M6 Proj Cost Mgmt (49) Flashcards
1) Tim is working on the cost estimate for his project. Because he is in the early phase of this project, he will develop a Rough Order of Magnitude (ROM) estimate. What is the expected degree of accuracy?
a. –25% to +75%
b. –5% to +10%
c. –25% to +25%
d. –50% to +25%
a. –25% to +75%
The best answer choice is A. The ROM typically varies between a –25% and a +75% accuracy.
2) You need to determine how well your project is progressing from a cost standpoint. Your have determined that your actual cost to this point in time is $150,000 and your Earned Value is $135,000. Which of the following represents your Cost Performance Index?
a. 0.9
b. 1.1
c. $15,000
d. $135,000
a. 0.9
The best answer choice is A. Using the formula CPI = EV / AC, the resulting Cost Performance Index is 0.9, indicating that the project is over planned cost at this point in time.
3) Establishing policies, procedures, and documentation for planning, managing, expending, and controlling project costs are elements of the process known as
a. Plan Cost Management
b. Project Integration Management
c. Project Time Management
d. Select Financial Metrics
a. Plan Cost Management
Plan Cost Management is the process that establishes the policies, procedures, and documentation for planning, managing, expending, and controlling project costs.
4) Which of the following are required in order to calculate the EAC forecast if future work will be performed at the budgeted rate?
a. BAC, EV, and AC
b. BAC, PV, and AC
c. BAC, EV, and PV
d. EAC, EV, and PV
a. BAC, EV, and AC
The best answer choice is A. The formula is EAC = AC + BAC – EV.
5) A type of estimate done in the beginning of a project with a range of –25% to +75% is
a. Rough Order of Magnitude
b. Budgetary
c. Engineering
d. Definitive
a. Rough Order of Magnitude
This measurement band can differ by industry, but it is a standard generic rough order of magnitude range.
6) Which of the following is used to compare actual project progress with planned progress?
a. Cost of Quality
b. Total Quality Management
c. Earned Value Management
d. Progressive elaboration
c. Earned Value Management
The best answer choice is C. Earned Value Management (EVM) is a methodology combining scope, schedule, and resource measurements to assess actual project performance and progress in comparison to planned progress at a specific point in time.
7) Your current Earned Value on your project is $360,000 and you have calculated the SPI at 0.8. What is your Planned value at this point?
a. $360,000
b. $480,000
c. $450,000
d. $288,000
c. $450,000
The best answer choice is C. SPI = EV / PV. In this scenario, we would need to divide the Earned Value by the SPI in order to calculate the Planned value.
8) Dena is managing a small project for a computer software development firm. The project is about half finished, and she is calculating the estimate at completion. From the following equations, which one should Dena use if she feels the remaining work will be accomplished at the planned rate.
a. EAC = AC + BAC – EV
b. EAC = BAC / CPI
c. EAC = AC + Bottom‐up ETC
d. EAC = AC + [(BAC – EV) / (CPI × SPI)]
a. EAC = AC + BAC – EV
The best answer choice is A. If future work is expected to be accomplished at the planned rate, the estimate at completion can be calculated as Actual Cost plus budget at completion minus earned value.
9) Which is an example of an indirect cost?
a. Costs for purchasing supplies needed to complete a project
b. Expenses for traveling to the project site
c. Rent paid for your home office space
d. Payments to contractors hired to work on a project
c. Rent paid for your home office space
Indirect costs are those costs not directly attributable to a project, such as overhead, management salaries, and so on.
10) Curtis is calculating the variance at completion on his project. If his budget at completion is $250,000 and his estimate at completion is $280,000, what is his variance at completion?
a. $30,000
b. –$30,000
c. $530,000
d. 0.89
b. –$30,000
The best answer choice is B. VAC = BAC – EAC. Because the BAC is $250,000 and the EAC is $280,000, this results in a negative $30,000 VAC.
11) Which of the following choices are considered components of the schedule performance index?
a. Leads and lags
b. Critical Path Method
c. Earned Value and Planned value
d. Earned Value and Actual Cost
c. Earned Value and Planned value
The best answer choice is C. Schedule performance index is the ratio of Earned Value to Planned value. The formula is SPI = EV / PV.
12) Parametric, analogous, and bottom‐up are estimating tools and techniques that are used in which of the following processes?
a. Plan Cost Management
b. Determine Budget
c. Estimate Costs
d. Control Costs
c. Estimate Costs
The best answer choice is C because the estimating techniques listed are tools and techniques of the Estimate Costs process.
13) Don is managing a project that requires close supervision because of the client’s directive that it not go over budget. Don has determined the Earned Value to be $450,000. The Actual Cost is $425,000. What can Don conclude based on these numbers?
a. The project is $25,000 over budget
b. The project is $25,000 under budget
c. The project only has $25,000 left in the budget
d. The cost variance is 1.06
b. The project is $25,000 under budget
The best answer choice is B. The Cost Variance equation is EV – AC. In this case, because Actual Cost is less than Earned Value, the project is $25,000 under budget.
14) Estimating costs is the process of determining the total cost for completing the project, and the accuracy of these estimates will increase as the project progresses. While working on a cost estimation for your new project, you have been asked to provide a Rough Order of Magnitude (ROM). What is the expected degree of accuracy using this type of estimate?
a. –10% to +25%
b. –50% to +50%
c. –5% to +10%
d. –25% to +50%
b. –50% to +50%
The best answer choice is B because ROM estimates typically vary by + or – 50%
15) The project budget is created after the Estimate Costs process. Which of the following is NOT a technique used to determine the project budget?
a. Cost aggregation
b. Reserve analysis
c. Historical data
d. Resource requirements
d. Resource requirements
Resource requirements is not a technique used to determine the project budget. Instead, funding limit reconciliation is.
16) The estimate at completion for your IT project is $125,000. At this point in the project life cycle, your actual cost is $90,000. What is your estimate to complete, assuming is proceeding on plan?
a. $35,000
b. $125,000
c. $215,000
d. $90,000
a. $35,000
The best answer choice is A. Estimate to Complete (ETC) can be calculated by subtracting the Actual Cost (AC) from the Estimate at Completion (EAC). The formula is ETC = EAC – AC.
17) When estimating costs, project budgets typically include management reserves as well as contingency reserves. Select the option below that is true regarding management reserves.
a. They are seldom included in the funding requirements
b. They are included to cover unapproved changes
c. They are a factor in determining Earned Value
d. They are not part of the cost baseline
d. They are not part of the cost baseline
The best answer choice is D because management reserves are not included when creating the cost baseline.
18) Max is managing a large construction project for senior living suites. His team has completed a variance analysis, and they have calculated several cost performance indicators including Cost Performance Index (CPI) and Cost Variance (CV). When they completed the calculations, they discovered a significant deviation between the actual performance and the cost performance baseline. Once this variance is detected, what should Max do immediately to restore the necessary cost performance?
a. Request more funding
b. Schedule a team meeting
c. Initiate a corrective action
d. Compress the schedule
c. Initiate a corrective action
The best answer choice is C. A corrective action is the first step Max should take in order to restore the necessary cost performance.
19) Which document sets out the format and establishes the activities and criteria for planning, structuring, and controlling the project’s cost?
a. Activity cost estimates
b. Basis of estimates
c. Cost management plan
d. Spend plan
c. Cost management plan
The cost management plan describes the structure and criteria that will be used for cost planning, estimating, budgeting, and reporting.