M8 Proj Human Resource Mgmt (32) Flashcards
1) Networking is used for developing the Human Resource Management Plan in order to
a. Determine the appropriate motivations and rewards for team members
b. Determine the number of labor units a team member will be working
c. Define the licenses, skills, and training needs for each team member
d. Gain expertise for determining the most effective organizational structure
d. Gain expertise for determining the most effective organizational structure
Networking is a constructive way to understand political and interpersonal factors that will impact the effectiveness of various staffing management options.
2) Walter is referencing material known as the Tuckman team development ladder. Walter is learning that one phase of team development involves the team beginning to address the project work, the technical decisions, and project management approach. If team members are not collaborative and open to differing ideas, the environment can become counterproductive. Which phase does this describe?
a. Performing
b. Storming
c. Norming
d. Forming
b. Storming
The best answer choice is B. The question defines the situation typically existing during the Storming phase.
3) Which of the following would be a responsibility of a sponsor?
a. Approves the project charter
b. Develops plans to achieve project objectives
c. Provides leadership for particular aspects of the project
d. Assists in identifying and responding to risk
a. Approves the project charter
A sponsor provides financial resources for a project and approving the project charter is one of the sponsor’s responsibilities.
4) Chuck is managing a virtual project team. He is trying to determine the most important factors for success. Which of the following should Chuck put at the top of his list?
a. Team building
b. Resource breakdown structure
c. Communication
d. Risk register
c. Communication
The best answer choice is C. Communication is one of the most important factors for success in managing a virtual team.
5) Which is the common order of the stages of team development?
a. Forming, norming, storming, adjourning, performing
b. Storming, norming, performing, adjourning
c. Forming, storming, norming, performing, adjourning
d. Performing, norming, adjourning, storming, norming
c. Forming, storming, norming, performing, adjourning
The stages of team development are commonly in the order of forming, storming, norming, performing, and adjourning.
6) If you want to create a matrix that shows the intersection of the organizational breakdown structure (OBS) and the work breakdown structure (WBS), you would create
a. A responsibility assignment matrix
b. A resource histogram
c. A resource breakdown structure
d. A roles and responsibilities chart
a. A responsibility assignment matrix
The responsibility assignment matrix shows the intersection of the OBS and the WBS.
7) Jan and Becky are arguing about who should have the final sign‐off on a component of a deliverable. What stage of team development are they likely in?
a. Forming
b. Storming
c. Norming
d. Performing
b. Storming
Jan and Becky are storming. They are experiencing conflict as they figure out how to work together.
8) Your project team is having some difficulties maintaining clear communications because they are scattered throughout the city in various offices in the numerous buildings your company owns. You have initiated a request to have additional office space finished out in the building where the majority of the team is located so that the remaining team members can be relocated into a central location. Which of the following describes this change?
a. Collaboration
b. Virtual team
c. Colocation
d. Manage communications
c. Colocation
The best answer choice is C because the situation described in the question involves colocation.
9) Hillary is working on a plan to improve the skills of her team members. She is also looking at ways to reduce the exceptionally high turnover rate while providing options for increasing the overall knowledge of her team members. Which of the following processes is Hillary working on?
a. Manage Project Team
b. Team Building
c. Develop Project Team
d. Plan Human Resource Management
c. Develop Project Team
The best answer choice is C. Hillary’s activities fall into the Develop Project Team process.
10) Retreating from a potential conflict situation describes which conflict management style?
a. Smoothing
b. Avoiding
c. Accommodating
d. Compromising
b. Avoiding
Avoiding is retreating from an actual or potential conflict situation.
11) You are a team member on a new project team consisting of highly qualified security experts and have been tasked with assigning the various work packages on the WBS. However, your project manager has changed some of your assignments, and you have distributed the new assignments to the team. Several team members have come to you to complain that the more difficult tasks have been assigned to the women on the team, and the men have received the easier work packages. At the same time, some of them male team members are complaining that they would like some of the more daunting tasks that could provide a learning experience and enhance their resumes. When you bring this up with your project manager, he simply tells you that he is managing the team and you will leave the assignments the way he determined. Which of the following describes the conflict resolution method the project manager is using?
a. Forcing
b. Compromising
c. Accommodating
d. Collaborating
a. Forcing
The best answer choice is A because the project manager is pushing his personal viewpoint on others by using the power of his position.
12) Sandi is managing a project in a matrix organization. One of her team members has completed his portion of the project. What should Sandi’s next step be?
a. Assign the team member to a new project
b. Place a staff evaluation in the team members performance appraisal
c. Allow the team member to remain on the project team
d. Ask the team member to assist in another work package
b. Place a staff evaluation in the team members performance appraisal
The best answer choice is B when a team member finishes his or her assignment on the project and completes the work assigned to them.
13) Which of the following documents would the project manager use to determine training needs, safety concerns, and procedures for releasing team members at the end of the project?
a. Resource requirements
b. Resource calendars
c. Staffing management plan
d. Resource breakdown schedule
c. Staffing management plan
The best answer choice is C because it contains the information the project manager needs as described in the question.
14) Sandra is a new project manager working with her first project team. Because this is her first team, she wants to make every effort to be a good team leader and have her project be successful. She realizes how important good communication is to project success. Which of the following would have the greatest positive impact on assuring good team communication?
a. Ground rules
b. Rewards and recognition
c. Compromising
d. Colocation
d. Colocation
The best answer choice is D. Colocation can be a major contributing factor in enhancing and maintaining good team communications.
15) When acquiring the team, ________ is one input derived from the Human Resource Management Plan.
a. Team performance assessment
b. Issue log
c. Hierarchy of Needs
d. Responsibility Assignment Matrix
d. Responsibility Assignment Matrix
Much of the information from the Human Resource Management plan will be used when acquiring the team, including the Responsibility Assignment Matrix.