Mod 12 Proj Stakeholder Mgmt (33) Flashcards
1) Paul is developing the stakeholder management strategy for his project. Which of the following would be an appropriate tool or technique to use?
a. Stakeholder analysis matrix
b. Monte Carlo simulation
c. Stakeholder register
d. Issue log
a. Stakeholder analysis matrix
Correct. The best answer choice is A. The stakeholder analysis matrix is a tool and technique used in the Identify Stakeholders process
2) Which of the following steps of analyzing stakeholders involves considering stakeholder reactions to various situations?
a. Identify advocates
b. Classify stakeholders
c. Identify stakeholders
d. Assess support
d. Assess support
Considering how each stakeholder would react in various situations will allow you to determine the best way to influence them to enhance their support for your project and minimize any negative influence they might exert.
3) All the following are important actions to take to keep your stakeholders satisfied except
a. Clarify and resolve issues in a timely manner.
b. Address stakeholder concerns before they escalate.
c. Actively manage stakeholder expectations.
d. Make sure they receive team member status reports weekly.
d. Make sure they receive team member status reports weekly.
Not all stakeholders should receive status or progress reports. Follow the Communications Management plan.3) All the following are important actions to take to keep your stakeholders satisfied except
4) Before Duane’s project team begins the planning work of the project, they created two documents. The first of these was the project charter. What was the other one?
a. Project management plan
b. Stakeholder register
c. Risk register
d. WBS
b. Stakeholder register
The best answer choice is B. The Initiating Process Group contains only two processes: Develop Project Charter and Identify Stakeholders. The outputs of those processes are the project charter and the stakeholder register.
5) Which input records information on stakeholder identification information and their category?
a. Enterprise environmental factors
b. Stakeholder register
c. Stakeholder management plan
d. Lessons learned
You Answered Correctly!
Correct. The stakeholder register lists stakeholder identification information and its category.
b. Stakeholder register
Correct. The stakeholder register lists stakeholder identification information and its category.
6) Which of the following is a goal of project stakeholder management?
a. To evenly distribute work among all stakeholders
b. To discipline ineffective stakeholders
c. To engage stakeholders in project decisions and execution
d. To conceptualize a project that will involve stakeholders
c. To engage stakeholders in project decisions and execution
Correct. Ultimately, the goal of project stakeholder management is to maintain stakeholder satisfaction during the execution of your project, and the ability to maintain this satisfaction relates to engaging stakeholders in project decisions and execution.
7) The classification of stakeholders based on their power, urgency, and legitimacy is a product of which of the following
a. Stakeholder matrix
b. Stakeholder register
c. Salience model
d. Power/influence grid
c. Salience model
Correct. The best answer choice is C. The salience model is used to classify stakeholders based on their power, urgency, and legitimacy.
8) Which stakeholder categories would be appropriate for a project sponsor?
a. Observer, supporter
b. Driver, resistor
c. Driver, advocate
d. Supporter, neutral
c. Driver, advocate
Correct. The sponsor has the authority to determine the direction of the project, and as a project champion, advocate for the project.
9) During the life cycle of the project, Robert has been devoting a lot of time to managing stakeholder engagement using active listening and trust building. These are examples of which of the following?
a. Lessons learned
b. Communication management
c. Conflict resolution
d. Interpersonal skills
d. Interpersonal skills
The best answer choice is D because active listening and trust building are considered interpersonal skills.
10) Project team members are also considered stakeholders in the project. Of the following processes, which one is not included in the Project Human Resource Management knowledge area?
a. Acquire Project Team
b. Develop Project Team
c. Identify Stakeholders
d. Manage Project Team
c. Identify Stakeholders
Correct. The best answer choice is C because it is the only process not included in the Project Human Resource Management knowledge area.
11) Which of the following best describes the process of Control Stakeholder Engagement?
a. Overseeing the relationships of stakeholders and adjusting tactics and plans for engaging stakeholders
b. Communicating with stakeholders to meet their needs and expectations, and addressing issues as they arise
c. Developing appropriate management strategies to effectively engage stakeholders throughout the project life cycle
d. Identifying the people, groups, or organizations that could impact, or be impacted by a project.
a. Overseeing the relationships of stakeholders and adjusting tactics and plans for engaging stakeholders
Control Stakeholder Management is the process of monitoring overall project stakeholder relationships and adjusting strategies and plans for engaging stakeholders.
12) Discussing needs and expectations with stakeholders, addressing issues, and fostering engagement are aspects of
a. Controlling stakeholder engagement
b. Identifying stakeholders
c. Planning stakeholder engagement
d. Managing stakeholder engagement
d. Managing stakeholder engagement
Managing stakeholder engagement is the process of communicating and working with stakeholders to meet their needs/expectations, address issues as they occur, and foster appropriate stakeholder engagement in project activities throughout the project life cycle.
13) Which of the following would not be considered an input to the Manage Stakeholder Engagement process?
a. Issue log
b. Change log
c. Stakeholder management plan
d. Organizational process assets
a. Issue log
Correct. The best answer choice is A. All of the choices listed are inputs to this process except the issue log, which is an output.
14) Melody is working with 30 key stakeholders in a highly complex architectural project. These stakeholders each have varying degrees of architectural, design, and engineering experience, and each has his or her own opinion of how the project should be executed to achieve the final result. In addition, several of the stakeholders have experience in procurement and are suggesting potential vendors for various aspects of the procurement needs on the project. Because of this difference in opinion, it is becoming increasingly difficult for Melody to resolve issues related to all stakeholders all the time. In an effort to address this situation, Melody has established three project coordination managers and assigned a set of 10 stakeholders to each to manage their expectations. Melody has also provided each group manager with a document consisting of the approach to maintain and increase the support of stakeholders and to manage the stakeholder engagement. In this scenario, what information has Melody provided to her stakeholder group managers?
a. Stakeholder management plan
b. Project management plan
c. Stakeholder register
d. Procurement management plan
You Answered Correctly!
Correct. The best answer choice is A. The information Melody has provided represents a management plan her group managers can use to manage the stakeholder expectations.
a. Stakeholder management plan
Correct. The best answer choice is A. The information Melody has provided represents a management plan her group managers can use to manage the stakeholder expectations.
15) Connie is examining the work performance data on her project. She will use this as an input to which of the following processes?
a. Control Stakeholder Engagement
b. Plan Stakeholder Management
c. Manage Project Team
d. Control Communications
You Answered Correctly!
Correct. The best answer choice is A because work performance data is an input to Control Stakeholder Engagement.
a. Control Stakeholder Engagement
Correct. The best answer choice is A because work performance data is an input to Control Stakeholder Engagement.