Instrument Power (NN) Flashcards

1
Q

What are the normal/alternate power supplies for NNN-D11?

A

Normal - NHN-M13
Alt - PHA- M31

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the normal/alternate power supplies for NNN-D12?

A

Normal - NHN-M10
Alternate - PHB-M32

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Are NNN-D11 and 12 grounded or ungrounded?

A

ungrounded with ground detection system

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the normal/alternate power supplies for NNN-D15?

A

Normal - NHN-M06
Alternate - NHN-M19 (SIAS LS)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the normal/alternate power supplies for NNN-D16?

A

Normal - NHN-M10
Alternate - NHN-M20 (U1/U2) (SIAS LS) or Unit 3- PHB-M38

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Are NNN-D15 and D16 grounded or ungrounded?

A

grounded

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Which NNN panels do you lose on a SIAS?

How do we get them back?

A

NNN-D15 and D16

reset at LC (MCC feed breaker) after DG loads the bus

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the purpose of NN system?

A

Supply 120VAC power to:

Non-essential reactor auxiliary control instrumentation (D11/D12)

Balance of plant loads (D15/D16)

Provide by automatic transfer, an alternate regulated power supply when the normal power supply is lost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

When does the NNN static transfer switch automatically switch to the emergency power source?

When does the alarm come in?

A

<90 volts (power seeking switch)

<100 volts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Will the NN static transfer switch automatically transfer back to the normal power source if it is on the alternate source and loses power?

A

yes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What could bring in this alarm?

A

This alarm window (1C11B) warns the operator of one of the following
conditions on the distribution panel:
* Ground
* Undervoltage (100 VAC)
* Breaker overload trip (main feed or load breakers)

Automatic Actions:
If the transfer switch is selected for auto, NNN-D11 will transfer to the
backup power supply on an undervoltage condition on the normal supply.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What could bring in this alarm?

A

This alarm window (1C12B) warns the operator of one of the following
conditions on the distribution panel:
* Ground
* Undervoltage (100 VAC)
* Breaker overload trip (main feed or load breakers)

Automatic Actions:
If the transfer switch is selected for auto, NNN-D12 will transfer to the
backup power supply on an undervoltage condition on the normal
supply.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What could bring in this alarm?

A

This alarm window (1C11C) warns the operator of one of the following
conditions on the distribution panel:
* Undervoltage (100 VAC)
* Breaker overload trip (main feed or load breakers)

Automatic Actions:
If the transfer switch is selected for auto, NNN-D15 will transfer to the
backup power supply on an undervoltage condition on the normal
supply.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What could bring in this alarm?

A

This alarm window (1C12C) warns the operator of one of the following
conditions on the distribution panel:
* Undervoltage (100 VAC)
* Breaker overload trip (main feed or load breakers)

Automatic Actions:
If the transfer switch is selected for auto, NNN-D16 will transfer to the
backup power supply on an undervoltage condition on the normal
supply.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly